You are on page 1of 2

DIMENSION CONSULTANCY BHOPAL.

DETAILED ESTIMATE OF THE CONSTRUCTION OF THE RETAINING WALL AT THE PUNA KHADIS TALAB
WARD NO. 9/11 CHICHOLI, DISTRICT- BETUL. (MP)
ESTIMATE FOR RETAINING WALL
SOR ITEM
S.N. DESCRIPTION OF ITEM UNIT NOS LENGTH BREADTH DEPTH QUANTITY RATE AMMOUNT
NO.

1 vol(III) 12.1 Earthwork in excavation of foundation of structures with


all lifts & lead upto 1000 meters as per drawing and
technical specification, including setting out, construction
of shoring and bracing, removal of stumps and other
deleterious matter,dressing of sides and bottom as per
relevant clauses of section 300 & 2100 in.

(i) soil (A) By Manual Means


(I) upto 3 m depth. cum 1 256 3.75 1.2 1152.00 181 208512.0
v Extra rates for quantities of Excavation, executed in /or 20% of
under water, including pumping out water as required. the
(The extra percentage rate is applicable in respect of each rate of
item but limited to quantities of work executed in these the
difficult conditions). item.
(I) upto 3 m depth. cum 1 256 3.75 1.2 1152.00 36.2 41702.4

2 vol(III) 12.5 12.5 Providing and laying Plain/Reinforced cement


concrete in open foundation including form work
shuttering etc. complete as per drawing and technical
specification sand as per relevant clauses of sections
1500,1700&2100 with .
a) PCC Grade M15 cum 1 256 3.8 0.1 97.28 4744 461496.3
f) RCC Grade M25
below GL
rectangle portion (hill+toe) 1 256 3.75 0.22 211.20
stem cum 1 256 0.3598 92.11
above GL
stem cum 1 256 0.5342 136.76
total concrete total 440.06 5701 2508804.9

5 12.24 12.24 Supplying, fitting and placing HYSD bar


reinforcement in foundation complete as per drawing and
technical specifications and as per relevant clauses of
sections 1600.
@120 kg/ cum
52807.68 tonne 52.81 59947 3165662.0

6 vol(II) 19.1 19.1 Centering and shuttering including strutting


,propping stretching etc. complete for and removal of
form work by sheet plate or plywood shuttering for :
vol (II)19.1.1 19.1.1Foundations, footings, bases of columns, etc. For
mass concrete.
rectangle portion sqm 2 256 0.22 112.64
stem (straight vertical) 1 256 0.98 250.88
stem (inclined vertical) 1 256 1 256.00
total 619.52 160 99123.2

7 vol(II)19.1.12 19.1.12Well steining Sqm 438.00


stem above GL (Straight vertical) sqm 1 256 2 512.00
stem above GL (inclined vertical) sqm 1 256 2.05 524.80
total 1036.80 438 454118.4

RETAINING WALL DETAILED ESTIMATE......


DIMENSION CONSULTANCY BHOPAL.

SOR ITEM
S.N. DESCRIPTION OF ITEM UNIT NOS LENGTH BREADTH DEPTH QUANTITY RATE AMMOUNT
NO.
8 Vol(III) 13.8 13.8 Providing weep holes in Brick
masonry/Plain/Reinforced concrete abutment, wing wall
/return wall with 100 mm dia AC/PVC/HDPE pipe,
extending through the full width of the structure with
slope of 1V:20H towards drawing foce.Complete as per
drawing and Technical specifications and as per clause
2706 of specifications.
1.8/sqm ((256*2)/1.8) meter 56.89 173 9841.8

9 vol(III) 13.10 Providing and laying of Filter media with granular


materials/stonecrushed aggregates satisfying the
requirements laid down in clause 2504.2.2.of MORTH
specifications to a thickness of not less than 600 mm with
smaller size to wards the soil and bigger size towards the
wall and provided over the entire surface behind
abutment, wingwall and returnwall to the full height
compacted to a firm condition complete as per drawing
and technical specification.

behind the retaining wall cum 1 256 0.15 2 76.80 1211 93004.8

TOTAL AMMOUNT 7042265.8

RETAINING WALL DETAILED ESTIMATE......