SOR Item No. Description Unit No. L (m) B (m) D (m) Qty. Rate Amount
Earth work in excavation by mechanical means (Hydraulic excavator) /
manual means in foundation trenches or drains (not exceeding 1.5 m in width
1 2.8/16 or 10 sqm on plan) including dressing of sides and ramming of bottoms, lift
upto 1.5 m, including getting out the excavated soil and disposal of surplus
excavated soil as directed, within a lead of 50 m.
B. Top Slab
Centering and shuttering including strutting, propping etc.and removal of form
10 20.1.3/209
for:Formwork - For Foundation Etc.
Side of Slab m2 2 115 0.15 34.50
Bot. of Slab m2 1 115 1.00 115.00
Total 149.500 204.30 30,542.85
TOTAL = 755,033.31