Keystone Infra Private Limited

Name of Work - Construction of New Police Head Quarter at Imphal, Manipur (Phase-II)
Manipur Police Housing Corporation Ltd., Imphal
Sl. Quantity As Calculated Calculated BoQ
Item Description Units Rate
No. Per BOQ Quantity Amount Amount
1 2 3 4 5 6 7 8
1 SH (I) :- Main Building (Block - B )(Ground Floor,1st Floor &
2nd Floor)
2 Earthwork in excavation in foundation trenches or drains including m3 164.00 707.03 701.98 115124.15
dressing of sides and ramming of bottoms including getting out
the excavted soil and disposal od surplus excavated soil as
directed within a lead of 50 m in Hard dense soil.(a) Lift upto 1.5 m
115952.92
3 Filling available excavated earth (excluding rock) in trenches, m3 130.00 235.68 450.00 58500.00
plinth, sides of foundation etc. in layers not exceeding 20 cm.in
depth, consolidating each deposited layer by ramming and
watering lead upto 50 metres lift upto 1.5 metre. 30638.4
4 Filling in plinth with granular material under floors including m3 1007.00 1819.71 2100.00 2114700.00
watering ramming, consolidating and dressing complete. 1832447.97
5 Providing and laying cement concrete works in foundation and m3 8650.00 248.32 243.39 2105298.07
plinth excluding the cost of centering & shuttering in (a) C.C.
1:5:10 (1 cement :5 Kanhaighat coarse sand :10 graded stone
aggrt. 40mm nominal size). 2147968
6 Providing and laying in position specified grade of reinforced m3 14825.00 571.41 570.00 8450263.90
cement concrete, excluding the cost of centering, shuttering,
finishing and reinforcement - All work up to plinth level : (a)1:1:2 (1
cement :1 coarse sand:2 graded stone aggregate 20 mm nominal
size.)
8471153.25
7 Reinforced cement concrete work in walls (any thickness), m3 15820.00 244.29 426.77 6751446.03
including attached pilasters, buttresses, plinth and string courses,
fillets, columns,pillars, piers, abutments, posts and struts etc. up to
floor five level,excluding cost of centering, shuttering, finishing and
reinforcement :(a)1:1:2 (1 cement :1 coarse sand:2 graded stone
aggregate 20 mm nominal size.)

3864667.8
8 Reinforced cement concrete work in beams, suspended floors, m3 15930.00 810.39 1362.21 21700062.17
roofs having slope up to 15° landings, balconies, shelves, chajjas,
lintels, bands, plain window sills, staircases and spiral stair cases
up to floor five level, excluding the cost of centering, shuttering,
finishing and reinforcement (a) 1: 1 : 2 (1 cement :1 Kanhaighat
coarse sand: 2 graded stone aggregate 20 mm nominal size.) (i)
Upto floor five level
12909512.7
9 Steel reinforcement for R.C.C. work including straightening, kg 143.00 297797.51 434207.74 62091706.50
cutting,bending, placing in position and binding all complete.steel
bars. (a) Thermo-Mechanically Treated bars. 42585043.93
10 Providing form work i/c centering & shuttering so as to give a m2 736.00 1218.36 1962.50 1444397.42
rough finish strutting and propping etc. height of propping and
centering below supporting floor to ceiling not exceeding 4m and
removal of the same for insitu reinforced concrete to and plain
concrete work in.(using 12mm shuttering ply)(a) Foundation
footings, bases of columns etc. and mass concrete.

896712.96
11 (b) Columns, pillars, posts and struts (square, rectangular or m2 954.00 1806.74 1662.47 1586000.20
polygon in plan). 1723629.96
12 (c) Sides and soffits of beams, beam haunchings, cantilivers, m2 852.00 2673.93 3072.94 2618147.01
girders, bressumers and lintels not exceeding 1m in depth.
2278188.36
13 (d ) Flat surfaces such as suspended floor, roofs landings and the m2 957.00 3795.44 4632.96 4433739.37
like (i) floors etc. upto 200mm in thickness. 3632236.08
14 (e) Staircases (e/c landing) slopping or stepped soffits including m2 588.00 79.22 465.47 273694.48
risers & stringers etc. 46581.36
15 (f) Edges of slab and breaks in floors and walls (i) Under 20cm m2 235.00 666.06 729.60 171456.00
wide 156524.1
16 (g) Vertical surface such as walls (any thickness), partition and the m2 958.00 481.82 524.70 502662.60
like including attached pilasters, buttresses, plinth and the string
courses and the like
461583.56
17 2nd class (local first class) brick work in foundation and plinth in m3 15326.00 168.18 235.68 3612087.54
cement mortar 1:4 (1 cement : 4 Kanhaighat coarse sand)
2577526.68
18 2nd class (local first class) brick work in superstructure in cement m3 16007.00 0.00
mortar 1:3 (1 Cem: 3 Kanhaighat C/Sand) (a) above plinth level
upto 1st floor level 0
19 (a) Above 1st floor level upto 2nd floor level. m3 16117.00 0.00 0
20 (b) Above 2nd floor level upto 3rd floor level. m3 0.00 0
21 Half brick masonry 2nd class (local first class) in cement mortar m2 0.00
1:3 (1 cement : 3 Kanaighat coarse sand) in superstructure (i)
above plinth level upto 1st floor level. 0
22 (ii) Above 1st floor level upto 2nd floor level m2 0.00 0
23 (iii) Above 2nd floor level upto 3rd floor level m2 0.00 0
24 Providing wood work in frames of doors, windows, c/windows & m3 0.00
other frame and fixed in position.(a)Local best quality Teak wood.

0
Sl. Quantity As Calculated Calculated BoQ
Item Description Units Rate
No. Per BOQ Quantity Amount Amount
25 Providing and fixing 50 mm thick panelled and glazed or panelled m3 0.00
and glazed shutters for doors, windows, c/windows ect. Including
bright finished brass hinges with necessary screws-(a) Local best
quality Teak wood. 0
26 Providing 40x3mm flat iron hold fast 40cm long i/c fixing to frames each 0.00
with 10mm dia bolts, nuts and wooden plugs and embedding to
cement concrete block 30x10 x15cm 1:3:6 (1 cement : 3
Kanaighat coarse sand : 6 stone aggrt. 20mm nominal guage).
0
27 Providing and fixing Brass sliding bolts bright finished or black each 0.00
enamelled with nuts & screws etc. complete. (a) 300 x 16 mm
0
28 P/F Brass Tower bolts with screws & nuts complete,(a) 250x10 each 0.00
mm 0
29 P/F Brass Handles with screws & nuts complete,(a) 125mm each 0.00 0
30 Providing and fixing aluminium hanging floor door stopper, ISI each 0.00
marked, anodised (anodic coating not less than grade AC 10 as
per IS : 1868) transparent or dyed to required colour and shade,
with necessary screws etc. complete.(a) Twin rubber stopper
0
31 Providing and fixing stainless steel ( Grade 304) railing made of kg 0.00
Hollow tubes, channels, plates etc., including welding, grinding,
buffing, polishing and making curvature (wherever required) and
fitting the same with necessary stainless steel nuts and bolts
complete, i/c fixing the railing with necessary accessories &
stainless steel dash fasteners , stainless steel bolts etc., of
required size, on the top of the floor or the side of waist slab with
suitable arrangement as per approval of Engineer-in-charge, ( for
payment purpose only weight of stainless steel members shall be
considered excluding fixing accessories such as nuts, bolts,
fasteners etc.).
0
32 Providing & fixing in position collapsible steel shutters with vertical m2 0.00
channels 20 mm X 10 mm X 2 mm & braced with flat iron
diagonals 20 mm X 5 mm sizes with top & bottom rails of T iron 40
mm X 40 mm X 6 mm with 38 mm dia steel pullets complete with
bolts & nuts, looking arrangement, stoppers, handles i/c applying a
priming coat of red lead paint.

0
33 Providing and laying vitrified floor tiles in different sizes (thickness m2 0.00
to be specified by the manufacturer) with water absorption’s less
than 0.08% and conforming to IS : 15622 of approved make in all
colours and shades, laid on 20mm thick cement mortar 1:4(1
cement: 4 coarse sand) including grouting the joints with white
cement and matching pigments etc., complete.Size of Tile
600x600 mm (Branded Double charged )

0
34 Providing and laying Vitrified tiles in different sizes (thickness to be m2 0.00
specified by manufacturer), with water absorption less than 0.08 %
and conforming to I.S. 15622, of approved make, in all colours &
shade, in skirting, riser of steps, over 12 mm thick bed of cement
mortar 1:3 (1 cement: 3 coarse sand), including grouting the joint
with white cement & matching pigments etc. complete.(a) Size of
Tile 600x600 mm (Double Charged) (i) Branded.

0
35 White ceramic glazed tiles 7.3 mm in flooring, treads or steps & m2 0.00
landing laid on a bed of 12 mm thick cement mortar 1:3 (1
cement:3 coarse sand) finished with flush pointing in white
cement. 0
36 Marble stone slab flooring over 20 mm (average) thick base of m2 0.00
cement mortar 1 : 6 (1 Cement: 6 coarse sand) laid and jointed
with grey cement slurry including rubbing and polishing complete
with -(a) white marble slab 20 mm thick (i) 60 x 90 cm
0
37 Granite stone slab flooring over 20 mm (average) thick base of m2 0.00
cement mortar 1 : 6 (1 Cement: 6 Kanhaighat coarse sand) laid
and jointed with grey cement slurry including rubbing and polishing
complete with -(a) Granite slab 20 mm slab thick (i)Jade Black 60
x 120 cm
0
38 12mm cement plaster 1:4 (1 cement : 4 Kanhaighat Coarse sand). m2 0.00

0
39 15mm cement plaster 1:4 (1 cement : 4 Kanhaighat Coarse sand). m2 0.00

0
40 15 mm cement plaster 1:3(1 cement:3 Kanhaighat Coarse m2 0.00
sand)finished with a floating coat of neat cement. 0
41 Painting on wall with (two coats) of plastic emulsion paint of m2 0.00
approved quality in all shades on new work to give an even shade.
0
42 Providing and applying plaster of paris putty of 2mm thickness m2 0.00
over plastered surface to prepare the surface even and smooth
complete. 0
43 Applying one coat of cement primer of approved quality on wall m2 0.00
surface. 0
44 Finishing wall weather shield paint of approved quality on new m2 0.00
work (three or more coats) to give an even shade. 0
Sl. Quantity As Calculated Calculated BoQ
Item Description Units Rate
No. Per BOQ Quantity Amount Amount
45 Applying ready mixed priming coat pink primer of approved quality m2 0.00
on wood work. 0
46 Painting (two or more coats excluding priming coat) with superior m2 0.00
ready mixed paint for wood work of approved quality in all shades
on new wood work to give an even shade.

0
47 Providing under layer for plinth protection of 75 mm thick m2 0.00
(unconsolidated) of stone aggrt. 40 mm nominal size wall rammed
& consolidated & grouted with fine sand i/c finishing the top of
concrete smooth. 0
48 Providing plinth protection 50 mm thick in cement concrete 1: 3 : 6 m2 0.00
(1 cement : 3 Kanhaighat coarse sand : 6 graded stone aggrt. of
20 mm nominal size) i/c finishing the top surface of concrete
smooth. 0
49 2nd class brick masonary 15x15cm open surface drain in c.m. 1: Rm 0.00
5(1cem : 5 Kanhaighat c/sand) i/c earth excavation 10cm bed
c.c.1: 5 : 10 1cem : 5 Kanhaighat c/sand :10gr.st.aggrt.40mm
n/size i/c 12mm thick cement plaster 1: 3 (1cem : 3 Kanhaighat
Coarse sand) with a floating coat of neat cement inside & outside
as per standard design.
0
50 Providing and fixing false ceiling at all height including providing m2 0.00
and fixing of frame work made of special sections, power pressed
from M.S. sheets and galvanized with zinc coating of 120 gms/sqm
(both side inclusive) as per IS : 277 and consisting of angle cleats
of size 25 mm wide x 1.6 mm thick with flanges of 27 mm flanges
of 20 mm and 30 mm long, the perimeter of ceiling fixed to
wall/partition with the help of rawl plugs at 450 mm centre, with 25
mm long dry wall screws @ 230 mm interval, including fixing of
gypsum board to (i) Fully Perforated Gypsum Plaster Board of
size 1200 x 2400x12.5 mm having approx. 15 % perforated area
with perforation size and pattern as approved by the Engineer-in-
tapered and backed by acoustical tissue with NRC value not less
than 0.60.charge and as per manufacturer's specification, with all 4
side

0
51 Providing and fixing aluminium works for doors windows, m2 0.00
Ventilators and partions both extruded built up standard tubular
sections/ appropriate Z sections and other sections of approved
make conforming to IS:733 and IS:1285, fiixed with rawl plugs and
screws or with fixing clips, or with expansion hold fasteners
including necessary filling up gaps at junctions, at top,bottom and
side with required EPDM rubber/Neoprene gasket etc. Aluminium
snap beading for glazing /panelling, C.P. brass/ Stainless steel
screws, all complete as per architectural drawing and the
directions of Engineer-in-charge.(Glazing and panelling to be paid
for separately):For shutters of doors, windows & ventilators
including, providing and fixing hinges/ pivots and making provision
for fixing of fitting wherever required including the cost of EPDM
rubber/neoprene gasket required (Fittings shall be paid for
separately).(a) Anodised aluminium (anodised transparent or dyed
to required shade according to IS:1868, Minimum anodic coating
of grade

0
52 Providing and fixing glazing in aluminium door, window, ventilator m2 0.00
shutters and partitions etc. with EPDM rubber/ neoprene gasket
etc. complete as per the architectural drawings and the directions
of engineer-incharge . (Cost of aluminium snap beading shall be
paid in basic item): (i) With float glass panes of 4.0 mm thickness
0
53 Providing and fixing aluminium works for partions both extruded m2 0.00
built up standard tubular sections/ appropriate Z sections and
other sections of approved make conforming to IS:733 and
IS:1285,bison board fiixed with rawl plugs and screws or with fixing
clips, or with expansion hold fasteners including necessary filling
up gaps at junctions, at top,bottom and side with required EPDM
rubber/Neoprene gasket etc. Aluminium snap beading for
glazing /panelling, C.P. brass/ Stainless steel screws, all complete
as per architectural drawing and the directions of Engineer-in-
charge.:For shutters of doors, windows & ventilators including,
providing and fixing hinges/ pivots and making provision for fixing
of fitting wherever required including the cost of EPDM
rubber/neoprene gasket required (Fittings shall be paid for
separately).(a) Anodised aluminium (anodised transparent or dyed
to required shade according to IS:1868, Minimum anodic coating
of grade (6mm thick Aluminium grill).

0
54 ELECTRICAL & FIRE FIGHTING 0.00 0
348 SH (III) ; CANTEEN & GYM 0.00 0
Sl. Quantity As Calculated Calculated BoQ
Item Description Units Rate
No. Per BOQ Quantity Amount Amount
349 Earthwork in excavation in foundation trenches or drains including m3 0.00
dressing of sides and ramming of bottoms including getting out
the excavted soil and disposal od surplus excavated soil as
directed within a lead of 50 m in Hard dense soil.(a) Lift upto 1.5 m
0
350 b) Lift above 1.5m upto 3.00m m3 0.00 0
351 Filling available excavated earth (excluding rock) in trenches, m3 0.00
plinth, sides of foundation etc. in layers not exceeding 20 cm.in
depth, consolidating each deposited layer by ramming and
watering lead upto 50 metres lift upto 1.5 metre. 0
352 Filling in plinth with sandy soil under floors including watering m3 0.00
ramming, consolidating and dressing complete with a lead of 50m
0
353 Providing and laying cement concrete works in foundation and m3 8650.00 38.70 26.02 225087.71
plinth excluding the cost of centering & shuttering in (a) C.C.
1:5:10 (1 cement :5 Kanhaighat coarse sand :10 graded stone
aggrt. 40mm nominal size). 334755
354 Providing and laying in position specified grade of reinforced m3 14825.00 92.85 84.36 1250707.42
cement concrete, excluding the cost of centering, shuttering,
finishing and reinforcement - All work up to plinth level : (a)1:1:2 (1
cement :1 coarse sand:2 graded stone aggregate 20 mm nominal
size.)
1376501.25
355 Reinforced cement concrete work in walls (any thickness), m3 0.00
including attached pilasters, buttresses, plinth and string courses,
fillets, columns,pillars, piers, abutments, posts and struts etc. up to
floor five level,excluding cost of centering, shuttering, finishing and
reinforcement :(a)1:1:2 (1 cement :1 coarse sand:2 graded stone
aggregate 20 mm nominal size.)

0
356 Reinforced cement concrete work in beams, suspended floors, m3 0.00
roofs having slope up to 15° landings, balconies, shelves, chajjas,
lintels, bands, plain window sills, staircases and spiral stair cases
up to floor five level, excluding the cost of centering, shuttering,
finishing and reinforcement (a) 1: 1 : 2 (1 cement :1 Kanhaighat
coarse sand: 2 graded stone aggregate 20 mm nominal size.) (i)
Upto floor five level
0
357 Steel reinforcement for R.C.C. work including straightening, kg 143.00 36303.59 7898.08 1129426.03
cutting,bending, placing in position and binding all complete.steel
bars. (a) Thermo-Mechanically Treated bars. 5191413.37
358 Providing form work i/c centering & shuttering so as to give a m2 0.00
rough finish strutting and propping etc. height of propping and
centering below supporting floor to ceiling not exceeding 4m and
removal of the same for insitu reinforced concrete to and plain
concrete work in.(using 12mm shuttering ply)(a) Foundation
footings, bases of columns etc. and mass concrete.

0
359 (b) Columns, pillars, posts and struts (square, rectangular or m2 0.00
polygon in plan). 0
360 (c) Sides and soffits of beams, beam haunchings, cantilivers, m2 0.00
girders, bressumers and lintels not exceeding 1m in depth.
0
361 (d ) Flat surfaces such as suspended floor, roofs landings and the m2 0.00
like (i) floors etc. upto 200mm in thickness. 0
362 (e) Staircases (e/c landing) slopping or stepped soffits including m2 0.00
risers & stringers etc. 0
363 (f) Edges of slab and breaks in floors and walls (i) Under 20cm m2 0.00
wide 0
364 (g) Vertical surface such as walls (any thickness), partition and the m2 0.00
like including attached pilasters, buttresses, plinth and the string
courses and the like 0
365 2nd class (local first class) brick work in foundation and plinth in m3 0.00
cement mortar 1:4 (1 cement : 4 Kanhaighat coarse sand)
0
366 Polygonal rubble masonry/R.R. masonry (uncoursed/ brought to m4 0.00
courses) squared rubble masonry (uncoursed/brought to courses)
with hard stone of approved quality in foundation & plinth in
cement mortar 1:6 (1 cement:6 coarse sand) i/c levelling up with
cement concrete 1:6:12 (1 cement:6 coarse sand:12 stone
aggregate 20 mm nominal size) at plinth level.

0
367 Half brick masonry 2nd class (local first class) in cement mortar m2 0.00
1:3 (1 cement : 3 Kanaighat coarse sand) in superstructure (i)
above plinth level upto 1st floor level. 0
368 (ii) Above 1st floor level upto 2nd floor level m2 0.00 0
369 (iii) Above 2nd floor level upto 3rd floor level m2 0.00 0
370 Providing wood work in frames of doors, windows, c/windows & m3 0.00
other frame and fixed in position.(a)Local best quality Teak wood.

0
371 Providing and fixing 50 mm thick panelled and glazed or panelled m3 0.00
and glazed shutters for doors, windows, c/windows ect. Including
bright finished brass hinges with necessary screws-(a) Local best
quality Teak wood. 0
Sl. Quantity As Calculated Calculated BoQ
Item Description Units Rate
No. Per BOQ Quantity Amount Amount
372 Providing 40x3mm flat iron hold fast 40cm long i/c fixing to frames each 0.00
with 10mm dia bolts, nuts and wooden plugs and embedding to
cement concrete block 30x10 x15cm 1:3:6 (1 cement : 3
Kanaighat coarse sand : 6 stone aggrt. 20mm nominal guage).
0
373 Providing and fixing Brass sliding bolts bright finished or black each 0.00
enamelled with nuts & screws etc. complete. (a) 300 x 16 mm
0
374 P/F Brass Tower bolts with screws & nuts complete,(a) 250x10 each 0.00
mm 0
375 P/F Brass Handles with screws & nuts complete,(a) 125mm each 0.00 0
376 Providing and fixing stainless steel ( Grade 304) railing made of kg 0.00
Hollow tubes, channels, plates etc., including welding, grinding,
buffing, polishing and making curvature (wherever required) and
fitting the same with necessary stainless steel nuts and bolts
complete, i/c fixing the railing with necessary accessories &
stainless steel dash fasteners , stainless steel bolts etc., of
required size, on the top of the floor or the side of waist slab with
suitable arrangement as per approval of Engineer-in-charge, ( for
payment purpose only weight of stainless steel members shall be
considered excluding fixing accessories such as nuts, bolts,
fasteners etc.).
0
377 Providing and laying vitrified floor tiles in different sizes (thickness m2 0.00
to be specified by the manufacturer) with water absorption’s less
than 0.08% and conforming to IS : 15622 of approved make in all
colours and shades, laid on 20mm thick cement mortar 1:4(1
cement: 4 coarse sand) including grouting the joints with white
cement and matching pigments etc., complete.Size of Tile
600x600 mm (Branded Double charged )

0
378 Providing and laying Vitrified tiles in different sizes (thickness to be m2 0.00
specified by manufacturer), with water absorption less than 0.08 %
and conforming to I.S. 15622, of approved make, in all colours &
shade, in skirting, riser of steps, over 12 mm thick bed of cement
mortar 1:3 (1 cement: 3 coarse sand), including grouting the joint
with white cement & matching pigments etc. complete.(a) Size of
Tile 600x600 mm (Double Charged) (i) Branded.

0
379 Marble stone slab flooring over 20 mm (average) thick base of m2 0.00
cement mortar 1 : 6 (1 Cement: 6 coarse sand) laid and jointed
with grey cement slurry including rubbing and polishing complete
with -(a) white marble slab 20 mm thick (i) 60 x 90 cm
0
380 12mm cement plaster 1:4 (1 cement : 4 Kanhaighat Coarse sand). m2 0.00

0
381 15mm cement plaster 1:4 (1 cement : 4 Kanhaighat Coarse sand). m2 0.00

0
382 15 mm cement plaster 1:3(1 cement:3 Kanhaighat Coarse m2 0.00
sand)finished with a floating coat of neat cement. 0
383 Painting on wall with (two coats) of plastic emulsion paint of m2 0.00
approved quality in all shades on new work to give an even shade.
0
384 Providing and applying plaster of paris putty of 2mm thickness m2 0.00
over plastered surface to prepare the surface even and smooth
complete. 0
385 Applying one coat of cement primer of approved quality on wall m2 0.00
surface. 0
386 Finishing wall weather shield paint of approved quality on new m2 0.00
work (three or more coats) to give an even shade. 0
387 Applying ready mixed priming coat pink primer of approved quality m2 0.00
on wood work. 0
388 Painting (two or more coats excluding priming coat) with superior m2 0.00
ready mixed paint for wood work of approved quality in all shades
on new wood work to give an even shade.

0
389 Providing under layer for plinth protection of 75 mm thick m2 0.00
(unconsolidated) of stone aggrt. 40 mm nominal size wall rammed
& consolidated & grouted with fine sand i/c finishing the top of
concrete smooth. 0
390 Providing plinth protection 50 mm thick in cement concrete 1: 3 : 6 m2 0.00
(1 cement : 3 Kanhaighat coarse sand : 6 graded stone aggrt. of
20 mm nominal size) i/c finishing the top surface of concrete
smooth. 0
391 2nd class brick masonary 15x15cm open surface drain in c.m. 1: Rm 0.00
5(1cem : 5 Kanhaighat c/sand) i/c earth excavation 10cm bed
c.c.1: 5 : 10 1cem : 5 Kanhaighat c/sand :10gr.st.aggrt.40mm
n/size i/c 12mm thick cement plaster 1: 3 (1cem : 3 Kanhaighat
Coarse sand) with a floating coat of neat cement inside & outside
as per standard design.
0
120634506.59 90633037.65
Keystone infra Pvt Ltd
Project : PHQ Phase II
Height/
Sl no Item description Unit nos Length Width Qnty Remarks
Depth

Earthwork in excavation in foundation trenches or drains including dressing of sides and ramming of bottoms
including getting out the excavted soil and disposal od surplus excavated soil as directed within a lead of 50
m in Hard dense soil.(a) Lift upto 1.5 m

1 1,G-O CP5 cum 15 3.60 3.60 1.25 243.00


2 1,M CP7 cum 3 4.53 4.63 1.25 78.65
3 3,P (Rectangle) CP3 cum 4 3.60 1.20 1.25 21.60
4 3,P (TRAPEZIUM) 1/2(S+S)XH CP3 cum 4 2.38 2.31 1.25 27.43
5 3-4,G CP1 cum 5 3.60 1.50 1.25 33.75
6 2,H-P CP6 cum 11 2.94 2.94 1.25 118.85
7 4,D (Rectangle) CP4 cum 1 3.25 1.35 1.25 5.48
8 4,D (TRAPEZIUM) 1/2(S+S)XH CP4 cum 1 2.05 1.96 1.25 5.02
9 CP9 cum 2 4.73 3.14 1.25 37.13
10 CP10 cum 1 6.98 3.20 1.25 27.92
11 CP6' cum 2 3.04 1.50 1.25 11.40
12 Grade Beam Extra Excavation
13 A1-A12 cum 1 26.64 0.30 1.25 9.99
14 B1-B12 cum 1 24.57 0.30 1.25 9.21
15 C1-C12 cum 1 23.61 0.30 1.25 8.85
16 D1-D12 cum 1 15.42 0.30 1.25 5.78
17 E3-E12 cum 1 17.85 0.30 1.25 6.69
18 A1-D1 & A2-D2 cum 2 7.22 0.30 1.25 5.42
A3-E3 &A6-E6 & A7-E7 & A8-E8 & A9-E9 & 7
19 A11-E11 & A12-E12 cum 12.21 0.30 1.25 32.05
20 A4-E4 cum 1 12.21 0.30 1.25 4.58
21 A5-E5 cum 1 12.21 0.30 1.25 4.58
22 cum 1 12.21 0.30 1.25 4.58
701.98
Height/
Sl no Item description Unit nos Length Width Depth Qnty Remarks

Providing and laying cement concrete works in foundation and plinth excluding the cost of centering &
shuttering in (a) C.C. 1:5:10 (1 cement :5 Kanhaighat coarse sand :10 graded stone aggrt. 40mm nominal
size).
PCC - FOOTING (M10)
23 1,G-O CP5 cum 15 3.70 3.70 0.15 30.80
24 1,M CP7 cum 3 4.63 4.63 0.15 9.65
25 3,P (Rectangle) CP3 cum 4 3.70 1.30 0.15 2.89
26 3,P (TRAPEZIUM) 1/2(S+S)XH CP3 cum 4 2.43 2.41 0.15 3.51
27 3-4,G CP1 cum 5 3.70 1.60 0.15 4.44
28 2,H-P CP6 cum 11 3.04 3.04 0.15 15.25
29 4,D (Rectangle) CP4 cum 1 3.05 1.15 0.15 0.53
30 4,D (TRAPEZIUM) 1/2(S+S)XH CP4 cum 1 2.10 1.76 0.15 0.55
31 CP9 cum 2 4.83 3.14 0.15 4.55
32 CP10 cum 1 6.98 3.30 0.15 3.46
33 CP6' cum 2 3.14 1.60 0.15 1.51
45 Grade Beam
46 A1-A12 cum 1 26.64 0.30 0.15 1.20
47 B1-B12 cum 1 24.57 0.30 0.15 1.11
48 C1-C12 cum 1 23.61 0.30 0.15 1.06
49 D1-D12 cum 1 15.42 0.30 0.15 0.69
50 E3-E12 cum 1 17.85 0.30 0.15 0.80
51 A1-D1 & A2-D2 cum 2 7.22 0.30 0.15 0.65

6 OF 58
A3-E3 &A6-E6 & A7-E7 & A8-E8 & A9-E9 & 7
52 A11-E11 & A12-E12 cum 12.21 0.30 0.15 3.85

7 OF 58
53 A4-E4 cum 1 12.21 0.30 0.15 0.55
54 A5-E5 cum 1 12.21 0.30 0.15 0.55
55 cum 1 12.21 0.30 0.15 0.55
Floor PCC cum 1 53.38 19.39 0.15 155.26
243.39
Height/
Sl no Item description Unit nos Length Width Qnty Remarks
Depth

Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of
centering, shuttering, finishing and reinforcement - All work up to plinth level : (a)1:1:2 (1 cement :1 coarse
sand:2 graded stone aggregate 20 mm nominal size.)
RCC FOOTING M20
1,G-O CP5 cum 15 3.10 3.10 1.25 180.19
1,M CP7 cum 3 4.03 4.03 1.25 60.90
3,P (Rectangle) CP3 cum 4 3.25 0.85 1.25 13.81
3,P (TRAPEZIUM) 1/2(S+S)XH CP3 cum 4 2.28 2.11 1.25 24.00
3-4,G CP1 cum 5 3.40 1.30 1.25 27.63
2,H-P CP6 cum 11 2.59 2.44 1.25 86.89
4,D (Rectangle) CP4 cum 1 2.75 1.00 1.25 3.44
4,D (TRAPEZIUM) 1/2(S+S)XH CP4 cum 1 2.03 1.61 1.25 4.08
CP9 cum 2 4.23 2.54 1.25 26.86
CP10 cum 1 6.38 2.70 1.25 21.53
CP6' cum 2 2.54 1.00 1.25 6.35
Grade Beam
A1-A12 cum 1 26.64 0.30 0.40 3.20
B1-B12 cum 1 24.57 0.30 0.40 2.95
C1-C12 cum 1 23.61 0.30 0.40 2.83
D1-D12 cum 1 15.42 0.30 0.40 1.85
E3-E12 cum 1 17.85 0.30 0.40 2.14
A1-D1 & A2-D2 cum 2 7.22 0.30 0.40 1.73
A3-E3 &A6-E6 & A7-E7 & A8-E8 & A9-E9 & 7
A11-E11 & A12-E12 cum 12.21 0.30 0.40 10.26
A4-E4 cum 1 12.21 0.30 0.40 1.47
A5-E5 cum 1 12.21 0.30 0.40 1.47
cum 1 12.21 0.30 0.40 1.47
RCC - (Pedestal column) M20
Column C6 A1,B1 cum 2 0.60 0.60 1.70 1.22
Column C7 B3,C4,D5,E9,E10 cum 5 0.60 0.60 1.70 3.06
Column C8 A5,A6,A7,A8,B7,C12 cum 6 0.60 0.60 1.70 3.67
Column C9 A4,A9-10,B6,C7,C8 cum 6 0.60 0.60 1.70 3.67
Column C10 A3,A11,B4-5,B9-10-11,C6-9- 14
10,D6,E5-7-8 cum 0.60 0.60 1.70 8.57
Column C11 A12-13,B8 B12-13,E12 cum 6 0.60 0.60 1.70 3.67
Column C14 C3-4,D4,E4-6-11 cum 6 0.60 0.60 1.70 3.67
Column C12 C13 cum 1 0.35 0.60 1.70 0.36
Column C15 B,4 cum 4 0.35 0.60 1.70 1.43
Column C1 C1-2,D1-2 cum 4 0.60 0.60 1.70 2.45
Column C13 D3,E13 cum 2 0.35 0.60 1.70 0.71
Plinth Beam
A1-A12,B1-B12,C1-C12 cum 3 47.07 0.30 0.40 16.95
D1-D5 cum 1 17.79 0.30 0.40 2.13
E3-E12 cum 1 43.61 0.30 0.40 5.23
A1-D1 & A2-D2 cum 2 13.27 0.30 0.40 3.18
A3-E3 TO A12-E12 cum 10 16.47 0.30 0.40 19.76
EXTRA C1-D1 cum 1 3.40 0.30 0.40 0.41
EXTRA C11-D11 & C12-D12 cum 3 7.36 0.30 0.40 2.65
EXTRA cum 4 3.00 0.30 0.40 1.44
EXTRA cum 4 1.50 0.30 0.40 0.72

8 OF 58
570.00

9 OF 58
Height/
Sl no Item description Unit nos Length Width Qnty Remarks
Depth

Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and
string courses, fillets, columns,pillars, piers, abutments, posts and struts etc. up to floor five level,excluding
cost of centering, shuttering, finishing and reinforcement :(a)1:1:2 (1 cement :1 coarse sand:2 graded stone
aggregate 20 mm nominal size.)
Ground floor RCC - (column) M20
Column C6 A1,B1 cum 2 0.60 0.60 3.15 2.27
Column C7 B3,C4,D5,E9,E10 cum 5 0.60 0.60 3.15 5.67
Column C8 A5,A6,A7,A8,B7,C12 cum 6 0.60 0.60 3.15 6.80
Column C9 A4,A9-10,B6,C7,C8 cum 6 0.60 0.60 3.15 6.80
Column C10 A3,A11,B4-5,B9-10-11,C6-9- 14
10,D6,E5-7-8 cum 0.60 0.60 3.15 15.88
Column C11 A12-13,B8 B12-13,E12 cum 6 0.60 0.60 3.15 6.80
Column C14 C3-4,D4,E4-6-11 cum 6 0.60 0.60 3.15 6.80
Column C12 C13 cum 1 0.35 0.60 3.15 0.66
Column C15 B,4 cum 4 0.35 0.60 3.15 2.65
Column C1 C1-2,D1-2 cum 4 0.60 0.60 3.15 4.54
Column C13 D3,E13 cum 2 0.35 0.60 3.15 1.32

Lift Wall Cum 1 1.65 0.25 3.3 1.36

Cum 2 1.80 0.25 3.3 2.97

Lift Wall Cum 1 2.00 0.25 3.3 1.65

Cum 2 3.00 0.25 3.3 4.95


First floor RCC - (column) M20 3.15
Column C6 A1,B1 cum 2 0.60 0.60 3.15 2.27
Column C7 B3,C4,D5,E9,E10 cum 5 0.60 0.60 3.15 5.67
Column C8 A5,A6,A7,A8,B7,C12 cum 6 0.60 0.60 3.15 6.80
Column C9 A4,A9-10,B6,C7,C8 cum 6 0.60 0.60 3.15 6.80
Column C10 A3,A11,B4-5,B9-10-11,C6-9- 14
10,D6,E5-7-8 cum 0.60 0.60 3.15 15.88
Column C11 A12-13,B8 B12-13,E12 cum 6 0.60 0.60 3.15 6.80
Column C14 C3-4,D4,E4-6-11 cum 6 0.60 0.60 3.15 6.80
Column C12 C13 cum 1 0.35 0.60 3.15 0.66
Column C15 B,4 cum 4 0.35 0.60 3.15 2.65
Column C1 C1-2,D1-2 cum 4 0.60 0.60 3.15 4.54
Column C13 D3,E13 cum 2 0.35 0.60 3.15 1.32

Lift Wall Cum 1 1.65 0.25 3.3 1.36

Cum 2 1.80 0.25 3.3 2.97

Lift Wall Cum 1 2.00 0.25 3.3 1.65

Cum 2 3.00 0.25 3.3 4.95


Second floor RCC - (column) M20 3.15
Column C6 A1,B1 cum 2 0.60 0.60 3.15 2.27
Column C7 B3,C4,D5,E9,E10 cum 5 0.60 0.60 3.15 5.67
Column C8 A5,A6,A7,A8,B7,C12 cum 6 0.60 0.60 3.15 6.80
Column C9 A4,A9-10,B6,C7,C8 cum 6 0.60 0.60 3.15 6.80
Column C10 A3,A11,B4-5,B9-10-11,C6-9- 14
10,D6,E5-7-8 cum 0.60 0.60 3.15 15.88
Column C11 A12-13,B8 B12-13,E12 cum 6 0.60 0.60 3.15 6.80
Column C14 C3-4,D4,E4-6-11 cum 6 0.60 0.60 3.15 6.80
Column C12 C13 cum 1 0.35 0.60 3.15 0.66
Column C15 B,4 cum 4 0.35 0.60 3.15 2.65
Column C1 C1-2,D1-2 cum 4 0.60 0.60 3.15 4.54
Column C13 D3,E13 cum 2 0.35 0.60 3.15 1.32

10 OF 58
Lift Wall Cum 1 1.65 0.25 3.3 1.36

Cum 2 1.80 0.25 3.3 2.97

Lift Wall Cum 1 2.00 0.25 3.3 1.65

Cum 2 3.00 0.25 3.3 4.95


Third floor RCC - (column) M20 3.15
Column C6 A1,B1 cum 2 0.60 0.60 3.15 2.27
Column C7 B3,C4,D5,E9,E10 cum 5 0.60 0.60 3.15 5.67
Column C8 A5,A6,A7,A8,B7,C12 cum 6 0.60 0.60 3.15 6.80
Column C9 A4,A9-10,B6,C7,C8 cum 6 0.60 0.60 3.15 6.80
Column C10 A3,A11,B4-5,B9-10-11,C6-9- 14
10,D6,E5-7-8 cum 0.60 0.60 3.15 15.88
Column C11 A12-13,B8 B12-13,E12 cum 6 0.60 0.60 3.15 6.80
Column C14 C3-4,D4,E4-6-11 cum 6 0.60 0.60 3.15 6.80
Column C12 C13 cum 1 0.35 0.60 3.15 0.66
Column C15 B,4 cum 4 0.35 0.60 3.15 2.65
Column C1 C1-2,D1-2 cum 4 0.60 0.60 3.15 4.54
Column C13 D3,E13 cum 2 0.35 0.60 3.15 1.32

Lift Wall Cum 1 1.65 0.25 3.3 1.36

Cum 2 1.80 0.25 3.3 2.97


Lift Wall Cum 1 2.00 0.25 3.3 1.65

Cum 2 3.00 0.25 3.3 4.95


Fourth floor RCC - (column) M20 3.15
Column C6 A1,B1 cum 2 0.60 0.60 3.15 2.27
Column C7 B3,C4,D5,E9,E10 cum 5 0.60 0.60 3.15 5.67
Column C8 A5,A6,A7,A8,B7,C12 cum 6 0.60 0.60 3.15 6.80
Column C9 A4,A9-10,B6,C7,C8 cum 6 0.60 0.60 3.15 6.80
Column C10 A3,A11,B4-5,B9-10-11,C6-9- 14
10,D6,E5-7-8 cum 0.60 0.60 3.15 15.88
Column C11 A12-13,B8 B12-13,E12 cum 6 0.60 0.60 3.15 6.80
Column C14 C3-4,D4,E4-6-11 cum 6 0.60 0.60 3.15 6.80
Column C12 C13 cum 1 0.35 0.60 3.15 0.66
Column C15 B,4 cum 4 0.35 0.60 3.15 2.65
Column C1 C1-2,D1-2 cum 4 0.60 0.60 3.15 4.54
Column C13 D3,E13 cum 2 0.35 0.60 3.15 1.32

Lift Wall Cum 1 1.65 0.25 3.3 1.36

Cum 2 1.80 0.25 3.3 2.97

Lift Wall Cum 1 2.00 0.25 3.3 1.65

Cum 2 3.00 0.25 3.3 4.95


Fifth floor RCC - (column) M20 3.15
Column C6 A1,B1 cum 2 0.60 0.60 3.15 2.27
Column C7 B3,C4,D5,E9,E10 cum 5 0.60 0.60 3.15 5.67
Column C8 A5,A6,A7,A8,B7,C12 cum 6 0.60 0.60 3.15 6.80
Column C9 A4,A9-10,B6,C7,C8 cum 6 0.60 0.60 3.15 6.80
Column C10 A3,A11,B4-5,B9-10-11,C6-9- 14
10,D6,E5-7-8 cum 0.60 0.60 3.15 15.88
Column C11 A12-13,B8 B12-13,E12 cum 6 0.60 0.60 3.15 6.80
Column C14 C3-4,D4,E4-6-11 cum 6 0.60 0.60 3.15 6.80
Column C12 C13 cum 1 0.35 0.60 3.15 0.66
Column C15 B,4 cum 4 0.35 0.60 3.15 2.65
Column C1 C1-2,D1-2 cum 4 0.60 0.60 3.15 4.54
Column C13 D3,E13 cum 2 0.35 0.60 3.15 1.32

11 OF 58
Lift Wall Cum 1 1.65 0.25 3.3 1.36

Cum 2 1.80 0.25 3.3 2.97

Lift Wall Cum 1 2.00 0.25 3.3 1.65

Cum 2 3.00 0.25 3.3 4.95


426.77
Height/
Sl no Item description Unit nos Length Width Qnty Remarks
Depth

Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings,
balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases up to floor five
level, excluding the cost of centering, shuttering, finishing and reinforcement (a) 1: 1 : 2 (1 cement :1
Kanhaighat coarse sand: 2 graded stone aggregate 20 mm nominal size.) (i) Upto floor five level

1st roof slab

Slab Cum 1 53.67 18.69 0.15 150.46

No SLAB Cum -1 10.06 3.85 0.15 -5.81

Lift(-) Cum -1 1.65 1.8 0.15 -0.45

Lift(-) Cum -1 2.00 3.00 0.15 -0.90

Staircase Cum -2 3.00 4.80 0.15 -4.32

1st roof Beam

A1-A12 Cum 1 46.47 0.35 0.52 8.46

B1-B12 Cum 1 53.07 0.35 0.52 9.66


C1-C12 Cum 1 46.47 0.35 0.52 8.46

D1-D12 Cum 1 46.37 0.35 0.52 8.44

E1-E12 Cum 1 50.07 0.35 0.52 9.11

F1-F12 Cum 1 38.21 0.35 0.52 6.95

A1-E1 & A2-E2 Cum 2 13.97 0.35 0.52 5.09

A3-E3 Cum 1 12.77 0.35 0.52 2.32

A4-E4 Cum 1 13.47 0.35 0.52 2.45

A5-E5 Cum 1 13.12 0.35 0.52 2.39

A6-E6, A7-E7, A8-E8& A9-E9 Cum 4 13.47 0.35 0.52 9.81

A10-E10 Cum 1 12.87 0.35 0.52 2.34

A11-E11 Cum 1 13.47 0.35 0.52 2.45

A12-E12 Cum 1 13.97 0.35 0.52 2.54

Ground floor Staircase Concrete 0.00

landing beam cum 1 3.20 0.35 0.75 0.84

Flight cum 1 8.00 3.21 0.18 4.62

flight1 steps cum 10 1.43 0.30 0.25 1.06

flight2 steps cum 10 1.43 0.30 0.25 1.06

2nd roof slab

Slab Cum 1 53.67 18.69 0.15 150.46

No SLAB Cum -1 10.06 3.85 0.15 -5.81

Lift(-) Cum -1 1.65 1.8 0.15 -0.45

12 OF 58
Lift(-) Cum -1 2.00 3.00 0.15 -0.90

Staircase Cum -2 3.00 4.80 0.15 -4.32

2nd roof Beam

A1-A12 Cum 1 46.47 0.35 0.52 8.46

B1-B12 Cum 1 53.07 0.35 0.52 9.66

C1-C12 Cum 1 46.47 0.35 0.52 8.46

D1-D12 Cum 1 46.37 0.35 0.52 8.44

E1-E12 Cum 1 50.07 0.35 0.52 9.11


F1-F12 Cum 1 38.21 0.35 0.52 6.95

A1-E1 & A2-E2 Cum 2 13.97 0.35 0.52 5.09

A3-E3 Cum 1 12.77 0.35 0.52 2.32

A4-E4 Cum 1 13.47 0.35 0.52 2.45


A5-E5 Cum 1 13.12 0.35 0.52 2.39

A6-E6, A7-E7, A8-E8& A9-E9 Cum 4 13.47 0.35 0.52 9.81

A10-E10 Cum 1 12.87 0.35 0.52 2.34

A11-E11 Cum 1 13.47 0.35 0.52 2.45

A12-E12 Cum 1 13.97 0.35 0.52 2.54

First floor Staircase Concrete 0.00

landing beam cum 1 3.20 0.35 0.75 0.84

Flight cum 1 8.00 3.21 0.18 4.62

flight1 steps cum 10 1.43 0.30 0.25 1.06

flight2 steps cum 10 1.43 0.30 0.25 1.06

3rd roof slab

Slab Cum 1 53.67 18.69 0.15 150.46

No SLAB Cum -1 10.06 3.85 0.15 -5.81

Lift(-) Cum -1 1.65 1.8 0.15 -0.45

Lift(-) Cum -1 2.00 3.00 0.15 -0.90

Staircase Cum -2 3.00 4.80 0.15 -4.32

3rd roof Beam

A1-A12 Cum 1 46.47 0.35 0.52 8.46

B1-B12 Cum 1 53.07 0.35 0.52 9.66

C1-C12 Cum 1 46.47 0.35 0.52 8.46

D1-D12 Cum 1 46.37 0.35 0.52 8.44

E1-E12 Cum 1 50.07 0.35 0.52 9.11

F1-F12 Cum 1 38.21 0.35 0.52 6.95

A1-E1 & A2-E2 Cum 2 13.97 0.35 0.52 5.09


A3-E3 Cum 1 12.77 0.35 0.52 2.32

A4-E4 Cum 1 13.47 0.35 0.52 2.45

A5-E5 Cum 1 13.12 0.35 0.52 2.39

13 OF 58
A6-E6, A7-E7, A8-E8& A9-E9 Cum 4 13.47 0.35 0.52 9.81

A10-E10 Cum 1 12.87 0.35 0.52 2.34

A11-E11 Cum 1 13.47 0.35 0.52 2.45

A12-E12 Cum 1 13.97 0.35 0.52 2.54

Second floor Staircase Concrete 0.00

landing beam cum 1 3.20 0.35 0.75 0.84

Flight cum 1 8.00 3.21 0.18 4.62

flight1 steps cum 10 1.43 0.30 0.25 1.06


flight2 steps cum 10 1.43 0.30 0.25 1.06

4th roof slab

Slab Cum 1 53.67 18.69 0.15 150.46

No SLAB Cum -1 10.06 3.85 0.15 -5.81


Lift(-) Cum -1 1.65 1.8 0.15 -0.45

Lift(-) Cum -1 2.00 3.00 0.15 -0.90

Staircase Cum -2 3.00 4.80 0.15 -4.32

4th roof Beam

A1-A12 Cum 1 46.47 0.35 0.52 8.46

B1-B12 Cum 1 53.07 0.35 0.52 9.66

C1-C12 Cum 1 46.47 0.35 0.52 8.46

D1-D12 Cum 1 46.37 0.35 0.52 8.44

E1-E12 Cum 1 50.07 0.35 0.52 9.11

F1-F12 Cum 1 38.21 0.35 0.52 6.95

A1-E1 & A2-E2 Cum 2 13.97 0.35 0.52 5.09

A3-E3 Cum 1 12.77 0.35 0.52 2.32

A4-E4 Cum 1 13.47 0.35 0.52 2.45

A5-E5 Cum 1 13.12 0.35 0.52 2.39

A6-E6, A7-E7, A8-E8& A9-E9 Cum 4 13.47 0.35 0.52 9.81

A10-E10 Cum 1 12.87 0.35 0.52 2.34

A11-E11 Cum 1 13.47 0.35 0.52 2.45

A12-E12 Cum 1 13.97 0.35 0.52 2.54

Third floor Staircase Concrete 0.00

landing beam cum 1 3.20 0.35 0.75 0.84

Flight cum 1 8.00 3.21 0.18 4.62

flight1 steps cum 10 1.43 0.30 0.25 1.06

flight2 steps cum 10 1.43 0.30 0.25 1.06

5th roof slab


Slab Cum 1 53.67 18.69 0.15 150.46

No SLAB Cum -1 10.06 3.85 0.15 -5.81

Lift(-) Cum -1 1.65 1.8 0.15 -0.45

14 OF 58
Lift(-) Cum -1 2.00 3.00 0.15 -0.90

Staircase Cum -2 3.00 4.80 0.15 -4.32

5th roof Beam

A1-A12 Cum 1 46.47 0.35 0.52 8.46

B1-B12 Cum 1 53.07 0.35 0.52 9.66

C1-C12 Cum 1 46.47 0.35 0.52 8.46

D1-D12 Cum 1 46.37 0.35 0.52 8.44

E1-E12 Cum 1 50.07 0.35 0.52 9.11


F1-F12 Cum 1 38.21 0.35 0.52 6.95

A1-E1 & A2-E2 Cum 2 13.97 0.35 0.52 5.09

A3-E3 Cum 1 12.77 0.35 0.52 2.32

A4-E4 Cum 1 13.47 0.35 0.52 2.45


A5-E5 Cum 1 13.12 0.35 0.52 2.39

A6-E6, A7-E7, A8-E8& A9-E9 Cum 4 13.47 0.35 0.52 9.81

A10-E10 Cum 1 12.87 0.35 0.52 2.34

A11-E11 Cum 1 13.47 0.35 0.52 2.45

A12-E12 Cum 1 13.97 0.35 0.52 2.54

Fourth floor Staircase Concrete 0.00

landing beam cum 1 3.20 0.35 0.75 0.84

Flight cum 1 8.00 3.21 0.18 4.62

flight1 steps cum 10 1.43 0.30 0.25 1.06

flight2 steps cum 10 1.43 0.30 0.25 1.06

6th roof slab

Slab Cum 1 53.67 18.69 0.15 150.46

No SLAB Cum -1 10.06 3.85 0.15 -5.81

Lift(-) Cum -1 1.65 1.8 0.15 -0.45

Lift(-) Cum -1 2.00 3.00 0.15 -0.90

Staircase Cum -2 3.00 4.80 0.15 -4.32

6th roof Beam

A1-A12 Cum 1 46.47 0.35 0.52 8.46

B1-B12 Cum 1 53.07 0.35 0.52 9.66

C1-C12 Cum 1 46.47 0.35 0.52 8.46

D1-D12 Cum 1 46.37 0.35 0.52 8.44

E1-E12 Cum 1 50.07 0.35 0.52 9.11

F1-F12 Cum 1 38.21 0.35 0.52 6.95

A1-E1 & A2-E2 Cum 2 13.97 0.35 0.52 5.09


A3-E3 Cum 1 12.77 0.35 0.52 2.32

A4-E4 Cum 1 13.47 0.35 0.52 2.45

A5-E5 Cum 1 13.12 0.35 0.52 2.39

15 OF 58
A6-E6, A7-E7, A8-E8& A9-E9 Cum 4 13.47 0.35 0.52 9.81

A10-E10 Cum 1 12.87 0.35 0.52 2.34

A11-E11 Cum 1 13.47 0.35 0.52 2.45

A12-E12 Cum 1 13.97 0.35 0.52 2.54

Fifth floor Staircase Concrete 0.00

landing beam cum 1 3.20 0.35 0.75 0.84

Flight cum 1 8.00 3.21 0.18 4.62

flight1 steps cum 10 1.43 0.30 0.25 1.06


flight2 steps cum 10 1.43 0.30 0.25 1.06
1362.21

Height/
Sl no Item description Unit nos Length Width Qnty Remarks
Depth

Providing form work i/c centering & shuttering so as to give a rough finish strutting and propping etc. height
of propping and centering below supporting floor to ceiling not exceeding 4m and removal of the same for
insitu reinforced concrete to and plain concrete work in.(using 12mm shuttering ply)(a) Foundation footings,
bases of columns etc. and mass concrete.
PCC - FOOTING (M10)
1,G-O CP5 Sqm 30 7.10 0.15 31.95
1,M CP7 Sqm 6 8.96 0.15 8.06
3,P (Rectangle) CP3 Sqm 8 4.70 0.15 5.64
3,P (TRAPEZIUM) 1/2(S+S)XH CP3 Sqm 8 2.43 0.15 2.91
3-4,G CP1 Sqm 10 4.70 0.15 7.05
2,H-P CP6 Sqm 22 5.78 0.15 19.07
4,D (Rectangle) CP4 Sqm 2 4.20 0.15 1.26
4,D (TRAPEZIUM) 1/2(S+S)XH CP4 Sqm 2 3.86 0.15 1.16
CP9 Sqm 4 7.67 0.15 4.60
CP10 Sqm 2 9.98 0.15 2.99
CP6' Sqm 4 4.44 0.15 2.66
RCC FOOTING M20
1,G-O CP5 Sqm 60 3.40 1.25 255.00
1,M CP7 Sqm 12 4.33 1.25 64.95
3,P (Rectangle) CP3 Sqm 8 4.10 1.25 41.00
3,P (TRAPEZIUM) 1/2(S+S)XH CP3 Sqm 8 4.19 1.25 41.85
3-4,G CP1 Sqm 10 4.55 1.25 56.88
2,H-P CP6 Sqm 22 2.74 1.25 75.35
4,D (Rectangle) CP4 Sqm 2 3.45 1.25 8.63
4,D (TRAPEZIUM) 1/2(S+S)XH CP4 Sqm 2 3.19 1.25 7.96
CP9 Sqm 4 7.37 1.25 36.85
CP10 Sqm 2 9.68 1.25 24.20
CP6' Sqm 4 4.14 1.25 20.70
Grade Beam
A1-A12 Sqm 2 1.1 26.64 58.61
B1-B12 Sqm 2 1.1 24.57 54.05
C1-C12 Sqm 2 1.1 23.61 51.94
D1-D12 Sqm 2 1.1 15.42 33.92
E3-E12 Sqm 2 1.1 17.85 39.27
A1-D1 & A2-D2 Sqm 4 1.1 7.22 31.77

16 OF 58
A3-E3 &A6-E6 & A7-E7 & A8-E8 & A9-E9 & 14
A11-E11 & A12-E12 Sqm 1.1 12.21 188.03
A4-E4 Sqm 2 1.1 12.21 26.86
A5-E5 Sqm 2 1.1 12.21 26.86
Sqm 2 1.1 12.21 26.86
RCC - (Pedestal column) M20
Column C6 A1,B1 Sqm 2 2.40 1.70 8.16
Column C7 B3,C4,D5,E9,E10 Sqm 5 2.40 1.70 20.40
Column C8 A5,A6,A7,A8,B7,C12 Sqm 6 2.40 1.70 24.48
Column C9 A4,A9-10,B6,C7,C8 Sqm 6 2.40 1.70 24.48
Column C10 A3,A11,B4-5,B9-10-11,C6-9- 14
10,D6,E5-7-8 Sqm 2.40 1.70 57.12
Column C11 A12-13,B8 B12-13,E12 Sqm 6 2.40 1.70 24.48
Column C14 C3-4,D4,E4-6-11 Sqm 6 2.40 1.70 24.48
Column C12 C13 Sqm 1 1.90 1.70 3.23
Column C15 B,4 Sqm 4 1.90 1.70 12.92
Column C1 C1-2,D1-2 Sqm 4 2.40 1.70 16.32
Column C13 D3,E13 Sqm 2 1.90 1.70 6.46
Plinth Beam
A1-A12,B1-B12,C1-C12 Sqm 3 47.07 1.10 155.33
D1-D5 Sqm 1 17.79 1.10 19.57
E3-E12 Sqm 1 43.61 1.10 47.97
A1-D1 & A2-D2 Sqm 2 13.27 1.10 29.18
A3-E3 TO A12-E12 Sqm 10 16.47 1.10 181.17
EXTRA C1-D1 Sqm 1 3.40 1.10 3.74
EXTRA C11-D11 & C12-D12 Sqm 3 7.36 1.10 24.29
EXTRA Sqm 4 3.00 1.10 13.20
EXTRA Sqm 4 1.50 1.10 6.60
1962.50

Height/
Sl no Item description Unit nos Length Width Qnty Remarks
Depth

(b) Columns, pillars, posts and struts (square, rectangular or polygon in plan).
Column Ground Floor
Column C6 A1,B1 Sqm 2 1.20 3.12 7.49
Column C7 B3,C4,D5,E9,E10 Sqm 5 1.20 3.12 18.72
Column C8 A5,A6,A7,A8,B7,C12 Sqm 6 1.20 3.12 22.46
Column C9 A4,A9-10,B6,C7,C8 Sqm 6 1.20 3.12 22.46
Column C10 A3,A11,B4-5,B9-10-11,C6-9- 14
10,D6,E5-7-8 Sqm 1.20 3.12 52.42
Column C11 A12-13,B8 B12-13,E12 Sqm 6 1.20 3.12 22.46
Column C14 C3-4,D4,E4-6-11 Sqm 6 1.20 3.12 22.46
Column C12 C13 Sqm 1 0.95 3.12 2.96
Column C15 B,4 Sqm 4 0.95 3.12 11.86
Column C1 C1-2,D1-2 Sqm 4 1.20 3.12 14.98
Column C13 D3,E13 Sqm 2 0.95 3.12 5.93
Column Frist Floor
Column C6 A1,B1 Sqm 2 1.20 3.12 7.49
Column C7 B3,C4,D5,E9,E10 Sqm 5 1.20 3.12 18.72
Column C8 A5,A6,A7,A8,B7,C12 Sqm 6 1.20 3.12 22.46
Column C9 A4,A9-10,B6,C7,C8 Sqm 6 1.20 3.12 22.46
Column C10 A3,A11,B4-5,B9-10-11,C6-9- 14
10,D6,E5-7-8 Sqm 1.20 3.12 52.42
Column C11 A12-13,B8 B12-13,E12 Sqm 6 1.20 3.12 22.46
Column C14 C3-4,D4,E4-6-11 Sqm 6 1.20 3.12 22.46
Column C12 C13 Sqm 1 0.95 3.12 2.96

17 OF 58
Column C15 B,4 Sqm 4 0.95 3.12 11.86
Column C1 C1-2,D1-2 Sqm 4 1.20 3.12 14.98
Column C13 D3,E13 Sqm 2 0.95 3.12 5.93

Lift Wall Sqm 2 1.65 3.3 10.89

Sqm 4 1.80 3.3 23.76

Lift Wall Sqm 2 2.00 3.3 13.20

Sqm 4 3.00 3.3 39.60


Column Second Floor
Column C6 A1,B1 Sqm 2 1.20 3.12 7.49
Column C7 B3,C4,D5,E9,E10 Sqm 5 1.20 3.12 18.72
Column C8 A5,A6,A7,A8,B7,C12 Sqm 6 1.20 3.12 22.46
Column C9 A4,A9-10,B6,C7,C8 Sqm 6 1.20 3.12 22.46
Column C10 A3,A11,B4-5,B9-10-11,C6-9- 14
10,D6,E5-7-8 Sqm 1.20 3.12 52.42
Column C11 A12-13,B8 B12-13,E12 Sqm 6 1.20 3.12 22.46
Column C14 C3-4,D4,E4-6-11 Sqm 6 1.20 3.12 22.46
Column C12 C13 Sqm 1 0.95 3.12 2.96
Column C15 B,4 Sqm 4 0.95 3.12 11.86
Column C1 C1-2,D1-2 Sqm 4 1.20 3.12 14.98
Column C13 D3,E13 Sqm 2 0.95 3.12 5.93

Lift Wall Sqm 2 1.65 3.3 10.89

Sqm 4 1.80 3.3 23.76

Lift Wall Sqm 2 2.00 3.3 13.20

Sqm 4 3.00 3.3 39.60


Column Third Floor
Column C6 A1,B1 Sqm 2 1.20 3.12 7.49
Column C7 B3,C4,D5,E9,E10 Sqm 5 1.20 3.12 18.72
Column C8 A5,A6,A7,A8,B7,C12 Sqm 6 1.20 3.12 22.46
Column C9 A4,A9-10,B6,C7,C8 Sqm 6 1.20 3.12 22.46
Column C10 A3,A11,B4-5,B9-10-11,C6-9- 14
10,D6,E5-7-8 Sqm 1.20 3.12 52.42
Column C11 A12-13,B8 B12-13,E12 Sqm 6 1.20 3.12 22.46
Column C14 C3-4,D4,E4-6-11 Sqm 6 1.20 3.12 22.46
Column C12 C13 Sqm 1 0.95 3.12 2.96
Column C15 B,4 Sqm 4 0.95 3.12 11.86
Column C1 C1-2,D1-2 Sqm 4 1.20 3.12 14.98
Column C13 D3,E13 Sqm 2 0.95 3.12 5.93

Lift Wall Sqm 2 1.65 3.3 10.89

Sqm 4 1.80 3.3 23.76


Lift Wall Sqm 2 2.00 3.3 13.20

Sqm 4 3.00 3.3 39.60


Column Fourth Floor
Column C6 A1,B1 Sqm 2 1.20 3.12 7.49
Column C7 B3,C4,D5,E9,E10 Sqm 5 1.20 3.12 18.72
Column C8 A5,A6,A7,A8,B7,C12 Sqm 6 1.20 3.12 22.46
Column C9 A4,A9-10,B6,C7,C8 Sqm 6 1.20 3.12 22.46
Column C10 A3,A11,B4-5,B9-10-11,C6-9- 14
10,D6,E5-7-8 Sqm 1.20 3.12 52.42
Column C11 A12-13,B8 B12-13,E12 Sqm 6 1.20 3.12 22.46
Column C14 C3-4,D4,E4-6-11 Sqm 6 1.20 3.12 22.46
Column C12 C13 Sqm 1 0.95 3.12 2.96

18 OF 58
Column C15 B,4 Sqm 4 0.95 3.12 11.86
Column C1 C1-2,D1-2 Sqm 4 1.20 3.12 14.98
Column C13 D3,E13 Sqm 2 0.95 3.12 5.93

Lift Wall Sqm 2 1.65 3.3 10.89

Sqm 4 1.80 3.3 23.76

Lift Wall Sqm 2 2.00 3.3 13.20

Sqm 4 3.00 3.3 39.60


Column Fifth Floor
Column C6 A1,B1 Sqm 2 1.20 3.12 7.49
Column C7 B3,C4,D5,E9,E10 Sqm 5 1.20 3.12 18.72
Column C8 A5,A6,A7,A8,B7,C12 Sqm 6 1.20 3.12 22.46
Column C9 A4,A9-10,B6,C7,C8 Sqm 6 1.20 3.12 22.46
Column C10 A3,A11,B4-5,B9-10-11,C6-9- 14
10,D6,E5-7-8 Sqm 1.20 3.12 52.42
Column C11 A12-13,B8 B12-13,E12 Sqm 6 1.20 3.12 22.46
Column C14 C3-4,D4,E4-6-11 Sqm 6 1.20 3.12 22.46
Column C12 C13 Sqm 1 0.95 3.12 2.96
Column C15 B,4 Sqm 4 0.95 3.12 11.86
Column C1 C1-2,D1-2 Sqm 4 1.20 3.12 14.98
Column C13 D3,E13 Sqm 2 0.95 3.12 5.93

Lift Wall Sqm 2 1.65 3.3 10.89

Sqm 4 1.80 3.3 23.76

Lift Wall Sqm 2 2.00 3.3 13.20

Sqm 4 3.00 3.3 39.60


1662.47

(c) Sides and soffits of beams, beam haunchings, cantilivers, girders, bressumers and lintels not exceeding 1m
in depth.

1st roof Beam

A1-A12 Sqm 1 46.47 1.39 64.59

B1-B12 Sqm 1 53.07 1.39 73.77

C1-C12 Sqm 1 46.47 1.39 64.59

D1-D12 Sqm 1 46.37 1.39 64.45

E1-E12 Sqm 1 50.07 1.39 69.60

F1-F12 Sqm 1 38.21 1.39 53.11

A1-E1 & A2-E2 Sqm 2 13.97 1.39 38.84

A3-E3 Sqm 1 12.77 1.39 17.75

A4-E4 Sqm 1 13.47 1.39 18.72

A5-E5 Sqm 1 13.12 1.39 18.24

A6-E6, A7-E7, A8-E8& A9-E9 Sqm 4 13.47 1.39 74.89

A10-E10 Sqm 1 12.87 1.39 17.89

A11-E11 Sqm 1 13.47 1.39 18.72

A12-E12 Sqm 1 13.97 1.39 19.42

2nd roof Beam

A1-A12 Sqm 1 46.47 1.39 64.59

B1-B12 Sqm 1 53.07 1.39 73.77

19 OF 58
C1-C12 Sqm 1 46.47 1.39 64.59

D1-D12 Sqm 1 46.37 1.39 64.45

E1-E12 Sqm 1 50.07 1.39 69.60

F1-F12 Sqm 1 38.21 1.39 53.11

A1-E1 & A2-E2 Sqm 2 13.97 1.39 38.84

A3-E3 Sqm 1 12.77 1.39 17.75

A4-E4 Sqm 1 13.47 1.39 18.72

A5-E5 Sqm 1 13.12 1.39 18.24


A6-E6, A7-E7, A8-E8& A9-E9 Sqm 4 13.47 1.39 74.89

A10-E10 Sqm 1 12.87 1.39 17.89

A11-E11 Sqm 1 13.47 1.39 18.72

A12-E12 Sqm 1 13.97 1.39 19.42


3rd roof Beam

A1-A12 Sqm 1 46.47 1.39 64.59

B1-B12 Sqm 1 53.07 1.39 73.77

C1-C12 Sqm 1 46.47 1.39 64.59

D1-D12 Sqm 1 46.37 1.39 64.45

E1-E12 Sqm 1 50.07 1.39 69.60

F1-F12 Sqm 1 38.21 1.39 53.11

A1-E1 & A2-E2 Sqm 2 13.97 1.39 38.84

A3-E3 Sqm 1 12.77 1.39 17.75

A4-E4 Sqm 1 13.47 1.39 18.72

A5-E5 Sqm 1 13.12 1.39 18.24

A6-E6, A7-E7, A8-E8& A9-E9 Sqm 4 13.47 1.39 74.89

A10-E10 Sqm 1 12.87 1.39 17.89

A11-E11 Sqm 1 13.47 1.39 18.72

A12-E12 Sqm 1 13.97 1.39 19.42

4th roof Beam

A1-A12 Sqm 1 46.47 1.39 64.59

B1-B12 Sqm 1 53.07 1.39 73.77

C1-C12 Sqm 1 46.47 1.39 64.59

D1-D12 Sqm 1 46.37 1.39 64.45

E1-E12 Sqm 1 50.07 1.39 69.60

F1-F12 Sqm 1 38.21 1.39 53.11

A1-E1 & A2-E2 Sqm 2 13.97 1.39 38.84

A3-E3 Sqm 1 12.77 1.39 17.75


A4-E4 Sqm 1 13.47 1.39 18.72

A5-E5 Sqm 1 13.12 1.39 18.24

A6-E6, A7-E7, A8-E8& A9-E9 Sqm 4 13.47 1.39 74.89

20 OF 58
A10-E10 Sqm 1 12.87 1.39 17.89

A11-E11 Sqm 1 13.47 1.39 18.72

A12-E12 Sqm 1 13.97 1.39 19.42

5th roof Beam

A1-A12 Sqm 1 46.47 1.39 64.59

B1-B12 Sqm 1 53.07 1.39 73.77

C1-C12 Sqm 1 46.47 1.39 64.59

D1-D12 Sqm 1 46.37 1.39 64.45


E1-E12 Sqm 1 50.07 1.39 69.60

F1-F12 Sqm 1 38.21 1.39 53.11

A1-E1 & A2-E2 Sqm 2 13.97 1.39 38.84

A3-E3 Sqm 1 12.77 1.39 17.75


A4-E4 Sqm 1 13.47 1.39 18.72

A5-E5 Sqm 1 13.12 1.39 18.24

A6-E6, A7-E7, A8-E8& A9-E9 Sqm 4 13.47 1.39 74.89

A10-E10 Sqm 1 12.87 1.39 17.89

A11-E11 Sqm 1 13.47 1.39 18.72

A12-E12 Sqm 1 13.97 1.39 19.42


3072.94

(d ) Flat surfaces such as suspended floor, roofs landings and the like (i) floors etc. upto 200mm in thickness.
1st roof slab

Slab Sqm 1 53.67 18.69 1003.09

No SLAB Sqm -1 10.06 3.85 -38.73

Lift(-) Sqm -1 1.65 1.8 -2.97

Lift(-) Sqm -1 2.00 3.00 -6.00

Staircase Sqm -2 3.00 4.80 -28.80


2nd roof slab

Slab Sqm 1 53.67 18.69 1003.09

No SLAB Sqm -1 10.06 3.85 -38.73

Lift(-) Sqm -1 1.65 1.8 -2.97

Lift(-) Sqm -1 2.00 3.00 -6.00

Staircase Sqm -2 3.00 4.80 -28.80


3rd roof slab

Slab Sqm 1 53.67 18.69 1003.09


No SLAB Sqm -1 10.06 3.85 -38.73

Lift(-) Sqm -1 1.65 1.8 -2.97

Lift(-) Sqm -1 2.00 3.00 -6.00

Staircase Sqm -2 3.00 4.80 -28.80


4th roof slab

21 OF 58
Slab Sqm 1 53.67 18.69 1003.09

No SLAB Sqm -1 10.06 3.85 -38.73

Lift(-) Sqm -1 1.65 1.8 -2.97

Lift(-) Sqm -1 2.00 3.00 -6.00

Staircase Sqm -2 3.00 4.80 -28.80


5th roof slab

Slab Sqm 1 53.67 18.69 1003.09

No SLAB Sqm -1 10.06 3.85 -38.73

Lift(-) Sqm -1 1.65 1.8 -2.97

Lift(-) Sqm -1 2.00 3.00 -6.00

Staircase Sqm -2 3.00 4.80 -28.80


4632.96
(e) Staircases (e/c landing) slopping or stepped soffits including risers & stringers etc.

Ground floor Staircase Concrete Staircase 2 0.00

landing beam cum 1 3.20 1.24 3.97

Flight cum 1 8.00 3.21 25.64

flight1 steps cum 10 1.43 0.30 4.28

flight2 steps cum 10 1.43 0.30 4.28

flight1 steps riser cum 10 1.43 0.15 2.14

flight2 steps riser cum 10 1.43 0.15 2.14

Frist floor Staircase Concrete Staircase 2 0.00

landing beam cum 1 3.20 1.24 3.97

Flight cum 1 8.00 3.21 25.64

flight1 steps cum 10 1.43 0.30 4.28

flight2 steps cum 10 1.43 0.30 4.28

flight1 steps riser cum 10 1.43 0.15 2.14

flight2 steps riser cum 10 1.43 0.15 2.14

Second floor Staircase Concrete Staircase 2 0.00


landing beam cum 1 3.20 1.24 3.97

Flight cum 1 8.00 3.21 25.64

flight1 steps cum 10 1.43 0.30 4.28

flight2 steps cum 10 1.43 0.30 4.28

flight1 steps riser cum 10 1.43 0.15 2.14

flight2 steps riser cum 10 1.43 0.15 2.14

Third floor Staircase Concrete Staircase 2 0.00

landing beam cum 1 3.20 1.24 3.97

Flight cum 1 8.00 3.21 25.64

flight1 steps cum 10 1.43 0.30 4.28

flight2 steps cum 10 1.43 0.30 4.28

22 OF 58
flight1 steps riser cum 10 1.43 0.15 2.14

flight2 steps riser cum 10 1.43 0.15 2.14

Fourth floor Staircase Concrete Staircase 2 0.00

landing beam cum 1 3.20 1.24 3.97

Flight cum 1 8.00 3.21 25.64

flight1 steps cum 10 1.43 0.30 4.28

flight2 steps cum 10 1.43 0.30 4.28

flight1 steps riser cum 10 1.43 0.15 2.14


flight2 steps riser cum 10 1.43 0.15 2.14

Fifth floor Staircase Concrete Staircase 2 0.00

landing beam cum 1 3.20 1.24 3.97

Flight cum 1 8.00 3.21 25.64


flight1 steps cum 10 1.43 0.30 4.28

flight2 steps cum 10 1.43 0.30 4.28

flight1 steps riser cum 10 1.43 0.15 2.14

flight2 steps riser cum 10 1.43 0.15 2.14

Ground floor Staircase Concrete Staircase 3 0.00

landing beam cum 1 3.00 1.50 4.50

Flight cum 1 5.56 3.21 17.82

flight1 steps cum 10 1.43 0.30 4.28

flight2 steps cum 10 1.43 0.30 4.28

flight1 steps riser cum 10 1.43 0.15 2.14

flight2 steps riser cum 10 1.43 0.15 2.14

First floor Staircase Concrete Staircase 3 0.00

landing beam cum 1 3.00 1.50 4.50

Flight cum 1 5.56 3.21 17.82

flight1 steps cum 10 1.43 0.30 4.28

flight2 steps cum 10 1.43 0.30 4.28

flight1 steps riser cum 10 1.43 0.15 2.14

flight2 steps riser cum 10 1.43 0.15 2.14

Second floor Staircase Concrete Staircase 3 0.00

landing beam cum 1 3.00 1.50 4.50

Flight cum 1 5.56 3.21 17.82

flight1 steps cum 10 1.43 0.30 4.28

flight2 steps cum 10 1.43 0.30 4.28

flight1 steps riser cum 10 1.43 0.15 2.14


flight2 steps riser cum 10 1.43 0.15 2.14

Third floor Staircase Concrete Staircase 3 0.00

landing beam cum 1 3.00 1.50 4.50

23 OF 58
Flight cum 1 5.56 3.21 17.82

flight1 steps cum 10 1.43 0.30 4.28

flight2 steps cum 10 1.43 0.30 4.28

flight1 steps riser cum 10 1.43 0.15 2.14

flight2 steps riser cum 10 1.43 0.15 2.14

Fourth floor Staircase Concrete Staircase 3 0.00

landing beam cum 1 3.00 1.50 4.50

Flight cum 1 5.56 3.21 17.82


flight1 steps cum 10 1.43 0.30 4.28

flight2 steps cum 10 1.43 0.30 4.28

flight1 steps riser cum 10 1.43 0.15 2.14

flight2 steps riser cum 10 1.43 0.15 2.14


Fifth floor Staircase Concrete Staircase 3 0.00

landing beam cum 1 3.00 1.50 4.50

Flight cum 1 5.56 3.21 17.82

flight1 steps cum 10 1.43 0.30 4.28

flight2 steps cum 10 1.43 0.30 4.28

flight1 steps riser cum 10 1.43 0.15 2.14

flight2 steps riser cum 10 1.43 0.15 2.14


465.47
(f) Edges of slab and breaks in floors and walls (i) Under 20cm wide
1st roof Slab RMT 2 53.67 107.34
RMT 2 19.29 38.58
2nd roof slab RMT 2 53.67 107.34
RMT 2 19.29 38.58
3rd roof slab RMT 2 53.67 107.34
RMT 2 19.29 38.58
4th roof slab RMT 2 53.67 107.34
RMT 2 19.29 38.58
5th roof slab RMT 2 53.67 107.34
RMT 2 19.29 38.58
729.60

(g) Vertical surface such as walls (any thickness), partition and the like including attached pilasters,
buttresses, plinth and the string courses and the like
Ground Floor Lift

Lift Wall Sqm 2 1.65 3.3 10.89

Sqm 4 1.80 3.3 23.76

Lift Wall Sqm 2 2.00 3.3 13.20

Sqm 4 3.00 3.3 39.60


Frist Floor Lift

24 OF 58
Lift Wall Sqm 2 1.65 3.3 10.89

Sqm 4 1.80 3.3 23.76

Lift Wall Sqm 2 2.00 3.3 13.20

Sqm 4 3.00 3.3 39.60


Second Floor Lift

Lift Wall Sqm 2 1.65 3.3 10.89

Sqm 4 1.80 3.3 23.76

Lift Wall Sqm 2 2.00 3.3 13.20

Sqm 4 3.00 3.3 39.60


Third Floor Lift

Lift Wall Sqm 2 1.65 3.3 10.89

Sqm 4 1.80 3.3 23.76

Lift Wall Sqm 2 2.00 3.3 13.20

Sqm 4 3.00 3.3 39.60


Fourth Floor Lift

Lift Wall Sqm 2 1.65 3.3 10.89

Sqm 4 1.80 3.3 23.76

Lift Wall Sqm 2 2.00 3.3 13.20

Sqm 4 3.00 3.3 39.60


Fifth Floor Lift

Lift Wall Sqm 2 1.65 3.3 10.89

Sqm 4 1.80 3.3 23.76

Lift Wall Sqm 2 2.00 3.3 13.20

Sqm 4 3.00 3.3 39.60


524.70

25 OF 58
Height/
Sl no Item description Unit nos Length Width Qnty Remarks
Depth
2nd class (local first class) brick work in foundation and plinth in cement mortar 1:4 (1 cement : 4 Kanhaighat
coarse sand)
45 Grade Beam
96 A1-A13 cum 1 46.47 0.23 2.15 22.98
97 B1-B13 cum 1 46.47 0.23 2.15 22.98
98 C1-C13 cum 1 47.32 0.23 2.15 23.40
99 D1-D13 cum 1 17.79 0.23 2.15 8.80
100 E4-E13 cum 1 37.86 0.23 2.15 18.72
101 A1-D1 & A2-D2 cum 2 13.79 0.23 2.15 13.64
C1-D1 cum 1 3.50 0.23 2.15 1.73
A3-E3 &A6-E6 & A7-E7 & A8-E8 & A9-E9 & 7
102 A11-E11 & A12-E12 A13-E13 cum 17.19 0.23 2.15 59.50
103 A4-E4 cum 1 15.72 0.23 2.15 7.77
104 A5-E5 cum 1 16.89 0.23 2.15 8.35
105 A6-E6 cum 1 16.72 0.23 2.15 8.27
Lift 2.15
106 EXTRA cum 3 7.27 0.23 2.15 10.79
107 EXTRA cum 4 7.27 0.23 2.15 14.38
108 EXTRA cum 4 7.27 0.23 2.15 14.38
235.68

26 OF 58
Project : PHQ PHASE II     

BAR BENDING SCHEDULE


Lap/ Bend - Cutting
Dia of No of No of Total No length Devlopm Deductio Total 0.394 0.615 0.886 1.575 2.462 3.846
SI No Description / Particulars         bar Spacing Shape of bar item bars of bars ent length length
length n
A B C D E 8MM 10MM 12MM 16MM 20MM 25MM
RCC FOOTING (PC1)
b
1 Top bar in Y direction 12 0.15 a
    
c 9 8 72 1.100 2.950 1.100 -0.048 5.102 367.344 - - 325.52 - - -
b

2 Top bar in Z direction 12 0.15 a c 9 22 198 1.100 0.850 1.100 -0.048 3.002 594.396 - - 526.73 - - -

3 Bottom bar in Y direction 20 a c 9 9 81 1.100 2.950 1.100 -0.080 5.070 410.67 - - - - 1010.88 -
b

4 Botom bar In Z direction 16 0.15 a c 9 22 198 1.100 0.850 1.100 -0.064 2.986 591.228 - - - 931.41 - -
b
d
a c
Side Thread Bar 10 e 9 7 63 2.950 0.850 2.950 0.850 0.150 -0.080 7.670 483.21 - 297.36 - - - -
b
RCC FOOTING (PC2)
b

Top bar in Y direction 12 0.150 a c 1 2 2 1.100 2.39 1.100 -0.048 4.542 9.084 - - 8.05 - - -

b
Top bar in Z direction 12 0.150 a c 1 4 4 0.750 0.85 0.750 -0.048 2.302 9.208 - - 8.16 - - -

Bottom bar in Y direction 20 a c 1 9 9 2.950 2.39 2.950 -0.080 8.210 73.89 - - - - 181.88 -
b

Botom bar In Z direction 16 0.150 a c 1 4 4 0.750 0.85 0.750 -0.064 2.286 9.144 - - - 14.41 - -
b
d
a c
Side Thread Bar 10 e 1 7 7 0.85 2.39 0.85 2.39 0.150 -0.080 6.550 45.85 - 28.22 - - - -
b
RCC FOOTING (PC4)
b

Top bar in Y direction 12 0.150 a c 6 10 60 1.100 2.465 1.100 -0.048 4.617 277.02 - - 245.48 - - -

Top bar in Z direction 12 0.150 6 8 48 1.100 2.12 1.100 -0.048 4.272 205.056 - - 181.71 - - -

b
Top bar in Z direction rectangle 12 0.150 a c 6 2 12 1.100 1 1.100 -0.048 3.152 37.824 - - 33.52 - - -

Bottom bar in Y direction 20 0.127 a c 6 11 66 1.100 2.54 1.100 -0.080 4.660 307.56 - - - - 757.07 -
b

Bottom bar in Z direction 20 0.127 6 4 24 1.100 1 1.100 -0.160 3.040 72.96 - - - - 179.59 -

27 OF 58
    

BAR BENDING SCHEDULE


Lap/
length Bend - 0.394 0.615 0.886 1.575 2.462 3.846
Dia of No of No of Total No Devlopm Cutting Total
SI No Description / Particulars         bar Spacing Shape of bar item bars of bars ent Deductio length length
length n
A B C D E 8MM 10MM 12MM 16MM 20MM 25MM

Bottom bar in Z direction 20 0.127 a c 6 10 60 1.100 0.85 1.100 -0.080 2.970 178.2 - - - - 438.65 -
rectangle b

Side Thread Bar 10 6 7 42 2.54 1.7 3.38 0.85 0.150 -0.080 8.540 358.68 - 220.73 - - - -

RCC FOOTING (PC3)


b
Top bar in Y direction 12 0.150 a c 4 11 44 1.100 2.54 1.100 -0.048 4.692 206.448 - - 182.94 - - -

Top bar in Z direction 12 0.150 4 13 52 1.100 2.12 1.100 -0.048 4.272 222.144 - - 196.85 - - -

b
Top bar in Z direction rectangle 12 0.150 a c 4 7 28 1.100 1 1.100 -0.048 3.152 88.256 - - 78.21 - - -

Bottom bar in Y direction 25 0.127 a c 4 13 52 0.750 2.54 0.750 -0.100 3.940 204.88 - - - - - 788.00
b

Bottom bar in Z direction 25 0.127 4 23 92 1.100 1 1.100 -0.200 3.000 276 - - - - - 1061.54

Bottom bar in Z direction 25 0.127 a c 4 19 76 1.100 0.85 1.100 -0.100 2.950 224.2 - - - - - 862.31
rectangle b

Side Thread Bar 10 4 7 28 3.1 1.7 4.52 0.85 0.150 -0.080 10.240 286.72 - 176.44 - - - -

RCC FOOTING (PC5)


b
1 Top bar in Y direction 12 0.15 a
    
c 15 21 315 1.100 2.950 1.100 -0.048 5.102 1607.13 - - 1424.16 - - -

b
2 Top bar in Z direction 12 0.15 a c 15 21 315 1.100 2.950 1.100 -0.048 5.102 1607.13 - - 1424.16 - - -

3 Bottom bar in Y direction 20 0.15 a c 15 21 315 1.100 2.950 1.100 -0.080 5.070 1597.05 - - - - 3931.20 -
b

4 Botom bar In Z direction 20 0.15 a c 15 21 315 1.100 2.950 1.100 -0.080 5.070 1597.05 - - - - 3931.20 -
b
d
a c
Side Thread Bar 10 e 15 7 105 2.950 2.950 2.950 2.950 0.150 -0.080 11.870 1246.35 - 766.98 - - - -
b
RCC FOOTING (PC6)
b
1 Top bar in Y direction 12 0.15 a
    
c 11 17 187 1.100 2.290 1.100 -0.048 4.442 830.654 - - 736.09 - - -

28 OF 58
    

BAR BENDING SCHEDULE


Lap/
length Bend - 0.394 0.615 0.886 1.575 2.462 3.846
Dia of No of No of Total No Devlopm Cutting Total
SI No Description / Particulars         bar Spacing Shape of bar item bars of bars ent Deductio length length
     length n
A B C D E 8MM 10MM 12MM 16MM 20MM 25MM

2 Top bar in Z direction 12 0.15 a c 11 17 187 1.100 2.290 1.100 -0.048 4.442 830.654 - - 736.09 - - -

3 Bottom bar in Y direction 20 0.15 a c 11 17 187 1.100 2.290 1.100 -0.080 4.410 824.67 - - - - 2029.96 -
b

4 Botom bar In Z direction 20 0.15 a c 11 17 187 1.100 2.290 1.100 -0.080 4.410 824.67 - - - - 2029.96 -
b
d
a c
Side Thread Bar 10 e 11 7 77 2.290 2.290 2.290 2.290 0.150 -0.080 9.230 710.71 - 437.36 - - - -
b
RCC FOOTING (PC7)
b
1 Top bar in Y direction 12 0.15 a
    
c 3 27 81 1.250 3.890 1.250 -0.048 6.342 513.702 - - 455.22 - - -

2 Top bar in Z direction 12 0.15 a c 3 27 81 1.100 3.890 1.250 -0.048 6.192 501.552 - - 444.45 - - -

3 Bottom bar in Y direction 20 0.15 a c 3 27 81 1.250 3.890 1.250 -0.080 6.310 511.11 - - - - 1258.12 -
b

4 Botom bar In Z direction 20 0.15 a c 3 27 81 1.250 3.890 1.250 -0.080 6.310 511.11 - - - - 1258.12 -
b
d
a c
Side Thread Bar 10 e 3 9 27 3.890 3.890 3.890 3.890 0.150 -0.080 15.630 422.01 - 259.70 - - - -
b
RCC FOOTING (PC8)
b
1 Top bar in Y direction 12 0.15 a c 23 0 1.250 3.090 1.250 -0.048 5.542 0 - - 0.00 - - -

b
2 Top bar in Z direction 12 0.15 a c 23 0 1.250 3.090 1.250 -0.048 5.542 0 - - 0.00 - - -

3 Bottom bar in Y direction 20 0.15 a c 23 0 1.250 3.090 1.250 -0.080 5.510 0 - - - - 0.00 -
b

4 Botom bar In Z direction 20 0.15 a c 23 0 1.250 3.090 1.250 -0.080 5.510 0 - - - - 0.00 -
b
d
a c
Side Thread Bar 10 e 9 0 3.090 3.090 3.090 3.090 0.150 -0.080 12.430 0 - 0.00 - - - -
b

- - - - - -

RCC FOOTING (PC9)

29 OF 58
    

BAR BENDING SCHEDULE


Lap/
length Bend - 0.394 0.615 0.886 1.575 2.462 3.846
Dia of No of No of Total No Devlopm Cutting Total
SI No Description / Particulars         bar Spacing Shape of bar item bars of bars ent Deductio length length
length n
A B C D E 8MM 10MM 12MM 16MM 20MM 25MM
b
1 Top bar in Y direction 12 0.15 a
    
c 2 29 58 1.150 2.390 1.150 -0.048 4.642 269.236 - - 238.58 - - -

2 Top bar in Z direction 12 0.15 a c 2 17 34 1.150 4.080 1.150 -0.048 6.332 215.288 - - 190.78 - - -

3 Bottom bar in Y direction 20 0.1 a c 2 42 84 1.150 2.390 1.150 -0.080 4.610 387.24 - - - - 953.21 -
b

4 Botom bar In Z direction 20 0.1 a c 2 25 50 1.150 4.080 1.150 -0.080 6.300 315 - - - - 775.38 -
b
d
a c
Side Thread Bar 10 e 2 8 16 2.390 4.080 2.390 4.080 0.150 -0.080 13.010 208.16 - 128.10 - - - -
b
RCC FOOTING (PC10)
b
1 Top bar in Y direction 12 0.15 a
    
c 1 43 43 1.100 2.550 1.100 -0.048 4.702 202.186 - - 179.17 - - -

2 Top bar in Z direction 12 0.15 a c 1 18 18 1.100 6.230 1.100 -0.048 8.382 150.876 - - 133.70 - - -

3 Bottom bar in Y direction 20 0.1 a c 1 64 64 1.100 2.550 1.100 -0.080 4.670 298.88 - - - - 735.70 -
b

4 Botom bar In Z direction 20 0.1 a c 1 27 27 1.100 6.230 1.100 -0.080 8.350 225.45 - - - - 554.95 -
b
d
a c
Side Thread Bar 10 e 1 8 8 2.550 6.230 2.550 6.230 0.150 -0.080 17.630 141.04 - 86.79 - - - -
b
Column Upto Plinth C1 for
c

column bar-A 25 b 4 12 48 2.9 1.25 -0.100 5.300 254.4 - - - - - 978.46


a
1.25
a
column bar-B 20 b 4 4 16 2.9 1.25 -0.080 5.070 81.12 - - - - 199.68 -
c 1
d

column master ring 8 0.125 a e c 4 24 96 0.27 0.52 0.27 0.52 0.15 -0.032 1.698 163.008 64.20 - - - - -
b c
d

Column ring 8 0.125 a e c 4 24 96 0.27 0.32 0.27 0.32 0.15 -0.032 1.298 124.608 49.08 - - - - -
b
d
e
Column ring 8 0.125 a c 4 24 96 0.27 0.13 0.27 0.13 0.15 -0.032 0.918 88.128 34.71 - - - - -
b
d
a c
Column ring 8 0.125 e 4 24 96 0.13 0.52 0.13 0.52 0.15 -0.064 1.386 133.056 52.40 - - - - -
b

30 OF 58
    

BAR BENDING SCHEDULE


Lap/
length Bend - 0.394 0.615 0.886 1.575 2.462 3.846
Dia of No of No of Total No Devlopm Cutting Total
SI No Description / Particulars         bar Spacing Shape of bar item bars of bars ent Deductio length length
length n
b A B C D E 8MM 10MM 12MM 16MM 20MM 25MM
Column Upto Plinth C6 for
c

column bar-A 20 b 2 12 24 2.9 1.25 -0.080 5.320 127.68 - - - - 314.29 -


a
1.25
a
column bar-B 16 b 2 8 16 2.9 1.25 -0.064 5.086 81.376 - - - 128.20 - -
c 1
d

column master ring 8 0.125 a e c 2 24 48 5.9 5.9 5.9 5.9 0.15 -0.032 23.718 1138.464 448.38 - - - - -
b c
d

Column ring 8 0.125 a e c 2 24 48 0.27 0.32 0.27 0.32 0.15 -0.032 1.298 62.304 24.54 - - - - -
b
d
e
Column ring 8 0.125 a c 2 24 48 0.27 0.13 0.27 0.13 0.15 -0.032 0.918 44.064 17.35 - - - - -
b
d
a c
Column ring 8 0.125 e 2 24 48 0.13 0.52 0.13 0.52 0.15 -0.064 1.386 66.528 26.20 - - - - -
b
Column Upto Plinth C7 for
c

column bar-A 20 b 5 16 80 2.9 1.25 -0.080 5.070 405.6 - - - - 998.40 -


a
1

Column ring 8 ae c 5 24 120 0.52 0.52 0.52 0.52 0.15 -0.032 2.198 263.76 103.88 - - - - -
0.125 d b
d

column master ring 8 0.125 a e c 5 24 120 0.27 0.52 0.27 0.52 0.15 -0.032 1.698 203.76 80.25 - - - - -
b c
d

Column ring 8 0.125 a e c 5 24 120 0.27 0.32 0.27 0.32 0.15 -0.032 1.298 155.76 61.35 - - - - -
b
d
e
Column ring 8 0.125 a c 5 24 120 0.52 0.52 0.52 0.52 0.15 -0.032 2.198 263.76 103.88 - - - - -
b
d
e c
Column ring 8 0.125 a 5 24 120 0.13 0.52 0.13 0.52 0.15 -0.064 1.386 166.32 65.50 - - - - -
b

Pedestal column C8 for


c

column bar-A 25 b 6 4 24 2.9 1.25 -0.100 5.300 127.2 - - - - - 489.23


a
1.25
c

column bar-B 20 b 6 16 96 2.9 1.25 -0.080 5.320 510.72 - - - - 1257.16 -


a
1.25
d
column master ring 8 0.125 a e c 6 24 144 0.52 0.52 0.52 0.52 0.15 -0.032 2.198 316.512 124.66 - - - - -
b
d

31 OF 58
    

BAR BENDING SCHEDULE


Lap/
length Bend - 0.394 0.615 0.886 1.575 2.462 3.846
Dia of No of No of Total No Devlopm Cutting Total
SI No Description / Particulars         bar Spacing Shape of bar item bars of bars ent Deductio length length
length n
A B C D E 8MM 10MM 12MM 16MM 20MM 25MM
d

column master ring 8 0.125 a e c 6 24 144 0.32 0.52 0..32 0.52 0.15 -0.032 1.478 212.832 83.82 - - - - -
b
d
Column ring 8 0.125 a e c 6 24 144 0.32 0.32 0..33 0.32 0.15 -0.032 1.078 155.232 61.14 - - - - -
b
d
e
Column ring 8 0.125 a c 6 24 144 0.52 0.52 0.52 0.52 0.15 -0.032 2.198 316.512 124.66 - - - - -
b
d
e
Column ring 8 0.125 a c 6 24 144 0.13 0.52 0.13 0.52 0.15 -0.064 1.386 199.584 78.61 - - - - -
b
Pedestal column C9 for
c

column bar-A 20 b 6 20 120 2.9 1.25 -0.080 5.320 638.4 - - - - 1571.45 -


a
1.25
d
column master ring 8 0.125 a e c 6 24 144 0.52 0.52 0.52 0.52 0.15 -0.032 2.198 316.512 124.66 - - - - -
b c
d

Column ring 8 0.125 a e c 6 24 144 0.52 0.32 0.52 0.32 0.15 -0.032 1.798 258.912 101.97 - - - - -
b
d
Column ring 8 0.125 a e c 6 24 144 0.52 0.52 0.52 0.52 0.15 -0.032 2.198 316.512 124.66 - - - - -
b
d
e
Column ring 8 0.125 a c 6 24 144 0.32 0.52 0.32 0.52 0.15 -0.064 1.766 254.304 100.16 - - - - -
b
d
e
Column ring 8 0.125 a c 6 24 144 0.13 0.52 0.13 0.52 0.15 -0.064 1.386 199.584 78.61 - - - - -
b
Pedestal column C10 for
c

column bar-A 25 bc 14 12 168 2.9 1.25 -0.100 5.300 890.4 - - - - - 3424.62


a
1.25

column bar-B 16 b 14 8 112 2.9 1.25 -0.064 5.336 597.632 - - - 941.50 - -


a
1.25
d
column master ring 8 0.125 a e c 14 24 336 0.52 0.52 0.52 0.52 0.15 -0.032 2.198 738.528 290.87 - - - - -
b c
d

Column ring 8 0.125 a e c 14 24 336 0.52 0.32 0.52 0.32 0.15 -0.032 1.798 604.128 237.93 - - - - -
b
d
Column ring 8 0.125 a e c 14 24 336 0.52 0.13 0.52 0.13 0.15 -0.032 1.418 476.448 187.65 - - - - -
b
d
e
Column ring 8 0.125 a c 14 24 336 0.52 0.52 0.52 0.52 0.15 -0.064 2.166 727.776 286.63 - - - - -
b
d

32 OF 58
    

BAR BENDING SCHEDULE


Lap/
length Bend - 0.394 0.615 0.886 1.575 2.462 3.846
Dia of No of No of Total No Devlopm Cutting Total
SI No Description / Particulars         bar Spacing Shape of bar item bars of bars ent Deductio length length
length n
A B C D E 8MM 10MM 12MM 16MM 20MM 25MM
d
e
Column ring 8 0.125 a c 14 24 336 0.13 0.52 0.13 0.52 0.15 -0.064 1.386 465.696 183.41 - - - - -
b
Pedestal column C11 for
c

column bar-A 25 b 6 12 72 2.9 1.25 -0.100 5.300 381.6 - - - - - 1467.69


a
c 1.25

column bar-B 16 b 6 8 48 2.9 1.25 -0.064 5.336 256.128 - - - 403.50 - -


a
1.25
d
column master ring 8 0.125 a e c 6 24 144 0.52 0.52 0.52 0.52 0.15 -0.032 2.198 316.512 124.66 - - - - -
b c
d

Column ring 8 0.125 a e c 6 24 144 0.52 0.32 0.52 0.32 0.15 -0.032 1.798 258.912 101.97 - - - - -
b
d
Column ring 8 0.125 a e c 6 24 144 0.52 0.52 0.52 0.52 0.15 -0.032 2.198 316.512 124.66 - - - - -
b
d
e
Column ring 8 0.125 a c 6 24 144 0.32 0.52 0.32 0.52 0.15 -0.064 1.766 254.304 100.16 - - - - -
b
d
e
Column ring 8 0.125 a c 6 24 144 0.13 0.52 0.13 0.52 0.15 -0.064 1.386 199.584 78.61 - - - - -
b
Pedestal column C12 for
c

column bar-A 25 bc 1 16 16 2.9 1.25 -0.100 5.300 84.8 - - - - - 326.15


a
1.25
d
column master ring 8 0.125 a e c 1 24 24 0.2 0.52 0.52 0.2 0.15 -0.032 1.558 37.392 14.73 - - - - -
b c
d

Column ring 8 0.125 a e c 1 24 24 0.52 0.32 0.52 0.32 0.15 -0.032 1.798 43.152 17.00 - - - - -
b
d
Column ring 8 0.125 a e c 1 24 24 0.52 0.13 0.52 0.13 0.15 -0.032 1.418 34.032 13.40 - - - - -
b
d
e
Column ring 8 0.125 a c 1 24 24 0.2 0.52 0.52 0.2 0.15 -0.064 1.526 36.624 14.42 - - - - -

Pedestal column C13 for


c

column bar-A 25 bc 2 8 16 2.9 1.25 -0.100 5.300 84.8 - - - - - 326.15


a
1.25

column bar-B 20 b 2 8 16 2.9 1.25 -0.080 5.320 85.12 - - - - 209.53 -


a
1.25
d

33 OF 58
    

BAR BENDING SCHEDULE


Lap/
length Bend - 0.394 0.615 0.886 1.575 2.462 3.846
Dia of No of No of Total No Devlopm Cutting Total
SI No Description / Particulars         bar Spacing Shape of bar item bars of bars ent Deductio length length
length n
A B C D E 8MM 10MM 12MM 16MM 20MM 25MM
d
column master ring 8 0.125 a e c 2 24 48 0.2 0.52 0.52 0.2 0.15 -0.032 1.558 74.784 29.45 - - - - -
b c
d

Column ring 8 0.125 a e c 2 24 48 0.52 0.32 0.52 0.32 0.15 -0.032 1.798 86.304 33.99 - - - - -
b
d
Column ring 8 0.125 a e c 2 24 48 0.52 0.13 0.52 0.13 0.15 -0.032 1.418 68.064 26.81 - - - - -
b
d
e
Column ring 8 0.125 a c 2 24 48 0.2 0.52 0.52 0.2 0.15 -0.064 1.526 73.248 28.85 - - - - -

Pedestal column C14 for


c

column bar-A 16 bc 6 16 96 2.9 1.25 -0.064 5.336 512.256 - - - 807.00 - -


a
1.25
d
column master ring 8 0.125 a e c 6 24 144 0.2 0.52 0.52 0.2 0.15 -0.032 1.558 224.352 88.36 - - - - -
b c
d

Column ring 8 0.125 a e c 6 24 144 0.52 0.32 0.52 0.32 0.15 -0.032 1.798 258.912 101.97 - - - - -
b
d
Column ring 8 0.125 a e c 6 24 144 0.52 0.13 0.52 0.13 0.15 -0.032 1.418 204.192 80.42 - - - - -
b
d
e
Column ring 8 0.125 a c 6 24 144 0.2 0.52 0.52 0.2 0.15 -0.064 1.526 219.744 86.55 - - - - -

Pedestal column C14 for


c

column bar-A 16 b 4 16 64 2.9 1.25 -0.064 5.336 341.504 - - - 538.00 - -


a
1.25
d
column master ring 8 0.125 a e c 4 24 96 0.2 0.52 0.52 0.2 0.15 -0.032 1.558 149.568 58.91 - - - - -
b c
d

Column ring 8 0.125 a e c 4 24 96 0.52 0.32 0.52 0.32 0.15 -0.032 1.798 172.608 67.98 - - - - -
b
d
Column ring 8 0.125 a e c 4 24 96 0.52 0.13 0.52 0.13 0.15 -0.032 1.418 136.128 53.61 - - - - -
b
d
e
Column ring 8 0.125 a c 4 24 96 0.2 0.52 0.52 0.2 0.15 -0.064 1.526 146.496 57.70 - - - - -

Grade Beam A1-A12 for - - - - - -

b
1 Top bar in Y direction 20
    
1 3 3 0.300 53.57 0.300 1.00 -0.080 55.090 165.27 - - - - 406.82 -

34 OF 58
    

BAR BENDING SCHEDULE


Lap/
length Bend - 0.394 0.615 0.886 1.575 2.462 3.846
Dia of No of No of Total No Devlopm Cutting Total
SI No Description / Particulars         bar Spacing Shape of bar item bars of bars ent Deductio length length
     length n
A B C D E 8MM 10MM 12MM 16MM 20MM 25MM

3 Bottom bar in Y direction 20 1 3 3 0.300 53.57 0.300 1.00 -0.080 55.090 165.27 - - - - 406.82 -
b
d
e
Side Thread Bar 8 0.125 a c 1 430 430 0.300 0.200 0.300 0.200 0.150 -0.064 1.086 466.98 183.92 - - - - -
b
Grade Beam B1-B12 for - - - - - -

b
1 Top bar in Y direction 20
    
1 3 3 0.300 53.57 0.300 1.00 -0.080 55.090 165.27 - - - - 406.82 -

3 Bottom bar in Y direction 20 1 3 3 0.300 53.57 0.300 1.00 -0.080 55.090 165.27 - - - - 406.82 -
b
d
e
Side Thread Bar 8 0.125 a c 1 429 429 0.300 0.200 0.300 0.200 0.150 -0.064 1.086 465.894 183.49 - - - - -
b
Grade Beam C1-C12 for - - - - - -

b
1 Top bar in Y direction 20
    
1 3 3 0.300 0.300 1.00 -0.080 55.190 165.57 - - - - 407.56 -
53.67

3 Bottom bar in Y direction 20 1 3 3 0.300 0.300 1.00 -0.080 55.190 165.57 - - - - 407.56 -
b 53.67
d
e
Side Thread Bar 8 0.125 a c 1 431 431 0.300 0.200 0.300 0.200 0.150 -0.064 1.086 468.066 184.35 - - - - -
b
Grade Beam D1-D12 for - - - - - -

b
1 Top bar in Y direction 20
    
1 3 3 0.300 0.300 1.00 -0.080 22.810 68.43 - - - - 168.44 -
21.29

3 Bottom bar in Y direction 20 1 3 3 0.300 0.300 1.00 -0.080 22.810 68.43 - - - - 168.44 -
b 21.29
d
e
Side Thread Bar 8 0.125 a c 1 172 172 0.300 0.200 0.300 0.200 0.150 -0.064 1.086 186.792 73.57 - - - - -
b
Grade Beam E4-E12 for - - - - - -

b
1 Top bar in Y direction 20
    
1 3 3 0.300 0.300 1.00 -0.080 44.430 133.29 - - - - 328.10 -
42.91

3 Bottom bar in Y direction 20 1 3 3 0.300 0.300 1.00 -0.080 44.430 133.29 - - - - 328.10 -
b 42.91
d
e
Side Thread Bar 8 0.125 a c 1 345 345 0.300 0.200 0.300 0.200 0.150 -0.064 1.086 374.67 147.56 - - - - -
b
Grade Beam for A1-D1 & A2-D2 - - - - - -

35 OF 58
    

BAR BENDING SCHEDULE


Lap/
length Bend - 0.394 0.615 0.886 1.575 2.462 3.846
Dia of No of No of Total No Devlopm Cutting Total
SI No Description / Particulars         bar Spacing Shape of bar item bars of bars ent Deductio length length
length n
A B C D E 8MM 10MM 12MM 16MM 20MM 25MM

b
1 Top bar in Y direction 20
    
2 3 6 0.300 0.300 1.00 -0.080 16.690 100.14 - - - - 246.50 -
15.17

3 Bottom bar in Y direction 20 2 3 6 0.300 0.300 1.00 -0.080 16.690 100.14 - - - - 246.50 -
b
15.17
d
e
Side Thread Bar 8 0.125 a c 2 123 246 0.300 0.200 0.300 0.200 0.150 -0.064 1.086 267.156 105.22 - - - - -
b

Grade Beam for A3-E3 &A6-E6 & A7-E7


& A8-E8 & A9-E9 & A11-E11 & A12-E12 - - - - - -

b
1 Top bar in Y direction 20
    
10 3 30 0.300 0.300 1.00 -0.080 20.200 606 - - - - 1491.69 -
18.68

3 Bottom bar in Y direction 20 10 3 30 0.300 0.300 1.00 -0.080 20.200 606 - - - - 1491.69 -
b 18.68
d
e
Side Thread Bar 8 0.125 a c 10 151 1510 0.300 0.200 0.300 0.200 0.150 -0.064 1.086 1639.86 645.85 - - - - -
b
Grade Beam for C1-D1 & C11-D11 - - - - - -

b
1 Top bar in Y direction 20
    
2 3 6 0.300 1.00 -0.080 4.540 27.24 - - - - 67.05 -
3.32

3 Bottom bar in Y direction 20 2 3 6 0.300 1.00 -0.080 4.540 27.24 - - - - 67.05 -


b 3.32
d
e
Side Thread Bar 8 0.125 a c 2 28 56 0.300 0.200 0.300 0.200 0.150 -0.064 1.086 60.816 23.95 - - - - -
b

Plinth Beam Reinforcement -

a      c
1 Top bar in Grid A1-A13,B1-B13 20 a c 2 3 6 0.600 53.594 0.600 1 55.794 334.764 - - - - 824.03 -

2 Top bar in Grid A1-A13,B1-B13 20 a


b
c 2 3 6 0.600 53.594 0.600 1 55.794 334.764 - - - - 824.03 -
b

3 Extra Bar 16 2 2 4 0.600 53.594 0.600 0.8 55.594 222.376 - - - 350.33 - -


b
d
e
4 Side Thread Bar 8 0.125 a c 2 430 860 0.300 0.200 0.300 0.200 0.150 -0.064 1.086 933.96 367.84 - - - - -
b

Plinth Beam Reinforcement -

a      c
1 Top bar in Grid C1-C13 20 a c 1 3 3 0.600 9.960 0.600 1 12.160 36.48 - - - - 89.80 -

36 OF 58
    

BAR BENDING SCHEDULE


Lap/
length Bend - 0.394 0.615 0.886 1.575 2.462 3.846
Dia of No of No of Total No Devlopm Cutting Total
SI No Description / Particulars         bar Spacing Shape of bar item bars of bars ent Deductio length length
length n
A B C D E 8MM 10MM 12MM 16MM 20MM 25MM

2 Bottom bar in grid C1-C13 20 a c 1 3 3 0.600 9.960 0.600 1 12.160 36.48 - - - - 89.80 -
b
b

3 Extra Bar 16 1 2 2 0.600 9.960 0.600 0.8 11.960 23.92 - - - 37.68 - -

a b c
a c
4 Side Thread Bar 8 0.125 e 1 9.960 9.96 0.300 0.200 0.300 0.200 0.150 -0.064 1.086 10.81656 4.26 - - - - -

a      c
5 Top bar in Grid C1-C13 20 a c 1 3 3 0.600 42.260 0.600 1 44.460 133.38 - - - - 328.32 -

6 Bottom bar in grid C1-C13 20 a c 1 3 3 0.600 42.260 0.600 1 44.460 133.38 - - - - 328.32 -
bb

7 Extra Bar 16 1 1 1 0.600 42.260 0.600 1.25 44.710 44.71 - - - 70.44 - -

a bd c
a c
8 Side Thread Bar 8 0.125 e 1 340 340 0.300 0.200 0.300 0.200 0.150 -0.064 1.086 369.24 145.42 - - - - -
b

Plinth Beam Reinforcement -


b
1 Top bar in Grid D1-D6 20 a
    
c 1 3 3 0.600 20.690 0.600 1 22.890 68.67 - - - - 169.03 -

b
2 Bottom bar in grid D1-D16 20 a c 1 3 3 0.600 20.690 0.600 1 22.890 68.67 - - - - 169.03 -

b
3 Extra Bar 16 a
    
c 1 2 2 0.600 20.690 0.600 0.8 22.690 45.38 - - - 71.49 - -

b
e
4 Side Thread Bar 8 0.125 a c 1 167 167 0.300 0.200 0.300 0.200 0.150 -0.064 1.086 181.362 71.43 - - - - -
b

Plinth Beam Reinforcement -

a      c
2 Top bar in Grid E4-E13 20 a c 1 3 3 0.300 42.910 0.300 1 44.510 133.53 - - - - 328.69 -

3 Bottom bar in grid E4-E13 20 a


b
c 1 3 3 0.300 42.910 0.300 1 44.510 133.53 - - - - 328.69 -
b

1 Extra Bar 16 1 2 2 0.300 42.910 0.300 0.8 44.310 88.62 - - - 139.61 - -

a bd c
a c
Side Thread Bar 8 0.125 e 1 325 325 0.300 0.200 0.300 0.200 0.150 -0.064 1.086 352.95 139.01 - - - - -
b

37 OF 58
    

BAR BENDING SCHEDULE


Lap/
length Bend - 0.394 0.615 0.886 1.575 2.462 3.846
Dia of No of No of Total No Devlopm Cutting Total
SI No Description / Particulars         bar Spacing Shape of bar item bars of bars ent Deductio length length
length n
b A B C D E 8MM 10MM 12MM 16MM 20MM 25MM

Plinth Beam Reinforcement -

a      c
2 Top bar in Grid A1-D1 & A2-D2A 20 a c 2 3 6 0.300 15.170 0.300 1 16.770 100.62 - - - - 247.68 -

3 Bottom bar in grid A1-D1 & A2-D 20 a


b
c 2 3 6 0.300 15.170 0.300 1 16.770 100.62 - - - - 247.68 -
b

1 Extra Bar 16 2 2 4 0.300 15.170 0.300 0.8 16.570 66.28 - - - 104.42 - -

a bd c
a c
Side Thread Bar 8 0.125 e 2 111 222 0.300 0.200 0.300 0.200 0.150 -0.064 1.086 241.092 94.95 - - - - -
b

Plinth Beam Reinforcement -

a      c
2 Top bar in Grid C1-D1 20 a c 2 3 6 0.300 3.750 0.300 1 5.350 32.1 - - - - 79.02 -

3 Bottom bar in grid A1-D1 & A2-D 20 a


b
c 2 3 6 0.300 3.750 0.300 1 5.350 32.1 - - - - 79.02 -
b

1 Extra Bar 16 2 2 4 0.300 3.750 0.300 0.8 5.150 20.6 - - - 32.45 - -

a bd c
a c
Side Thread Bar 8 0.125 e 2 31 62 0.300 0.200 0.300 0.200 0.150 -0.064 1.086 67.332 26.52 - - - - -
b

Plinth Beam Reinforcement -

a      c
2 Top bar grid A3-E3 to A12-E12 20 a c 10 3 30 0.300 18.680 0.300 1 20.280 608.4 - - - - 1497.60 -

3 Top bar grid A3-E3 to A12-E12 20 a


b
c 10 3 30 0.300 18.680 0.300 1 20.280 608.4 - - - - 1497.60 -
b

1 Extra Bar 16 10 2 20 0.300 18.680 0.300 0.8 20.080 401.6 - - - 632.67 - -

a bd c
a c
Side Thread Bar 8 0.125 e 10 138 1380 0.674 0.274 0.674 0.274 0.150 -0.064 1.982 2735.16 1077.23 - - - - -
b
Column upto plinth
c

column bar-A 25 b 4 12 48 3.12 1.25 -0.100 5.520 264.96 - - - - - 1019.08


a
1.25
a
column bar-B 20 b 4 4 16 3.12 1.25 -0.080 5.290 84.64 - - - - 208.34 -
c 1
d

38 OF 58
    

BAR BENDING SCHEDULE


Lap/
length Bend - 0.394 0.615 0.886 1.575 2.462 3.846
Dia of No of No of Total No Devlopm Cutting Total
SI No Description / Particulars         bar Spacing Shape of bar item bars of bars ent Deductio length length
length n
c A B C D E 8MM 10MM 12MM 16MM 20MM 25MM
d

column master ring 8 0.125 a e c 4 25 100 0.27 0.52 0.27 0.52 0.15 -0.032 1.698 169.8 66.88 - - - - -
b c
d

Column ring 8 0.125 a e c 4 25 100 0.27 0.32 0.27 0.32 0.15 -0.032 1.298 129.8 51.12 - - - - -
b
d
e
Column ring 8 0.125 a c 4 25 100 0.27 0.13 0.27 0.13 0.15 -0.032 0.918 91.8 36.16 - - - - -
b
d
a c
Column ring 8 0.125 e 4 25 100 0.13 0.52 0.13 0.52 0.15 -0.064 1.386 138.6 54.59 - - - - -
b
Column Upto Plinth C6 for
c

column bar-A 20 b 2 12 24 3.12 1.25 -0.080 5.540 132.96 - - - - 327.29 -


a
1.25
a
column bar-B 16 b 2 8 16 3.12 1.25 -0.064 5.306 84.896 - - - 133.74 - -
c 1
d

column master ring 8 0.125 a e c 2 25 50 5.9 5.9 5.9 5.9 0.15 -0.032 23.718 1185.9 467.06 - - - - -
b c
d

Column ring 8 0.125 a e c 2 25 50 0.27 0.32 0.27 0.32 0.15 -0.032 1.298 64.9 25.56 - - - - -
b
d
e
Column ring 8 0.125 a c 2 25 50 0.27 0.13 0.27 0.13 0.15 -0.032 0.918 45.9 18.08 - - - - -
b
d
a c
Column ring 8 0.125 e 2 25 50 0.13 0.52 0.13 0.52 0.15 -0.064 1.386 69.3 27.29 - - - - -
b
Column Upto Plinth C7 for
c

column bar-A 20 b 5 16 80 3.12 1.25 -0.080 5.290 423.2 - - - - 1041.72 -


a
1

Column ring 8 ae c 5 25 125 0.52 0.52 0.52 0.52 0.15 -0.032 2.198 274.75 108.21 - - - - -
0.125 d b
d

column master ring 8 0.125 a e c 5 25 125 0.27 0.52 0.27 0.52 0.15 -0.032 1.698 212.25 83.59 - - - - -
b c
d

Column ring 8 0.125 a e c 5 25 125 0.27 0.32 0.27 0.32 0.15 -0.032 1.298 162.25 63.90 - - - - -
b
d
e
Column ring 8 0.125 a c 5 25 125 0.52 0.52 0.52 0.52 0.15 -0.032 2.198 274.75 108.21 - - - - -
b
d
e
Column ring 8 0.125 a c 5 25 125 0.13 0.52 0.13 0.52 0.15 -0.064 1.386 173.25 68.23 - - - - -
b

39 OF 58
    

BAR BENDING SCHEDULE


Lap/
length Bend - 0.394 0.615 0.886 1.575 2.462 3.846
Dia of No of No of Total No Devlopm Cutting Total
SI No Description / Particulars         bar Spacing Shape of bar item bars of bars ent Deductio length length
length n
A B C D E 8MM 10MM 12MM 16MM 20MM 25MM
Pedestal column C8 for
c

column bar-A 25 b 6 4 24 3.12 1.25 -0.100 5.520 132.48 - - - - - 509.54


a
1.25
c

column bar-B 20 b 6 16 96 2.9 1.25 -0.080 5.320 510.72 - - - - 1257.16 -


a
1.25
d
column master ring 8 0.125 a e c 6 25 150 0.52 0.52 0.52 0.52 0.15 -0.032 2.198 329.7 129.85 - - - - -
b
d

column master ring 8 0.125 a e c 6 25 150 0.32 0.52 0..32 0.52 0.15 -0.032 1.478 221.7 87.32 - - - - -
b
d
Column ring 8 0.125 a e c 6 25 150 0.32 0.32 0..33 0.32 0.15 -0.032 1.078 161.7 63.68 - - - - -
b
d
e
Column ring 8 0.125 a c 6 25 150 0.52 0.52 0.52 0.52 0.15 -0.032 2.198 329.7 129.85 - - - - -
b
d
e
Column ring 8 0.125 a c 6 25 150 0.13 0.52 0.13 0.52 0.15 -0.064 1.386 207.9 81.88 - - - - -
b
Pedestal column C9 for
c

column bar-A 20 b 6 20 120 3.12 1.25 -0.080 5.540 664.8 - - - - 1636.43 -


a
1.25
d
column master ring 8 0.125 a e c 6 25 150 0.52 0.52 0.52 0.52 0.15 -0.032 2.198 329.7 129.85 - - - - -
b c
d

Column ring 8 0.125 a e c 6 25 150 0.52 0.32 0.52 0.32 0.15 -0.032 1.798 269.7 106.22 - - - - -
b
d
Column ring 8 0.125 a e c 6 25 150 0.52 0.52 0.52 0.52 0.15 -0.032 2.198 329.7 129.85 - - - - -
b
d
e
Column ring 8 0.125 a c 6 25 150 0.32 0.52 0.32 0.52 0.15 -0.064 1.766 264.9 104.33 - - - - -
b
d
e
Column ring 8 0.125 a c 6 25 150 0.13 0.52 0.13 0.52 0.15 -0.064 1.386 207.9 81.88 - - - - -
b
Pedestal column C10 for
c

column bar-A 25 bc 14 12 168 3.12 1.25 -0.100 5.520 927.36 - - - - - 3566.77


a
1.25

column bar-B 16 b 14 8 112 3.12 1.25 -0.064 5.556 622.272 - - - 980.32 - -


a
1.25
d

40 OF 58
    

BAR BENDING SCHEDULE


Lap/
length Bend - 0.394 0.615 0.886 1.575 2.462 3.846
Dia of No of No of Total No Devlopm Cutting Total
SI No Description / Particulars         bar Spacing Shape of bar item bars of bars ent Deductio length length
length n
A B C D E 8MM 10MM 12MM 16MM 20MM 25MM
d
column master ring 8 0.125 a e c 14 25 350 0.52 0.52 0.52 0.52 0.15 -0.032 2.198 769.3 302.99 - - - - -
b c
d

Column ring 8 0.125 a e c 14 25 350 0.52 0.32 0.52 0.32 0.15 -0.032 1.798 629.3 247.85 - - - - -
b
d
Column ring 8 0.125 a e c 14 25 350 0.52 0.13 0.52 0.13 0.15 -0.032 1.418 496.3 195.47 - - - - -
b
d
e c
Column ring 8 0.125 a 14 25 350 0.52 0.52 0.52 0.52 0.15 -0.064 2.166 758.1 298.57 - - - - -
b
d
e
Column ring 8 0.125 a c 14 25 350 0.13 0.52 0.13 0.52 0.15 -0.064 1.386 485.1 191.05 - - - - -
b
Pedestal column C11 for
c

column bar-A 25 b 6 12 72 3.12 1.25 -0.100 5.520 397.44 - - - - - 1528.62


a
c 1.25

column bar-B 16 b 6 8 48 3.12 1.25 -0.064 5.556 266.688 - - - 420.14 - -


a
1.25
d
column master ring 8 0.125 a e c 6 25 150 0.52 0.52 0.52 0.52 0.15 -0.032 2.198 329.7 129.85 - - - - -
b c
d

Column ring 8 0.125 a e c 6 25 150 0.52 0.32 0.52 0.32 0.15 -0.032 1.798 269.7 106.22 - - - - -
b
d
Column ring 8 0.125 a e c 6 25 150 0.52 0.52 0.52 0.52 0.15 -0.032 2.198 329.7 129.85 - - - - -
b
d
e c
Column ring 8 0.125 a 6 25 150 0.32 0.52 0.32 0.52 0.15 -0.064 1.766 264.9 104.33 - - - - -
b
d
e
Column ring 8 0.125 a c 6 25 150 0.13 0.52 0.13 0.52 0.15 -0.064 1.386 207.9 81.88 - - - - -
b
Pedestal column C12 for
c

column bar-A 25 bc 1 16 16 3.12 1.25 -0.100 5.520 88.32 - - - - - 339.69


a
1.25
d
column master ring 8 0.125 a e c 1 25 25 0.2 0.52 0.52 0.2 0.15 -0.032 1.558 38.95 15.34 - - - - -
b c
d

Column ring 8 0.125 a e c 1 25 25 0.52 0.32 0.52 0.32 0.15 -0.032 1.798 44.95 17.70 - - - - -
b
d
Column ring 8 0.125 a e c 1 25 25 0.52 0.13 0.52 0.13 0.15 -0.032 1.418 35.45 13.96 - - - - -
b
d

41 OF 58
    

BAR BENDING SCHEDULE


Lap/
length Bend - 0.394 0.615 0.886 1.575 2.462 3.846
Dia of No of No of Total No Devlopm Cutting Total
SI No Description / Particulars         bar Spacing Shape of bar item bars of bars ent Deductio length length
length n
A B C D E 8MM 10MM 12MM 16MM 20MM 25MM
d
e
Column ring 8 0.125 a c 1 25 25 0.2 0.52 0.52 0.2 0.15 -0.064 1.526 38.15 15.03 - - - - -

Pedestal column C13 for


c

column bar-A 25 bc 2 8 16 3.12 1.25 -0.100 5.520 88.32 - - - - - 339.69


a
1.25

column bar-B 20 b 2 8 16 3.12 1.25 -0.080 5.540 88.64 - - - - 218.19 -


a
1.25
d
column master ring 8 0.125 a e c 2 25 50 0.2 0.52 0.52 0.2 0.15 -0.032 1.558 77.9 30.68 - - - - -
b c
d

Column ring 8 0.125 a e c 2 25 50 0.52 0.32 0.52 0.32 0.15 -0.032 1.798 89.9 35.41 - - - - -
b
d
Column ring 8 0.125 a e c 2 5 10 0.52 0.13 0.52 0.13 0.15 -0.032 1.418 14.18 5.58 - - - - -
b
d
e
Column ring 8 0.125 a c 2 3 6 0.2 0.52 0.52 0.2 0.15 -0.064 1.526 9.156 3.61 - - - - -

Pedestal column C14 for


c

column bar-A 16 bc 6 16 96 3.12 1.25 -0.064 5.556 533.376 - - - 840.27 - -


a
1.25
d
column master ring 8 0.125 a e c 6 25 150 0.2 0.52 0.52 0.2 0.15 -0.032 1.558 233.7 92.04 - - - - -
b c
d

Column ring 8 0.125 a e c 6 25 150 0.52 0.32 0.52 0.32 0.15 -0.032 1.798 269.7 106.22 - - - - -
b
d
Column ring 8 0.125 a e c 6 25 150 0.52 0.13 0.52 0.13 0.15 -0.032 1.418 212.7 83.77 - - - - -
b
d
e
Column ring 8 0.125 a c 6 25 150 0.2 0.52 0.52 0.2 0.15 -0.064 1.526 228.9 90.15 - - - - -

Pedestal column C14 for


c

column bar-A 16 b 4 16 64 3.12 1.25 -0.064 5.556 355.584 - - - 560.18 - -


a
1.25
d
column master ring 8 0.125 a e c 4 25 100 0.2 0.52 0.52 0.2 0.15 -0.032 1.558 155.8 61.36 - - - - -
b c
d

Column ring 8 0.125 a e c 4 25 100 0.52 0.32 0.52 0.32 0.15 -0.032 1.798 179.8 70.81 - - - - -
b
d

42 OF 58
    

BAR BENDING SCHEDULE


Lap/
length Bend - 0.394 0.615 0.886 1.575 2.462 3.846
Dia of No of No of Total No Devlopm Cutting Total
SI No Description / Particulars         bar Spacing Shape of bar item bars of bars ent Deductio length length
length n
A B C D E 8MM 10MM 12MM 16MM 20MM 25MM
d
Column ring 8 0.125 a e c 4 25 100 0.52 0.13 0.52 0.13 0.15 -0.032 1.418 141.8 55.85 - - - - -
b
d
e
Column ring 8 0.125 a c 4 25 100 0.2 0.52 0.52 0.2 0.15 -0.064 1.526 152.6 60.10 - - - - -
b
Column grom Ground To 5th floor
c

column bar-A 25 b 20 12 240 3.12 -0.100 4.270 1024.8 - - - - - 3941.54


a
1.25
a
column bar-B 20 b 20 4 80 3.12 -0.080 4.040 323.2 - - - - 795.57 -
c 1
d

column master ring 8 0.125 a e c 20 25 500 0.27 0.52 0.27 0.52 0.15 -0.032 1.698 849 334.38 - - - - -
b c
d

Column ring 8 0.125 a e c 20 25 500 0.27 0.32 0.27 0.32 0.15 -0.032 1.298 649 255.61 - - - - -
b
d
e
Column ring 8 0.125 a c 20 25 500 0.27 0.13 0.27 0.13 0.15 -0.032 0.918 459 180.78 - - - - -
b
d
a c
Column ring 8 0.125 e 20 25 500 0.13 0.52 0.13 0.52 0.15 -0.064 1.386 693 272.94 - - - - -
b

column bar-A 20 b 10 12 120 3.12 1.25 -0.080 5.540 664.8 - - - - 1636.43 -


a
1.25
a
column bar-B 16 b 10 8 80 3.12 1.25 -0.064 5.306 424.48 - - - 668.72 - -
c 1
d

column master ring 8 0.125 a e c 10 25 250 5.9 5.9 5.9 5.9 0.15 -0.032 23.718 5929.5 2335.31 - - - - -
b c
d

Column ring 8 0.125 a e c 10 25 250 0.27 0.32 0.27 0.32 0.15 -0.032 1.298 324.5 127.80 - - - - -
b
d
e
Column ring 8 0.125 a c 10 25 250 0.27 0.13 0.27 0.13 0.15 -0.032 0.918 229.5 90.39 - - - - -
b
d
a c
Column ring 8 0.125 e 10 25 250 0.13 0.52 0.13 0.52 0.15 -0.064 1.386 346.5 136.47 - - - - -
b

column bar-A 20 b 25 16 400 3.12 1.25 -0.080 5.290 2116 - - - - 5208.62 -


a
1

43 OF 58
    

BAR BENDING SCHEDULE


Lap/
length Bend - 0.394 0.615 0.886 1.575 2.462 3.846
Dia of No of No of Total No Devlopm Cutting Total
SI No Description / Particulars         bar Spacing Shape of bar item bars of bars ent Deductio length length
length n
A B C D E 8MM 10MM 12MM 16MM 20MM 25MM

Column ring 8 ae c 25 25 625 0.52 0.52 0.52 0.52 0.15 -0.032 2.198 1373.75 541.05 - - - - -
0.125 d b
d

column master ring 8 0.125 a e c 25 25 625 0.27 0.52 0.27 0.52 0.15 -0.032 1.698 1061.25 417.97 - - - - -
b c
d

Column ring 8 0.125 a e c 25 25 625 0.27 0.32 0.27 0.32 0.15 -0.032 1.298 811.25 319.51 - - - - -
b
d
e
Column ring 8 0.125 a c 25 25 625 0.52 0.52 0.52 0.52 0.15 -0.032 2.198 1373.75 541.05 - - - - -
b
d
e
Column ring 8 0.125 a c 25 25 625 0.13 0.52 0.13 0.52 0.15 -0.064 1.386 866.25 341.17 - - - - -
b

column bar-A 25 b 30 4 120 3.12 1.25 -0.100 5.520 662.4 - - - - - 2547.69


a
1.25
c

column bar-B 20 b 30 16 480 2.9 1.25 -0.080 5.320 2553.6 - - - - 6285.78 -


a
1.25
d
column master ring 8 0.125 a e c 30 25 750 0.52 0.52 0.52 0.52 0.15 -0.032 2.198 1648.5 649.26 - - - - -
b
d

column master ring 8 0.125 a e c 30 25 750 0.32 0.52 0..32 0.52 0.15 -0.032 1.478 1108.5 436.58 - - - - -
b
d
Column ring 8 0.125 a e c 30 25 750 0.32 0.32 0..33 0.32 0.15 -0.032 1.078 808.5 318.42 - - - - -
b
d
e c
Column ring 8 0.125 a 30 25 750 0.52 0.52 0.52 0.52 0.15 -0.032 2.198 1648.5 649.26 - - - - -
b
d
e
Column ring 8 0.125 a c 30 25 750 0.13 0.52 0.13 0.52 0.15 -0.064 1.386 1039.5 409.40 - - - - -
b

column bar-A 20 b 30 20 600 3.12 1.25 -0.080 5.540 3324 - - - - 8182.15 -


a
1.25
d
column master ring 8 0.125 a e c 30 25 750 0.52 0.52 0.52 0.52 0.15 -0.032 2.198 1648.5 649.26 - - - - -
b c
d

Column ring 8 0.125 a e c 30 25 750 0.52 0.32 0.52 0.32 0.15 -0.032 1.798 1348.5 531.10 - - - - -
b
d
Column ring 8 0.125 a e c 30 25 750 0.52 0.52 0.52 0.52 0.15 -0.032 2.198 1648.5 649.26 - - - - -
b
d

44 OF 58
    

BAR BENDING SCHEDULE


Lap/
length Bend - 0.394 0.615 0.886 1.575 2.462 3.846
Dia of No of No of Total No Devlopm Cutting Total
SI No Description / Particulars         bar Spacing Shape of bar item bars of bars ent Deductio length length
length n
A B C D E 8MM 10MM 12MM 16MM 20MM 25MM
d
e
Column ring 8 0.125 a c 30 25 750 0.32 0.52 0.32 0.52 0.15 -0.064 1.766 1324.5 521.65 - - - - -
b
d
e
Column ring 8 0.125 a c 30 25 750 0.13 0.52 0.13 0.52 0.15 -0.064 1.386 1039.5 409.40 - - - - -
b

column bar-A 25 bc 70 12 840 3.12 1.25 -0.100 5.520 4636.8 - - - - - 17833.85


a
1.25

column bar-B 16 b 70 8 560 3.12 1.25 -0.064 5.556 3111.36 - - - 4901.59 - -


a
1.25
d
column master ring 8 0.125 a e c 70 25 1750 0.52 0.52 0.52 0.52 0.15 -0.032 2.198 3846.5 1514.93 - - - - -
b c
d

Column ring 8 0.125 a e c 70 25 1750 0.52 0.32 0.52 0.32 0.15 -0.032 1.798 3146.5 1239.24 - - - - -
b
d
Column ring 8 0.125 a e c 70 25 1750 0.52 0.13 0.52 0.13 0.15 -0.032 1.418 2481.5 977.33 - - - - -
b
d
e
Column ring 8 0.125 a c 70 25 1750 0.52 0.52 0.52 0.52 0.15 -0.064 2.166 3790.5 1492.87 - - - - -
b
d
e
Column ring 8 0.125 a c 70 25 1750 0.13 0.52 0.13 0.52 0.15 -0.064 1.386 2425.5 955.27 - - - - -
b

column bar-A 25 b 30 12 360 3.12 1.25 -0.100 5.520 1987.2 - - - - - 7643.08


a
c 1.25

column bar-B 16 b 30 8 240 3.12 1.25 -0.064 5.556 1333.44 - - - 2100.68 - -


a
1.25
d
column master ring 8 0.125 a e c 30 25 750 0.52 0.52 0.52 0.52 0.15 -0.032 2.198 1648.5 649.26 - - - - -
b c
d

Column ring 8 0.125 a e c 30 25 750 0.52 0.32 0.52 0.32 0.15 -0.032 1.798 1348.5 531.10 - - - - -
b
d
Column ring 8 0.125 a e c 30 25 750 0.52 0.52 0.52 0.52 0.15 -0.032 2.198 1648.5 649.26 - - - - -
b
d
e
Column ring 8 0.125 a c 30 25 750 0.32 0.52 0.32 0.52 0.15 -0.064 1.766 1324.5 521.65 - - - - -
b
d
e
Column ring 8 0.125 a c 30 25 750 0.13 0.52 0.13 0.52 0.15 -0.064 1.386 1039.5 409.40 - - - - -
b

45 OF 58
    

BAR BENDING SCHEDULE


Lap/
length Bend - 0.394 0.615 0.886 1.575 2.462 3.846
Dia of No of No of Total No Devlopm Cutting Total
SI No Description / Particulars         bar Spacing Shape of bar item bars of bars ent Deductio length length
length n
b A B C D E 8MM 10MM 12MM 16MM 20MM 25MM

column bar-A 25 bc 5 16 80 3.12 1.25 -0.100 5.520 441.6 - - - - - 1698.46


a
1.25
d
column master ring 8 0.125 a e c 5 25 125 0.2 0.52 0.52 0.2 0.15 -0.032 1.558 194.75 76.70 - - - - -
b c
d

Column ring 8 0.125 a e c 5 25 125 0.52 0.32 0.52 0.32 0.15 -0.032 1.798 224.75 88.52 - - - - -
b
d
Column ring 8 0.125 a e c 5 25 125 0.52 0.13 0.52 0.13 0.15 -0.032 1.418 177.25 69.81 - - - - -
b
d
e
Column ring 8 0.125 a c 5 25 125 0.2 0.52 0.52 0.2 0.15 -0.064 1.526 190.75 75.13 - - - - -

column bar-A 25 bc 10 8 80 3.12 1.25 -0.100 5.520 441.6 - - - - - 1698.46


a
1.25

column bar-B 20 b 10 8 80 3.12 1.25 -0.080 5.540 443.2 - - - - 1090.95 -


a
1.25
d
column master ring 8 0.125 a e c 10 25 250 0.2 0.52 0.52 0.2 0.15 -0.032 1.558 389.5 153.40 - - - - -
b c
d

Column ring 8 0.125 a e c 10 25 250 0.52 0.32 0.52 0.32 0.15 -0.032 1.798 449.5 177.03 - - - - -
b
d
Column ring 8 0.125 a e c 10 5 50 0.52 0.13 0.52 0.13 0.15 -0.032 1.418 70.9 27.92 - - - - -
b
d
e
Column ring 8 0.125 a c 10 3 30 0.2 0.52 0.52 0.2 0.15 -0.064 1.526 45.78 18.03 - - - - -

column bar-A 16 bc 30 16 480 3.12 1.25 -0.064 5.556 2666.88 - - - 4201.36 - -


a
1.25
d
column master ring 8 0.125 a e c 30 25 750 0.2 0.52 0.52 0.2 0.15 -0.032 1.558 1168.5 460.21 - - - - -
b c
d

Column ring 8 0.125 a e c 30 25 750 0.52 0.32 0.52 0.32 0.15 -0.032 1.798 1348.5 531.10 - - - - -
b
d
Column ring 8 0.125 a e c 30 25 750 0.52 0.13 0.52 0.13 0.15 -0.032 1.418 1063.5 418.86 - - - - -
b
d

46 OF 58
    

BAR BENDING SCHEDULE


Lap/
length Bend - 0.394 0.615 0.886 1.575 2.462 3.846
Dia of No of No of Total No Devlopm Cutting Total
SI No Description / Particulars         bar Spacing Shape of bar item bars of bars ent Deductio length length
length n
A B C D E 8MM 10MM 12MM 16MM 20MM 25MM
d
e
Column ring 8 0.125 a c 30 25 750 0.2 0.52 0.52 0.2 0.15 -0.064 1.526 1144.5 450.76 - - - - -

column bar-A 16 b 20 16 320 3.12 1.25 -0.064 5.556 1777.92 - - - 2800.91 - -


a
1.25
d
column master ring 8 0.125 a e c 20 25 500 0.2 0.52 0.52 0.2 0.15 -0.032 1.558 779 306.81 - - - - -
b c
d

Column ring 8 0.125 a e c 20 25 500 0.52 0.32 0.52 0.32 0.15 -0.032 1.798 899 354.07 - - - - -
b
d
Column ring 8 0.125 a e c 20 25 500 0.52 0.13 0.52 0.13 0.15 -0.032 1.418 709 279.24 - - - - -
b
d
e
Column ring 8 0.125 a c 20 25 500 0.2 0.52 0.52 0.2 0.15 -0.064 1.526 763 300.50 - - - - -

36715.55 2401.68 7749.58 22811.02 66639.31 52390.62

188707.75

47 OF 58
PHQ PHASE II
BAR DETAIL SHAPE
OF BAR Length Length per dia of bar
BAR Dia of No of No of
MARK MEMBER PLACING Spacing bar bar sets Cutting Total
OF BAR a b c d e f 8mm 10mm 12mm 16mm 20mm 25mm
(m) length length
Beam

Top main
1 Grid 1-1 20
15.81 4 6 1.07 15.8225 1.07 17.9625 431.100 - - - - 431.1 -
Bar 1.1

0.59
Bottom 0.59
20 2 6 0.59 15.8225 0.59 17.0025 204.030 - - - - 204.03 -
Main 15.81

0.59
Bottom 16
0.59
2 6 0.59 15.8225 0.59 17.0025 204.030 - - - 204.03 - -
Main 15.81

Top Extra
16
15.81 2 6 0.59 7.91125 0.59 9.09125 109.095 - - - 109.095 - -
Bar 0.59

0..29
7 5
0.0
Stirup 0.125 0.61 8 128 6 0.61 0.29 0.61 0.29 0.075 0.075 1.95 1497.600 1497.6 - - - - -

Top main
2 Grid 2-2 25
15.82 4 6 1.345 15.8225 1.345 18.5125 444.300 - - - - - 444.3
Bar 1.345

0.59
Bottom 0.59
25 4 6 0.59 15.8225 0.59 17.0025 408.060 - - - - - 408.06
Main 15.82

Top Extra 16 2 6 0.59 7.91125 0.59 9.09125 109.095 - - - 109.095 - -


Bar 0.59 7.911

0..29
7 5
0.0
Stirup 0.125 0.61 8 128 6 0.61 0.29 0.61 0.29 0.075 0.075 1.95 1497.600 1497.6 - - - - -

Top main
3 Grid 3-3 25
19.22 4 6 1.345 19.22 1.345 21.91 525.840 - - - - - 525.84
Bar 1.375

0.59
Bottom 0.59
25 4 6 0.59 19.22 0.59 20.4 489.600 - - - - - 489.6
Main 19.22
Top Extra
16
9.61 2 6 0.59 9.61 0.59 10.79 129.480 - - - 129.48 - -
Bar 0.59

0..29
7 5
0.0
Stirup 0.125 0.61 8 155 6 0.61 0.29 0.61 0.29 0.075 0.075 1.95 1813.500 1813.5 - - - - -

Top main
4 Grid 4-4 25
19.22 4 6 1.345 19.22 1.345 21.91 525.840 - - - - - 525.84
Bar 1.37
5

0.59
Bottom 0.59
25 4 6 0.59 19.22 0.59 20.4 489.600 - - - - - 489.6
Main 19.22

Top Extra 25 2 6 0.59 9.61 0.59 10.79 129.480 - - - - - 129.48


Bar 0.59 9.61

0..29
7 5
0.0
Stirup 0.125 0.61 8 155 6 0.61 0.29 0.61 0.29 0.075 0.075 1.95 1813.500 1813.5 - - - - -

Top main
5 Grid 5-5 25
19.22 4 6 1.345 19.22 1.345 21.91 525.840 - - - - - 525.84
Bar 1.375

0.59
Bottom 0.59
25 4 6 0.59 19.22 0.59 20.4 489.600 - - - - - 489.6
Main 19.22

Top Extra
25
9.61 2 6 0.59 9.61 0.59 10.79 129.480 - - - - - 129.48
Bar 0.59

0.59
Bottom 0 16
0.59
2 6 0.59 19.22 0.59 20.4 244.800 - - - 244.8 - -
Extra 19.22

7 5
0.0
Stirup 0.125 0.61 8 155 6 0.61 0.29 0.61 0.29 0.075 0.075 1.95 1813.500 1813.5 - - - - -

Top main
6 Grid 6-6 25
19.22 4 6 1.345 19.22 1.345 21.91 525.840 - - - - - 525.84
Bar 1.375

0.59
Bottom 0.59
25 4 6 0.59 19.22 0.59 20.4 489.600 - - - - - 489.6
Main 19.22
Top Extra
25
9.61 2 6 0.59 9.61 0.59 10.79 129.480 - - - - - 129.48
Bar 0.59

0.59
Bottom 0 0.59
16 2 6 0.59 19.22 0.59 20.4 244.800 - - - 244.8 - -
Extra 19.22

7 5
0.0
Stirup 0.125 0.61 8 155 6 0.61 0.29 0.61 0.29 0.075 0.075 1.95 1813.500 1813.5 - - - - -

Top main
7 Grid 7-7 25
19.22 4 6 1.345 19.22 1.345 21.91 525.840 - - - - - 525.84
Bar 1.375

0.59
Bottom 0.59
25 4 6 0.59 19.22 0.59 20.4 489.600 - - - - - 489.6
Main 19.22

Top Extra
25
9.615 2 6 0.59 9.61 0.59 10.79 129.480 - - - - - 129.48
Bar 0.59

0.59
Bottom 0 0.59
16 2 6 0.59 19.22 0.59 20.4 244.800 - - - 244.8 - -
Extra 19.22

7 5
0.0
Stirup 0.125 0.61 8 155 6 0.61 0.29 0.61 0.29 0.075 0.075 1.95 1813.500 1813.5 - - - - -

Top main
8 Grid 8-8 25
19.22 4 6 1.345 19.22 1.345 21.91 525.840 - - - - - 525.84
Bar 1.375

0.59
Bottom 25
0.59
4 6 0.59 19.22 0.59 20.4 489.600 - - - - - 489.6
Main 19.22

Top Extra
16
9.61 2 6 0.59 9.61 0.59 10.79 129.480 - - - 129.48 - -
Bar 0.59

0.29
7 5
0.0
Stirup 0.125 0.61 8 155 6 0.61 0.29 0.61 0.29 0.075 0.075 1.95 1813.500 1813.5 - - - - -

Top main
9 Grid 9-9 25
19.22 4 6 1.345 19.22 1.345 21.91 525.840 - - - - - 525.84
Bar 1.375
0.59
Bottom 0.59
25 4 6 0.59 19.22 0.59 20.4 489.600 - - - - - 489.6
Main 19.22

Top Extra 20 2 6 0.59 9.61 0.59 10.79 129.480 - - - - 129.48 -


Bar 0.59 9.61

0.29
7 5
0.0
Stirup 0.125 0.61 8 155 6 0.61 0.29 0.61 0.29 0.075 0.075 1.95 1813.500 1813.5 - - - - -

Top main
10 Grid 10-10 25
19.22 4 6 1.345 19.22 1.345 21.91 525.840 - - - - - 525.84
Bar 1.375

0.59
Bottom 0.59
25 4 6 0.59 19.22 0.59 20.4 489.600 - - - - - 489.6
Main 19.22

Top Extra
20
9.61 2 6 0.59 9.61 0.59 10.79 129.480 - - - - 129.48 -
Bar 0.59

0.29
7 5
0.0
Stirup 0.125 0.61 8 155 6 0.61 0.29 0.61 0.29 0.075 0.075 1.95 1813.500 1813.5 - - - - -

11 Grid 11-11 Top main 25


19.22 4 6 1.345 19.22 1.345 21.91 525.840 - - - - - 525.84
Bar 1.375

0.59
Bottom 25
0.59
4 6 0.59 19.22 0.59 20.4 489.600 - - - - - 489.6
Main 19.22

Top Extra
25
9.61 2 6 0.59 9.61 0.59 10.79 129.480 - - - - - 129.48
Bar 0.59

0.59
Bottom 16
0.59
2 6 0.59 19.22 0.59 20.4 244.800 - - - 244.8 - -
Extra 19.22
0.29
7 5
0.0
Stirup 0.125 0.61 8 155 6 0.61 0.29 0.61 0.29 0.075 0.075 1.95 1813.500 1813.5 - - - - -

Top main
12 Grid 12-12 25
19.22 4 6 1.345 19.22 1.345 21.91 525.840 - - - - - 525.84
Bar 1.375
0.59
Bottom 0.59
25 4 6 0.59 19.22 0.59 20.4 489.600 - - - - - 489.6
Main 19.22

Top Extra 25 2 6 0.59 9.61 0.59 10.79 129.480 - - - - - 129.48


Bar 0.59 9.165

0.29
7 5
0.0
Stirup 0.125 0.61 8 155 6 0.61 0.29 0.61 0.29 0.075 0.075 1.95 1813.500 1813.5 - - - - -

Top main
13 Grid 13-13 25
53.31 4 6 1.345 53.31 1.345 56 1344.000 - - - - - 1344
Bar 1.375

0.59
Bottom 0.59
25 4 6 0.59 53.31 0.59 54.49 1307.760 - - - - - 1307.76
Main 53.31

Top Extra
16
26.66 2 6 0.59 26.655 0.59 27.835 334.020 - - - 334.02 - -
Bar 0.59

0..29
7 5
0.0
Stirup 0.125 0.61 8 427 6 0.61 0.29 0.61 0.29 0.075 0.075 1.95 4995.900 4995.9 - - - - -

14 Grid 14-14 Top main 20


53.31 2 6 1.07 53.31 1.07 55.45 665.400 - - - - 665.4 -
Bar 1.1

Top main
16
53.31 2 6 0.88 53.31 0.88 55.07 660.840 - - - 660.84 - -
Bar 0.88

0.59
Bottom 0.59
20 2 6 0.59 53.31 0.59 54.49 653.880 - - - - 653.88 -
Main 53.31
52.71
Bottom 0.59 0.59
16 2 6 0.59 53.31 0.59 54.49 653.880 - - - 653.88 - -
Main 53.31

26.66
Top Extra
16 2 6 0.59 26.655 0.59 27.835 334.020 - - - 334.02 - -
Bar 0.59 0.59

7 5
0.0
Stirup 0.125 0.61 8 427 6 0.61 0.29 0.61 0.29 0.075 0.075 1.95 4995.900 4995.9 - - - - -
15 Grid 15-15 Top main 25
53.31 4 6 1.345 53.31 1.345 56 1344.000 - - - - - 1344
Bar 1.375

.59
Bottom 20
0.59
4 6 0.59 53.31 0.59 54.49 1307.760 - - - - 1307.76 -
Main 53.31

Top Extra
16
26.66 2 6 0.59 26.655 0.59 27.835 334.020 - - - 334.02 - -
Bar 0.59

0..29
7 5
0.0
Stirup 0.125 0.61 8 427 6 0.61 0.29 0.61 0.29 0.075 0.075 1.95 4995.900 4995.9 - - - - -

Top main
16 Grid 16-16 25
43.25 4 6 1.345 43.25 1.345 45.94 1102.560 - - - - - 1102.56
Bar 1.37
5

0.59
Bottom 0.59
25 2 6 0.59 43.25 0.59 44.43 533.160 - - - - - 533.16
Main 43.25

0.59
Bottom 0.59
20 2 6 0.59 43.25 0.59 44.43 533.160 - - - - 533.16 -
Main 43.25

Top Extra 16 2 6 0.59 21.625 0.59 22.805 273.660 - - - 273.66 - -


Bar 0.59 21.63

0..29
7 5
0.0
Stirup 0.125 0.61 8 347 6 0.61 0.29 0.61 0.29 0.075 0.075 1.95 4059.900 4059.9 - - - - -

Top main
17 Grid 17-17 25
10.6 4 6 1.345 10.6 1.345 13.29 318.960 - - - - - 318.96
Bar 1.375

0.59
Bottom 0.59
25 2 6 0.59 10.6 0.59 11.78 141.360 - - - - - 141.36
Main 10.6

0.59
Bottom 0.59
20 2 6 0.59 10.6 0.59 11.78 141.360 - - - - 141.36 -
Main 10.6

Top Extra
16
5.3 2 6 0.59 5.3 0.59 6.48 77.760 - - - 77.76 - -
Bar 0.59
0..29
7 5
0.0
Stirup 0.125 0.61 8 86 6 0.61 0.29 0.61 0.29 0.075 0.075 1.95 1006.200 1006.2 - - - - -

Top main
18 Grid 18-18 25
53.31 4 6 1.345 53.31 1.345 56 1344.000 - - - - - 1344
Bar 1.375

0.59
Bottom 0.59
25 2 6 0.59 53.31 0.59 54.49 653.880 - - - - - 653.88
Main 53.31

0.59
Bottom 0.59
20 2 6 0.59 53.31 0.59 54.49 653.880 - - - - 653.88 -
Main 53.31

Top Extra
16
26.66 2 6 0.59 26.655 0.59 27.835 334.020 - - - 334.02 - -
Bar 0.59

0..29
7 5
0.0
Stirup 0.125 0.61 8 427 6 0.61 0.29 0.61 0.29 0.075 0.075 1.95 4995.900 4995.9 - - - - -

19 Grid 19-19 Top main 25


43.25 4 6 1.345 43.25 1.345 45.94 1102.560 - - - - - 1102.56
Bar 1.375

0.59
Bottom 25
0.59
2 6 0.59 43.25 0.59 44.43 533.160 - - - - - 533.16
Main 43.25

0.59
Bottom 20
0.59
2 6 0.59 43.25 0.59 44.43 533.160 - - - - 533.16 -
Main 43.25

Top Extra
16
21.63 2 6 0.59 21.625 0.59 22.805 273.660 - - - 273.66 - -
Bar 0.59

0..29
7 5
0.0
Stirup 0.125 0.61 8 347 6 0.61 0.29 0.61 0.29 0.075 0.075 1.95 4059.900 4059.9 - - - - -

SLAB Top& 0.13 10 437 12 0.1 19.24 0.1 19.44 101835.692 - 101835.6923 - - - -
Bottom

Top&
SLAB 0.13 10 149 12 0.1 56.57 0.1 56.77 101504.760 - 101504.76 - - - -
Bottom
Top&
Staircase-2 0.13 10 37 -12 0.1 2.95 0.1 3.15 -1381.154 - -1381.15385 - - - -
Bottom

Top&
Staircase-2 0.13 10 23 -12 0.1 4.75 0.1 4.95 -1347.923 - -1347.92308 - - - -
Bottom

Staircase-3 Top& 0.13 10 35 -12 0.1 2.95 0.1 3.15 -1305.554 - -1305.55385 - - - -
Bottom

Top&
Staircase-3 0.13 10 23 -12 0.1 4.49 0.1 4.69 -1277.123 - -1277.12308 - - - -
Bottom

Lift Top& 0.13 10 12 -12 0.17 1.82 0.17 2.16 -323.003 - -323.003077 - - - -
Bottom

Top&
Lift 0.13 10 14 -12 0.17 1.62 0.17 1.96 -329.280 - -329.28 - - - -
Bottom

Total length/dia 50239.80 197376.42 0.00 4936.26 5382.69 21509.04


Unit weight 0.395 0.617 0.889 1.580 2.469 3.846
Total weight/dia 19847.82 121837.29 0.00 7800.51 13290.59 82723.77
Gross total weight(KG) 245499.99

3.85
Gym & Canteen BBS
PCC A-A 1 12.3 2.9 0.15 5.3505
PCC B-B 1 12.3 3.54 0.15 6.5313
PCC C-C 1 12.3 2.72 0.15 5.0184
PCC D-D 1 12.3 3.1 0.15 5.7195
PCC E-E 1 10.8 2.1 0.15 3.402
26 CUM
Footing A-A M25 1 12 2.6 0.25 7.8
Footing B-B 1 12 3.24 0.25 9.72
Footing C-C 1 12 2.42 0.25 7.26
Footing D-D 1 12 2.8 0.25 8.4
Footing E-E 1 10.5 1.8 0.25 4.725
Strip A-A M25 1 12 0.45 1 5.4
Strip B-B 1 12 0.45 1 5.4
Strip C-C 1 12 0.45 1 5.4
Strip D-D 1 12 0.45 1 5.4
Strip E-E 1 10.5 0.45 1 4.725
Grade Beam 4 7.35 0.3 0.4 3.528
Grade Beam
1 5.5 0.3 0.4 0.66
Column -16 0.35 0.35 0.35 -0.686
Grade Beam
3 13.55 0.3 0.4 4.878
Column -16 0.35 0.35 0.35 -0.686
Plinth Beam 4 7.35 0.3 0.35 3.087
Plinth Beam
1 5.5 0.3 0.35 0.5775
Column -16 0.35 0.35 0.35 -0.686
Plinth Beam
3 13.55 0.3 0.35 4.26825
Column -16 0.35 0.35 0.35 -0.686
Column 16 0.35 0.35 3 6 Cum
84.36475
PHQ Gym & Canteen BBS
Lapping Length of
No. of Item Dia of bar No of Bar a b c d e a+b+c+d Length Bar 8MM 10MM 12MM 16MM 20MM 25MM
Footing A-A Main Bar 12 80 0.15 2.55 0.15 2.85 228 - - 202.04 - - -
Distribution 10 17 0.15 11.95 0.15 12.25 0.55 217.6 - 133.91 - - - -
Raft S1 strip Main Bar 20 8 1.1 11.95 1.1 14.15 1.1 122 - - - - 300.31 -
Main Bar 16 8 11.95 11.95 95.6 - - - 150.61 - -
Ring 8 96 0.4 1.1 0.4 1.1 3 288 113.43 - - - - -
Ring 8 96 0.15 1.1 0.15 1.1 2.5 240 94.52 - - - - -
Footing B-B Main Bar 12 80 0.15 3.19 0.15 3.49 279.2 - - 247.41 - - -
Distribution 10 33 0.15 11.95 0.15 12.25 404.25 - 248.77 - - - -
Raft S2 strip Main Bar 25 12 1.1 11.95 1.1 14.15 1.1 183 - - - - - 703.85
Main Bar 16 4 11.95 11.95 47.8 - - - 75.30 - -
Ring 8 97 0.4 1.1 0.4 1.1 3 291 114.61 - - - - -
Ring 8 97 0.15 1.1 0.15 1.1 2.5 242.5 95.51 - - - - -
Footing C-C Main Bar 12 80 0.15 2.19 0.15 2.49 199.2 - - 176.52 - - -
Distribution 10 16 0.15 11.95 0.15 12.25 0.55 204.8 - 126.03 - - - -
Raft S3 strip Main Bar 12 2 11.95 0 11.95 23.9 - - 21.18 - - -
Main Bar 20 8 1.1 11.95 1.1 14.15 1.1 122 - - - - 300.31 -
Main Bar 16 4 11.95 11.95 47.8 - - - 75.30 - -
Ring 8 96 0.4 1.1 0.4 1.1 3 288 113.43 - - - - -
Ring 8 97 0.15 1.1 0.15 1.1 2.5 242.5 95.51 - - - - -
Footing D-D Main Bar 12 80 0.15 3.05 0.15 3.35 268 - - 237.49 - - -
Distribution 10 25 0.15 11.95 0.15 12.25 0.55 320 - 196.92 - - - -
Raft S4 strip Main Bar 20 12 1.1 11.95 1.1 14.15 1.1 183 - - - - 450.46 -
Main Bar 16 4 11.95 11.95 47.8 - - - 75.30 - -
Ring 8 97 0.4 1.1 0.4 1.1 3 291 114.61 - - - - -
Ring 8 97 0.15 1.1 0.15 1.1 2.5 242.5 95.51 - - - - -
Footing E-E Main Bar 12 70 0.15 1.75 0.15 2.05 143.5 - - 127.16 - - -
Distribution 10 13 0.15 10.45 0.15 10.75 0.55 146.9 - 90.40 - - - -
Raft S5 strip Main Bar 16 12 1.1 10.45 1.1 12.65 1.1 165 - - - 259.94 - -
Main Bar 12 2 10.45 10.45 20.9 - - 18.52 - - -
Ring 8 85 0.4 1.1 0.4 1.1 3 255 100.43 - - - - -
Ring 8 85 0.15 1.1 0.15 1.1 2.5 212.5 83.69 - - - - -
Grade Beam
A-A to E-E Section 1-1 Main Bar 16 6 0.3 13.45 0.3 14.05 0.88 89.58 - - - 141.12 - -
Distribution 10 109 0.3 0.2 0.3 0.2 0.15 1.15 125.35 - 77.14 - - - -
A-A to E-E Section 2-2 Main Bar 16 6 0.3 13.45 0.3 14.05 0.88 89.58 - - - 141.12 - -
Distribution 10 109 0.3 0.2 0.3 0.2 0.15 1.15 125.35 - 77.14 - - - -
A-A to E-E Section 3-3 Main Bar 16 6 0.3 10.45 0.3 11.05 66.30 - - - 104.45 - -
Distribution 10 85 0.3 0.2 0.3 0.2 0.15 1.15 97.75 - 60.15 - - - -
A-A to E-E Section 4-4 Main Bar 16 6 0.3 3.25 0.3 3.85 23.10 - - - 36.39 - -
Distribution 10 27 0.3 0.2 0.3 0.2 0.15 1.15 31.05 - 19.11 - - - -
Plinth Beam
Plinth Beam Section 1-1 Main Bar 16 6 0.25 13.45 0.25 13.95 0.88 88.98 - - - 140.18 - -
Distribution 10 109 0.25 0.2 0.25 0.2 0.15 1.05 114.45 - 70.43 - - - -
Plinth Beam Section 2-2 Main Bar 16 6 0.25 13.45 0.25 13.95 0.88 88.98 - - - 140.18 - -
Distribution 10 109 0.25 0.2 0.25 0.2 0.15 1.05 114.45 - 70.43 - - - -
Plinth Beam Section 3-3 Main Bar 16 6 0.25 10.45 0.25 10.95 0.88 70.98 - - - 111.82 - -
Distribution 10 85 0.25 0.2 0.25 0.2 0.15 1.05 89.25 - 54.92 - - - -
Plinth Beam Section 4-4 Main Bar 16 6 0.25 3.25 0.25 3.75 0.88 27.78 - - - 43.76 - -
Distribution 10 27 0.25 0.2 0.25 0.2 0.15 1.05 28.35 - 17.45 - - - -
Column upto - - - - 588.88 -
3m Main Bar 16 20 4 0.8 2.938 3.738 239.232
Main Bar 16 16 4 0.8 2.938 3.738 239.232 - - - 376.88 - -
Distribution 16 8 25 0.27 0.27 0.27 0.27 0.15 1.23 492 193.77 - - - - -
Distribution 16 8 25 0.27 0.27 0.27 0.27 0.15 1.23 492 193.77 - - - - -
Total Quantity(KG) 1408.79 1242.80 1030.33 1872.36 1639.96 703.85
7898.08