You are on page 1of 100

Detailed Quantity Estimate of Septic Tank

Type of Building :- Septic Tank

S.No. Description Nos. Length Breadth

1 EARTH WORK
1 EARTH WORK
1.1 Surface dressing and Top soil cutting with 150 to 200
mm depth including disposing the surplus excvated
earth within the premises for layout & setting out of
structure as per drawing & specification.
1 20.00 7.00

1.2 Earthwork in excavation in all kinds of soil and


diposing lead up to 30m including dressing of sides,
ramming of bottom, watering, ramming, consolidation
and dressing, with all necessary shoring and
dewatering as well as backfilling the trench and
compact.
1 20.00 7.00
2 CONCRETE WORK
2.1 Supplying mixing, placing, compacting & curing of
reinforced cement concrete including plastisizer
admixture exluding the cost of form work and
reinforcement.

a) M20 (1 Cement : 1.5 Sand : 3 coarse aggregate) 1 20.00 7.00

b) M10 (1 Cement : 3 Sand : 6 coarse aggregate) 1 20.00 7.00

2.2 Supplying, fixing, cutting, bending, binding and


placing in position steel reinforcement bar including
the cost of 14 gauge galvanized iron binding wire all
complete as per drawing, specification and approval
of engineer.
a) Tor Steel

2.3 Providing, placing, fixing centering and shuttering of


plywood or steel form work for slabs, walls, columns,
lintel and beams (with necessary provision of
extension of reinforcement of wall ties) and other RCC
works including nails, propping supports and bracings
of steel pipes including lead & lift at any height &
removal and disposal of the same all complete as per
specification & approval of engineer.

1 20.00 7.00
3 BRICKWORK
3.1 Providing & laying brick masonary using first class
chimney made bricks with 1:4 cement sand mortar
including scaffolding, curing, cleaning, and racking out
mortar joints & making ducts, recesses where
required as per drawing, specification & approval of
engineer.
3 20.00 0.34
4 5.98 0.34

3.2 Dry brick soling in foundation and floors with first class
chimney made bricks in true line & level including
watering, compacting etc. all complete as per
drawing, specification & instruction.

a) On flat 1 20.00 7.00

4 FLOOR FINISH
4.1 Providing, mixing, laying and compacting 20 to 25mm
thick cement and screed (1:4) on floors in true line &
level including curing as drawing, specification &
instruction.
6 6.21 2.99

4.2 Providing, mixing, laying neat cement punning on


floors in true line & level including curing as drawing,
specification & instruction.
12 6.21
12 2.99
6 2.99 6.21

5
PLASTER AND FINISHING WORK
5.1 Providing and laying 12.5mm thick plaster on wall with
1:4 cement sand mortar in perfect line and level
including scaffolding, curing etc. all complete as per
drawing, specification & instruction.
12 6.21
12 2.99
6 2.99 6.21

6 Miscellaneous work
6.1
CI manhole cover 600 mm* 600 mm medium quality 12
nk

Civil Works

Height Quantity Remarks

140.00 m2
140.00 m2

2.28 318.50 m3

0.10 14.00
14.00 m3

0.08 10.50
10.50 m3

1,648.50 Kg

1,648.50 Kg

140.00
140.00 m2

2.10 42.84
2.10 17.08
59.92 m3

140.00 m2
140.00 m2

111.47 m2
111.47 m2

2.10 156.58
2.10 75.35
111.47
343.39 m2

2.10 156.58
2.10 75.35
111.47
343.39 m2

12.00 nos
COST ESTIMATE OF SEPTIC TANK

Type of Building :- Septic Tank Civil Works


S.No. Description Unit Quantity Rate Amount Remarks
1 EARTH WORK
1 EARTH WORK
1.1 Surface dressing and Top soil cutting with 150 to 200 mm
depth including disposing the surplus excvated earth within
the premises for layout & setting out of building as per
drawing & specification. m2 140.00 15.34 2,147.74
1.2 Earthwork in excavation in all kinds of soil and diposing lead
up to 30m including dressing of sides, ramming of bottom,
watering, ramming, consolidation and dressing, with all
necessary shoring and dewatering as well as backfilling the
trench and compact.
m3 318.50 480.91 153,168.88
2 CONCRETE WORK -
2.1 Supplying mixing, placing, compacting & curing of
reinforced cement concrete including plastisizer admixture
exluding the cost of form work and reinforcement. -
a) M20 (1 Cement : 1.5 Sand : 3 coarse aggregate) m3 14.00 15,241.01 213,374.16
a) M10 (1 Cement : 3 Sand : 6 coarse aggregate) m3 10.50 10,764.62 113,028.52
2.2 Supplying, fixing, cutting, bending, binding and placing in
position steel reinforcement bar including the cost of 14
gauge galvanized iron binding wire all complete as per
drawing, specification and approval of engineer. -
a) Tor Steel kg 140.00 98.52 13,793.11
2.3 Providing, placing, fixing centering and shuttering of
plywood or steel form work for slabs, walls, columns, lintel
and beams (with necessary provision of extension of
reinforcement of wall ties) and other RCC works including
nails, propping supports and bracings of steel pipes
including lead & lift at any height & removal and disposal of
the same all complete as per specification & approval of
engineer.
m2 140.00 666.01 93,242.04
-
3 BRICKWORK -
3.1 Providing & laying brick masonary using first class chimney
made bricks with 1:4 cement sand mortar including
scaffolding, curing, cleaning, and racking out mortar joints &
making ducts, recesses where required as per drawing,
specification & approval of engineer.
m3 59.92 13,422.32 804,250.65
3.2 Dry brick soling in foundation and floors with first class
chimney made bricks in true line & level including watering,
compacting etc. all complete as per drawing, specification &
instruction. -
a) On flat m2 140.00 897.99 125,717.97
4 FLOOR FINISH -
4.1 Providing, mixing, laying and compacting 20 to 25mm thick
cement and screed (1:4) on floors in true line & level
including curing as drawing, specification & instruction. m2 111.47 602.08 67,112.65
4.2 Providing, mixing, laying neat cement punning on floors in
true line & level including curing as drawing, specification &
instruction. m2 343.39 242.30 83,203.96
5 PLASTER AND FINISHING WORK -
5.1 Providing and laying 12.5mm thick plaster on wall with 1:4
cement sand mortar in perfect line and level including
scaffolding, curing etc. all complete as per drawing,
specification & instruction. m2 343.39 342.13 117,484.14
6 Miscellaneous work -
6.1 CI manhole cover 600 mm* 600 mm medium quality Nos 12.00 4,070.00 48,840.00
Total 1,835,363.83
S.No. Description Quantity Unit Rate

Supplying, fitting and fixing urine bucket wall hanging


1 with with cement mortar (1:4) finishing with neat
cement on wall with flushing system. 90 No. 4174

Supplying, fitting and fixing 72x37x76cm size toilet


seat(commord) with siphon s-trap with cement
mortar (1:4) finishing with neat cement on bottom.
2 Cutting R.C slab with reinforcement if any, for setting
of commord. Supplying fitting, fixing 15 litres capacity
flushing cisterns on a pair of brackets including
painting two coats and making 12 mm diameter wipe
joints with 12 mm diameter lead pipe supplied, fitted,
fixed at one end with 12 mm diameter G.I. pipe and at
other end with cistern . 84 No. 20389

3 Supplying, fitting and fixing Ariel Pedestal Basin of


55X40X79 cm size with cement mortar (1:4) finishing
with neat cement on wall with flushing system. 101 No. 8348

4
Supplying,fitting ,fixing multi floor trap 4" w/o jali
75mm. 124 No. 470.25

Supplying, fitting, fixing 100mm diameter H.C.I. yard


5 gully 15cmx10cm with 95cm including construction
of brick chamber as per drawing complete and
making connection with 100mm diameter
wastewater pipe 30 No. 1000

6 Supplying, fitting, fixing tee outlet bell-mouth for


ventilation and making the bell-mouth with cement
mortar(1:4) finished smooth with neat cement 32 No. 300

7 Supplying, fitting, fixing 100mm diameter bell-mouth,


PVC pipe trap with tee outlet 32 No. 300
8 uPVC Soil Pipe
Supplying, fitting, fixing 100mm diameter uPVC soil
pipe 339.896 RM 742
Supplying, fitting, fixing 150mm diameter uPVC soil
pipe 290.444 RM 1542
Supplying, fitting, fixing 200mm diameter uPVC soil
pipe
Supplying, fitting, fixing 250mm diameter uPVC soil 256.718 RM 2431
pipe 34.013 RM 3000
9 uPVC Wastewater Pipe
Supplying, fitting, fixing 75mm diameter uPVC
wastewater pipe 612.992 RM 351
Supplying, fitting, fixing 100mm diameter uPVC
wastewater pipe 136.15 RM 742
Supplying, fitting, fixing 150mm diameter uPVC
wastewater pipe 408.18 RM 1542
Supplying, fitting, fixing 200mm diameter uPVC
wastewater pipe 39.64 RM 2431
10 Apron Drain
Providing, mixing, laying and finishing concrete
surface drain including providing MS grating 916.52 RM 500
Supplying, fitting, fixing 150mm diameter uPVC
wastewater pipe 67.68 RM 1542
11 Supplying, fitting, fixing 100mm diameter cowl in
vent pipe 32 No. 87
12 90° elbow
Supplying, fitting, fixing 100mm 90° elbow 35 No. 200
Supplying, fitting, fixing 75 mm 90° elbow 88 No. 108
13 Tee
Supplying, fitting, fixing 100mm tee 62 No. 279

Supplying, fitting, fixing 75 mm tee 274 No. 147

Supplying, fitting, fixing 100 mm 45° tee 32 No. 363


14 Manhole

Construction of wastewater manhole 90 cmx90 cmx1


to 1.4m average depth with brick masonry (1:6) 40 No. 15000

Construction of soil manhole 90 cmx90 cmx1 to 1.4m


average depth with brick masonry (1:6) 32 No. 15000

Labour-charge for making connections of 100m


15
diameter soil and 50mm diameter antisiphonage ppr
with siphon trap in W.C. and Bath rooms 84 No. 500
16 Charges for service connection 1 LS 1500000

Total
Contengencies 10%

Grand Total
Amount
Nrs.

375660

1712676

843148

58311

30000

9600

9600

0
252202.8
447864.6
624081.5
102039
215160.2

101023.3

629413.6

96364.84

458260

104362.6

2784

7000
9504

17298

40278

11616

600000

480000

42000

1500000

8780247
878024.7

9658272
Amount
S.No. Description Quantity Unit Rate
Nrs.
Supplying, fitting, fixing gum metal
1 wheel (peets) valve of approved 5 No. 13833 69165
quality
2 Basin swan neck pillar cock 101 No. 1234 124634

3 12mm diameter Bib cock 84 No. 1361 114324

4 Angular stop cock 275 No. 1213 333575

5 Ball valve

Ball valve 25mm 50 No. 805 40250

Ball valve 50mm 20 No. 3888 77760


6 Ball valve-handle (approximate) 150 No. 350 52500

7 Stopcock

25 mm diameter PPR stopcock with


100 No. 392 39200
all specials

50mm diameter PPR stopcock with


50 No. 845 42250
all specials for fire fighting

75 mm diameter PPR stopcock with


15 No. 1269 19035
all specials

8 90° elbow

Supplying, fitting, fixing 12mm 90°


250 No. 9 2250
PPR elbow

Supplying, fitting, fixing 25 mm 90°


97 No. 19 1843
PPR elbow

Supplying, fitting, fixing 50 mm 90°


20 No. 115 2300
PPR elbow

Supplying, fitting, fixing 75 mm 90°


15 No. 380 5700
PPR elbow

9 Tee

Supplying, fitting, fixing 25 mm 90°


220 No. 23 5060
PPR tee
Supplying, fitting, fixing 37 mm 90°
15 No. 78 1170
PPR tee

Supplying, fitting, fixing 50 mm 90°


70 No. 133 9310
PPR tee

Supplying, fitting, fixing 75 mm 90°


10 No. 423 4230
PPR tee

Supplying, fitting, fixing 12 mm PPR


10 200 No. 92 18400
Coupler

11 PPR pipe

Supplying, fitting, fixing 12mm PPR


258.585 RM 76 19652.46
pipe making all connections

Supplying, fitting, fixing 25mm PPR


429.551 RM 118 50687.02
pipe making all connections

Supplying, fitting, fixing 37mm PPR


298.068 RM 298 88824.26
pipe making all connections

Supplying, fitting, fixing 50mm PPR


772.543 RM 462 356914.9
pipe making all connections

Supplying, fitting, fixing 75mm PPR


508.589 RM 1041 529441.1
pipe making all connections

Supplying, fitting, fixing Gun Metal


fire hydrant Landing Valve
12 30 No. 10000 300000
(Safeguard India or Eq.) for fire
fighting making all connections

Thermal resisting pipe 37mm for fire


13 900 RM 1000 900000
fighting @ 30m each connection

Supplying,Providing,fixing 2Hp
14 2 No. 29233 58466
Water Pump

15 Charges for service connection 1 LS 1500000 1500000

Total 4766942

Contengencies 10% 476694.2

Grand Total 5243636


RATE ANALYSIS

Lalitp
District :
ur
2073/2
F/Y :
074

CIVIL WORKS :

Contents
CATE
GORI
ES WORKS
A: Site clearance Works
B: Earth cutting and Filling Works
C: Brick Works
D: Stone Works
E: Cement Concrete Works
F: Form Works
G: Roofing Works
H: Wood Works
I: Flooring Works
J: Plastering Works
K: Painting Works
L: Pointing Works
M: Water Proofing Works
N: Maintenance works
O: Iron (Steel) Works
P: Miscellaneous Works

2073 Bhadra

A. Site clearance Works


1. Tree Lawn ,Branch seperation etc. with 15m Lead. (1nos)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: Unskilled 0.130 Nos. 667.00 86.71 86.71
Actual rate 86.71
Rate 15% contractor's overhead 13.01
Per no Total 99.72
86.71

2. Excavation of roots of trees, with disposal within 15m Lead. (1nos)


Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: Unskilled 0.400 Nos. 667.00 266.80 266.80
Actual rate 266.80
Rate 15% contractor's overhead 40.02
Per no Total 306.82
266.80

3. Surface dressing, Pit filling, mud cutting works etc, (1sqm/10.76 sft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: Unskilled 0.010 Nos. 667.00 6.67 6.67
Actual rate 6.67
Rate 15% contractor's overhead 1.00
Per sqm. Per sft. Total 7.67
6.67 0.62

4. Removal of grasses, small trees, levelling of undulated ground, landscaping all complete
work, and disposal existing earth materials away from construction site (thickness 15- 20 cm.)
(10sqm)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: Unskilled 0.230 Nos. 667.00 153.41 153.41
Actual rate 153.41
Rate 15% contractor's overhead 23.01
Per sqm. Per sft. Total 176.42
15.34 1.43

B. Earth work in excavation and filling


5. Earth work in excavation in soft clay/silt including 10m hauling, disposing (1cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: Coolies 0.700 Nos. 667.00 466.90 466.90
Tools & Equipments 3% of total labour cost 14.01 14.01
Actual rate 480.91
Rate 15% contractor's overhead 72.14
Per cum. Per cft. Total 553.04
480.91 13.63

6. Earth work in excavation in hard soil soft rocks including 10m hauling, dis (1cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: Coolies 0.800 Nos. 667.00 533.60 533.60
Tools & Equipments 3% of total labour cost 16.01 16.01
Actual rate 549.61
Rate 15% contractor's overhead 82.44
Per cum. Per cft. Total 632.05
549.61 15.58

7. Earth back filling with compaction in 6" layer with sprinkling water , trans ( 1cu.m/35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
a) Coolies 0.500 Nos. 667.00 333.50 333.50
Actual rate 333.50
Rate 15% contractor's overhead 50.03
Per cum. Per cft. Total 383.53
333.50 9.45

8. Earth filling with compaction in 6" layer without sprinkling water, transp ( 1cu.m/35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
a) Coolies 0.250 Nos. 667.00 166.75 166.75
Actual rate 166.75
Rate 15% contractor's overhead 25.01
Per cum. Per cft. Total 191.76
166.75 4.73

9. Pumping out water from trench -Put Qty according to capacity of pumpset ( 5000L/0.5 cum)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
a) pump
Hours 0.500 Hours 200.00 100.000 100.000
Actual rate 100.000
Rate 15% contractor's overhead 15.000
Per 5000L Per Lit. Total 115.000
100.00 0.02

10. Sand filling with compaction in 6" layer, watering etc. transporting from ( 1cu.m/35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Coolies 0.700 Nos. 667.00 466.90 466.90
Materials Sand 1.100 cu.m. 2787.12 3065.83 3065.83
Actual rate 3532.73
Rate 15% contractor's overhead 529.91
Per cum. Per cft. Total 4062.64
3532.73 100.13

C. Brick & stone works


11. Brick work in 1:3 cement mortar in Ground Floor using machine made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.50 Nos. 908.00 1362.00
b) Unskilled 2.20 Nos. 667.00 1467.40
c) Unskilled( 0.20 Nos. 667.00 133.40 2962.80
Bricks 530.000 Nos. 15.30 8109.00
Materials Cement 0.130 MT 15940.00 2072.20
Sand 0.270 Cub.M. 2787.12 752.52 10933.72
Sundries 3% of (c) 4.00 4.00
Actual rate 13900.52
Rate 15% contractor's overhead 2085.08
Per cum. Per cft. Total 15985.60
13900.52 394.01

12. Brick work in 1:3 c/s mortar above Ground Floor using machine made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.50 Nos. 908.00 1362.00
b) Unskilled 2.20 Nos. 667.00 1467.40
c) Unskilled 0.70 Nos. 667.00 466.90 3296.30
Bricks 530.000 Nos. 15.30 8109.00
Materials Cement 0.130 MT 15940.00 2072.20
Sand 0.270 Cub.M. 2787.12 752.52 10933.72
Sundries 3% of (c) 14.01 14.01
Actual rate 14244.03
Rate 15% contractor's overhead 2136.60
Per cum. Per cft. Total 16380.63
14244.03 403.74

13. Brick work in 1:4 cem mortar in Ground Floor using machine made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.50 Nos. 908.00 1362.00
b) Unskilled 2.20 Nos. 667.00 1467.40
c) Unskilled 0.20 Nos. 667.00 133.40 2962.80
Bricks 530.000 Nos. 15.30 8109.00
Materials Cement 0.100 MT 15940.00 1594.00
Sand 0.270 Cub.M. 2787.12 752.52 10455.52
Sundries 3% of (c) 4.00 4.00
Actual rate 13422.32
Rate 15% contractor's overhead 2013.35
Per cum. Per cft. Total 15435.67
13422.32 380.45

14. Brick work in 1:4 cem mortar above Ground Floor using machine made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.50 Nos. 908.00 1362.00
b) Unskilled 2.20 Nos. 667.00 1467.40
c) Unskilled( 0.70 Nos. 667.00 466.90 3296.30
Bricks 530.000 Nos. 15.30 8109.00
Materials Cement 0.100 MT 15940.00 1594.00
Sand 0.270 Cub.M. 2787.12 752.52 10455.52
Sundries 3% of (c) 14.01 14.01
Actual rate 13765.83
Rate 15% contractor's overhead 2064.87
Per cum. Per cft. Total 15830.70
13765.83 390.19

15. B/W in 1:5 cement mortar on Ground Floor using machine made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.50 Nos. 908.00 1362.00
b) Unskilled 2.20 Nos. 667.00 1467.40
c) Unskilled( 0.20 Nos. 667.00 133.40 2962.80
Bricks 530.000 Nos. 15.30 8109.00
Materials Cement 0.090 MT 15940.00 1434.60
Sand 0.310 Cub.M. 2787.12 864.01 10407.61
Sundries 3% of (c) 4.00 4.00
Actual rate 13374.41
Rate 15% contractor's overhead 2006.16
Per cum. Per cft. Total 15380.57
13374.41 379.09

16. B/W in 1:5 cement mortar above Ground Floor using machine made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.50 Nos. 908.00 1362.00
b) Unskilled 2.20 Nos. 667.00 1467.40
c) Unskilled( 0.70 Nos. 667.00 466.90 3296.30
Bricks 530.000 Nos. 15.30 8109.00
Materials Cement 0.090 MT 15940.00 1434.60
Sand 0.310 Cub.M. 2787.12 864.01 10407.61
Sundries 3% of (c) 14.01 14.01
Actual rate 13717.91
Rate 15% contractor's overhead 2057.69
Per cum. Per cft. Total 15775.60
13717.91 388.83

17. B/W in 1:6 cement mortar in Ground Floor using machine made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.50 Nos. 908.00 1362.00
b) Unskilled 2.20 Nos. 667.00 1467.40
c) Unskilled 0.20 Nos. 667.00 133.40 2962.80
Bricks 530.000 Nos. 15.30 8109.00
Materials Cement 0.070 MT 15940.00 1115.80
Sand 0.300 Cub.M. 2787.12 836.14 10060.94
Sundries 3% of (c) 4.00 4.00
Actual rate 13027.74
Rate 15% contractor's overhead 1954.16
Per cum. Per cft. Total 14981.90
13027.74 369.27

18. B/W in 1:6 cement mortar above Ground Floor using machine made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 2.200 Nos. 667.00 1467.40
c)
Unskilled(f
or
scafolding) 0.700 Nos. 667.00 466.90 3296.30
Bricks 530.000 Nos. 15.30 8109.00
Materials Cement 0.070 MT 15940.00 1115.80
Sand 0.300 Cub.M. 2787.12 836.14 10060.94
Sundries 3% of (c) 14.01 14.01
Actual rate 13371.24
Rate 15% contractor's overhead 2005.69
Per cum. Per cft. Total 15376.93
13371.24 379.00
19. Brick work in 1:3 cement mortar in ground floor using chimney made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 2.200 Nos. 667.00 1467.40
c)
Unskilled(f
or
scafolding) 0.200 Nos. 667.00 133.40 2962.80
Bricks 560.000 Nos. 14.00 7840.00
Materials Cement 0.130 MT 15940.00 2072.20
Sand 0.270 Cub.M. 2787.12 752.52 10664.72
Sundries 3% of (c) 4.00 4.00
Actual rate 13631.52
Rate 15% contractor's overhead 2044.73
Per cum. Per cft. Total 15676.25
13631.52 386.38

20. Brick work in 1:3 cement mortar above ground floor using chimney made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 2.200 Nos. 667.00 1467.40
c)
Unskilled(f
or
scafolding) 0.700 Nos. 667.00 466.90 3296.30
Bricks 560.000 Nos. 14.00 7840.00
Materials Cement 0.130 MT 15940.00 2072.20
Sand 0.270 Cub.M. 2787.12 752.52 10664.72
Sundries 3% of (c) 14.01 14.01
Actual rate 13975.03
Rate 15% contractor's overhead 2096.25
Per cum. Per cft. Total 16071.28
13975.03 396.12

21. Brick work in 1:4 cement mortar in ground floor using chimney made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 2.200 Nos. 667.00 1467.40
c)
Unskilled(f
or
scafolding) 0.200 Nos. 667.00 133.40 2962.80
Bricks 560.000 Nos. 14.00 7840.00
Materials Cement 0.100 MT 15940.00 1594.00
Sand 0.280 Cub.M. 2787.12 780.39 10214.39
Sundries 3% of (c) 4.00 4.00
Actual rate 13181.20
Rate 15% contractor's overhead 1977.18
Per cum. Per cft. Total 15158.37
13181.20 373.62

22. Brick work in 1:4 cement mortar above ground floor using chimney made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 2.200 Nos. 667.00 1467.40
c)
Unskilled(f
or
scafolding) 0.700 Nos. 667.00 466.90 3296.30
Bricks 560.000 Nos. 14.00 7840.00
Materials Cement 0.100 MT 15940.00 1594.00
Sand 0.280 Cub.M. 2787.12 780.39 10214.39
Sundries 3% of (c) 14.01 14.01
Actual rate 13524.70
Rate 15% contractor's overhead 2028.71
Per cum. Per cft. Total 15553.41
13524.70 383.35

23 . Half brick thick brick work in 1:4 cement mortar in all height using chimney made brick & including 30m trasportation
(1
sqm/10.76
sft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.350 Nos. 908.00 317.80
b) Unskilled 0.510 Nos. 667.00 340.17
c)
Unskilled(f
or
scafolding) 0.161 Nos. 667.00 107.39 765.36
Bricks 73.000 Nos. 14.00 1022.00
Materials Cement 0.010 MT 15940.00 159.40
Sand 0.040 Cub.M. 2787.12 111.48 1292.88
Sundries 3% of (c) 3.22 3.22
Actual rate 2061.46
Rate 15% contractor's overhead 309.22
Per sqm. Per sft. Total 2370.68
2061.46 191.59

24. Brick work in 1:6 cement mortar in ground floor using chimney made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 2.200 Nos. 667.00 1467.40
c)
Unskilled(f
or
scafolding) 0.200 Nos. 667.00 133.40 2962.80
Bricks 560.000 Nos. 14.00 7840.00
Materials Cement 0.070 MT 15940.00 1115.80
Sand 0.300 Cub.M. 2787.12 836.14 9791.94
Sundries 3% of (c) 4.00 4.00
Actual rate 12758.74
Rate 15% contractor's overhead 1913.81
Per cum. Per cft. Total 14672.55
12758.74 361.64

25. Brick work in 1:6 cement mortar in above ground floor using chimney made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 2.200 Nos. 667.00 1467.40
c)
Unskilled(f
or
scafolding) 0.700 Nos. 667.00 466.90 3296.30
Bricks 560.000 Nos. 14.00 7840.00
Materials Cement 0.070 MT 15940.00 1115.80
Sand 0.300 Cub.M. 2787.12 836.14 9791.94
Sundries 3% of (c) 14.01 14.01
Actual rate 13102.24
Rate 15% contractor's overhead 1965.34
Per cum. Per cft. Total 15067.58
13102.24 371.38

26. Brick work in 1:1:1 Lime Sand Surki in ground floor using chimney made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 2.200 Nos. 667.00 1467.40
c)
Unskilled(f
or
scafolding) 0.200 Nos. 667.00 133.40 2962.80
Bricks 560.000 Nos. 14.00 7840.00
Materials Lime 0.140 Cub.M. 16800.00 2352.00
Sand 0.140 Cub.M. 2787.12 390.20
Surki 0.140 Cub.M. 1541.03 215.74 10797.94
Sundries 3% of (c) 4.00 4.00
Actual rate 13764.74
Rate 15% contractor's overhead 2064.71
Per cum. Per cft. Total 15829.45
13764.74 390.16

27. B/W in 1:1:1 Lime Sand Surki above Gnd Floor using chimney made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 2.200 Nos. 667.00 1467.40
c)
Unskilled(f
or
scafolding) 0.700 Nos. 667.00 466.90 3296.30
Bricks 560.000 Nos. 14.00 7840.00
Materials Lime 0.140 Cub.M. 16800.00 2352.00
Sand 0.140 Cub.M. 2787.12 390.20
Surki 0.140 Cub.M. 1541.03 215.74 10797.94
Sundries 3% of (c) 14.01 14.01
Actual rate 14108.25
Rate 15% contractor's overhead 2116.24
Per cum. Per cft. Total 16224.49
14108.25 399.89

28. Brick work in 1:2 Lime Surki in ground floor using chimney made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 2.200 Nos. 667.00 1467.40
c)
Unskilled(f
or
scafolding) 0.200 Nos. 667.00 133.40 2962.80
Bricks 560.000 Nos. 14.00 7840.00
Materials Lime 0.140 Cub.M. 16800.00 2352.00
Surki 0.280 Cub.M. 1541.03 431.49 10623.49
Sundries 3% of (c) 4.00 4.00
Actual rate 13590.29
Rate 15% contractor's overhead 2038.54
Per cum. Per cft. Total 15628.83
13590.29 385.21

29. B/W in 1:2 Lime Surki above ground floor using chimney made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 2.200 Nos. 667.00 1467.40
c)
Unskilled(f
or
scafolding) 0.700 Nos. 667.00 466.90 3296.30
Bricks 560.000 Nos. 14.00 7840.00
Materials Lime 0.140 MT 16800.00 2352.00
Surki 0.280 Cub.M. 1541.03 431.49 10623.49
Sundries 3% of (c) 14.01 14.01
Actual rate 13933.80
Rate 15% contractor's overhead 2090.07
Per cum. Per cft. Total 16023.86
13933.80 394.95

30. Brick work in mud mortar in ground floor using chimney made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Unskilled 1.700 Nos. 667.00 1133.90
c)Unskilled(
for
scafolding) 0.200 Nos. 667.00 133.40 2175.30
Bricks 560.000 Nos. 14.00 7840.00
Materials Mud 0.420 Cub.M. 260.00 109.20 7949.20
Sundries 3% of (c) 4.00 4.00
Actual rate 10128.50
Rate 15% contractor's overhead 1519.28
Per cum. Per cft. Total 11647.78
10128.50 287.09

31. Brick work in mud mortar above ground floor using chimney made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Unskilled 1.700 Nos. 667.00 1133.90
c)Unskilled(
for
scafolding) 0.700 Nos. 667.00 466.90 2508.80
Bricks 560.000 Nos. 14.00 7840.00
Materials Mud 0.420 Cub.M. 260.00 109.20 7949.20
Sundries 3% of (c) 14.01 14.01
Actual rate 10472.01
Rate 15% contractor's overhead 1570.80
Per cum. Per cft. Total 12042.81
10472.01 296.83

D. Stone Works
32. Rubble stone masonryworks in 1:3 c/s mortar & including 10m trasportatio( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 5.000 Nos. 667.00 3335.00 4697.00
Cement 0.194 MT 15940.00 3092.36
Materials Sand 0.420 Cub.M. 2787.12 1170.59
Blockstone 1.000 Cub.M. 2116.80 2116.80
Bundstone 0.100 Cub.M. 2116.80 211.68 6591.43
Actual rate 11288.43
Rate 15% contractor's overhead 1693.26
Per cum. Per cft. Total 12981.69
11288.43 319.97

33. Rubble stone masonryworks in 1:4 c/s mortar & including 10m trasportatio( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 5.000 Nos. 667.00 3335.00 4697.00
Cement 0.159 MT 15940.00 2534.46
Materials Sand 0.440 Cub.M. 2787.12 1226.33
Blockstone 1.000 Cub.M. 2116.80 2116.80
Bundstone 0.100 Cub.M. 2116.80 211.68 6089.27
Actual rate 10786.27
Rate 15% contractor's overhead 1617.94
Per cum. Per cft. Total 12404.21
10786.27 305.73

34. Rubble stone masonryworks in 1:6 c/s mortar & including 10m trasportati ( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 5.000 Nos. 667.00 3335.00 4697.00
Cement 0.106 MT 15940.00 1689.64
Materials Sand 0.470 Cub.M. 2787.12 1309.95
Blockstone 1.000 Cub.M. 2116.80 2116.80
Bundstone 0.100 Cub.M. 2116.80 211.68 5328.07
Actual rate 10025.07
Rate 15% contractor's overhead 1503.76
Per cum. Per cft. Total 11528.83
10025.07 284.16

35. Dry stone Rubble masonryworks & including 30m trasportation ( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Unskilled 2.000 Nos. 667.00 1334.00 2242.00
Materials Blockstone 1.000 Cub.M. 2116.80 2116.80
Bundstone 0.100 Cub.M. 2116.80 211.68 2328.48
Actual rate 4570.48
Rate 15% contractor's overhead 685.57
Per cum. Per cft. Total 5256.05
4570.48 129.55

36. Rubble stone masonry works in mud mortar & including 30m trasportati ( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Unskilled 2.250 Nos. 667.00 1500.75 2408.75
Materials Blockstone 1 Cub.M. 2116.80 2116.8
Bundstone 0.1 Cub.M. 2116.80 211.68
Mud 0.42 Cub.M. 260.00 109.2 2437.68
Actual rate 4846.43
Rate 15% contractor's overhead 726.96
Per cum. Per cft. Total 5573.39
4846.43 137.37

37. Rubble stone masonry works in 1:3 cement mortar on arch and lintels & including( 130m
cu.m./35.28
tr cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.000 Nos. 908.00 1816.00
b) Unskilled 5.400 Nos. 667.00 3601.80 5417.80
Cement 0.194 MT 15940.00 3092.36
Materials Sand 0.420 Cub.M. 2787.12 1170.59
Blockstone 1.000 Cub.M. 2116.80 2116.80
Bundstone 0.100 Cub.M. 2116.80 211.68 6591.43
Actual rate 12009.23
Rate 15% contractor's overhead 1801.38
Per cum. Per cft. Total 13810.61
12009.23 340.40

38. Rubble stone masonry works in 1:4 cement mortar on arch and lintels & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.000 Nos. 908.00 1816.00
b) Unskilled 5.400 Nos. 667.00 3601.80 5417.80
Cement 0.159 MT 15940.00 2534.46
Materials Sand 0.450 Cub.M. 2787.12 1254.20
Blockstone 1.000 Cub.M. 2116.80 2116.80
Bundstone 0.100 Cub.M. 2116.80 211.68 6117.14
Actual rate 11534.94
Rate 15% contractor's overhead 1730.24
Per cum. Per cft. Total 13265.19
11534.94 326.95

39. Rubble stone masonry works in 1:6 cement mortar on arch and lintels & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.000 Nos. 908.00 1816.00
b) Unskilled 5.400 Nos. 667.00 3601.80 5417.80
Cement 0.106 MT 15940.00 1689.64
Materials Sand 0.470 Cub.M. 2787.12 1309.95
Blockstone 1.000 Cub.M. 2116.80 2116.80
Bundstone 0.100 Cub.M. 2116.80 211.68 5328.07
Actual rate 10745.87
Rate 15% contractor's overhead 1611.88
Per cum. Per cft. Total 12357.75
10745.87 304.59

40. Dressed stone masonry works in 1:6 cement mortar ( 10 cu.m./352.8 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 15.000 Nos. 908.00 13620.00
b) Unskilled 30.000 Nos. 667.00 20010.00 33630.00
Cement 0.400 MT 15940.00 6376.00
Materials Sand 4.200 Cub.M. 2787.12 11705.90
Dressed
stone 11.000 Cub.M. 2469.60 27165.60 45247.50
Actual rate 78877.50
Rate 15% contractor's overhead 11831.63
Per cum. Per cft. Total 90709.13
7887.75 223.58

41. Stone filling on trench and levelling transporting upto 30m ( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.000 Nos. 908.00 0.00
b) Unskilled 1.500 Nos. 667.00 1000.50 1000.50
Materials Blockstone 1.000 Cub.M. 2116.80 2116.80
Bundstone 0.200 Cub.M. 2116.80 423.36 2540.16
Actual rate 3540.66
Rate 15% contractor's overhead 531.10
Per cum. Per cft. Total 4071.76
3540.66 100.36

E. Cement Concrete Work

42. 1:4:8 P.C.C. work in foundation, walls and floor,etc. including material collection and transportation upto 30m
( 1 cu.m./ 35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Coolies 4.000 Nos. 667.00 2668.00 3576.00
Materials Cement 0.170 MT 15940.00 2709.80
Sand 0.470 Cub M 2787.12 1309.95
40 mm
aggregate 0.650 Cub M 2646.00 1719.90
20 mm
aggregate 0.240 Cub M 2716.56 651.97 6391.62
Actual rate 9967.62
Rate 15% contractor's overhead 1495.14
Per cum. Per cft. Total 11462.76
9967.62 282.53

43. 1:3:6 P.C.C. work in foundation, and floor, including material collection and transportation upto 30m
( 1 cu.m./ 35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Coolies 4.000 Nos. 667.00 2668.00 3576.00
Materials Cement 0.220 MT 15940.00 3506.80
Sand 0.470 Cub M 2787.12 1309.95
40 mm
aggregate 0.650 Cub M 2646.00 1719.90
20 mm
aggregate 0.240 Cub M 2716.56 651.97 7188.62
Actual rate 10764.62
Rate 15% contractor's overhead 1614.69
Per cum. Per cft. Total 12379.31
10764.62 305.12

44. 1:2:4 P.C.C. work in foundation and floor including material collection & transportation upto 30m
( 1 cu.m./ 35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Coolies 4.000 Nos. 667.00 2668.00 3576.00
Materials Cement 0.320 MT 15940.00 5100.80
Sand 0.445 Cu.m. 2787.12 1240.27
40 mm
aggregate 0.520 Cu.m. 2646.00 1375.92
20 mm
aggregate 0.220 Cu.m. 2716.56 597.64
10 mm
aggregate 0.110 Cu.m. 2540.16 279.42 8594.05
Actual rate 12170.05
Rate 15% contractor's overhead 1825.51
Per cum. Per cft. Total 13995.56
12170.05 344.96

45. 1:2:4 P.C.C. work in superstructure slab, beams, columns, lintels etc. with transportation up to 30m
( 1 cu.m./ 35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.800 Nos. 908.00 726.40
b) Coolies 7.000 Nos. 667.00 4669.00 5395.40
Materials Cement 0.320 MT 15940.00 5100.80
Sand 0.445 Cub M 2787.12 1240.27
40 mm
aggregate 0.520 Cub M 2646.00 1375.92
20 mm
aggregate 0.220 Cub M 2716.56 597.64
10 mm
aggregate 0.110 Cub M 2540.16 279.42 8594.05
Actual rate 13989.45
Rate 15% contractor's overhead 2098.42
Per cum. Per cft. Total 16087.87
13989.45 396.53

46. 1:1.5:3 P.C.C. work in superstructure slab, beams, columns, lintels etc. with transportation up to 30m
( 1 cu.m./ 35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.800 Nos. 908.00 726.40
b) Coolies 7.000 Nos. 667.00 4669.00 5395.40
Materials Cement 0.400 MT 15940.00 6376.00
Sand 0.425 Cub M 2787.12 1184.53
20 mm
aggregate 0.570 Cub M 2716.56 1548.44
10 mm
aggregate 0.290 Cub M 2540.16 736.65 9845.61
Actual rate 15241.01
Rate 15% contractor's overhead 2286.15
Per cum. Per cft. Total 17527.16
15241.01 432.00

47. 1:1:2 P.C.C. work in superstructure slab, beams, columns, lintels etc. with transportation up to 30m
(1 cu.m./ 35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.800 Nos. 908.00 726.40
b) Coolies 7.000 Nos. 667.00 4669.00 5395.40
Materials Cement 0.610 MT 15940.00 9723.40
Sand 0.425 Cub M 2787.12 1184.53
20 mm
aggregate 0.640 Cub M 2716.56 1738.60
10 mm
aggregate 0.210 Cub M 2540.16 533.43 13179.96
Actual rate 18575.36
Rate 15% contractor's overhead 2786.30
Per cum. Per cft. Total 21361.66
18575.36 526.51

48. Curtail, bent up, binding of MS bars according to the drawing for RCC and its transportation up to 30m
( 1 MT =1000 kg )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 12.000 Nos. 908.00 10896.00
b) Coolies 12.000 Nos. 667.00 8004.00 18900.00
Tor
steel/MS
Materials bar 1.050 MT 75000.00 78750.00
Binding
Wires 10.000 Kg 87.22 872.20 79622.20
Actual rate 98522.20
Rate 15% contractor's overhead 14778.33
Per mt Per kg Total 113300.53
98522.20 98.52

49. 6.35cm thick Reinforced Brick work in 1:3 cement mortar in superstructure slab, lintels etc. with transportation
upto 30m(for 10 sq.m./ 107.58sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.150 Nos. 908.00 1044.20
b) Coolies 3.000 Nos. 667.00 2001.00 3045.20
Materials Cement 0.100 MT 15940.00 1594.00
Sand 0.200 Cub M 2787.12 557.42
Local
Bricks 377.000 Nos. 14.00 5278.00 7429.42
Actual rate 10474.62
Rate 15% contractor's overhead 1571.19
Per sqm. Per sft Total 12045.82
1047.46 97.37

F. Form Work
50. Form work for beams, slab in structure including, screening, fitting, oiling, dismantling, removing and transportation up to 3
( 10 sq.m./ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.720 Nos. 908.00 1561.76
b) Coolies 2.570 Nos. 667.00 1714.19 3275.95
Wood
(Local/Nor
Materials mal)* 0.070 Cub M 44452.80 3111.70
Nails 2.500 Kg 109.00 272.50 3384.20
Actual rate 6660.15
Rate 15% contractor's overhead 999.02
Per sqm. Per sft. Total 7659.17
666.01 61.91
* Asume that timber and ballies will become unserviceable after being used for 6 Times
\ Qty. of material = 0.526/8 = 0.07 Cu. m.

( 10 sq.m./
51. Column post fitting and dismantling, removing with supplying wood and transporting upto107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 3.748 Nos. 908.00 3403.18
b) Coolies 5.622 Nos. 667.00 3749.87 7153.06
Wood
Materials (Ordinary) 0.070 Cub M 44452.80 3111.70
Nails 2.500 Kg 109.00 272.50 3384.20
Actual rate 10537.25
Rate 15% contractor's overhead 1580.59
Per sqm. Per sft. Total 12117.84
1053.73 97.95

52. Form work for structural beams installlation and dismantling, removing and transporting upto 30m & up to 0.3m Ht of beam
( 10 sq.m./ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 4.000 Nos. 908.00 3632.00
b) Coolies 6.000 Nos. 667.00 4002.00 7634.00
Wood
(Local/Nor
Materials mal)* 0.070 Cub M 44452.80 3111.70
Nails 2.500 Kg 109.00 272.50 3384.20
Actual rate 11018.20
Rate 15% contractor's overhead 1652.73
Per sqm. Per sft. Total 12670.93
1101.82 102.42
53. Form work for structural beams installlation and dismantling, removing and transporting upto 30m
(0.3m to 0.8m Ht of beams) ( 10 sq.m./ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.670 Nos. 908.00 2424.36
b) Coolies 4.000 Nos. 667.00 2668.00 5092.36
Wood
(Local/Nor
Materials mal)* 0.070 Cub M 44452.80 3111.70
Nails 2.500 Kg 109.00 272.50 3384.20
Actual rate 8476.56
Rate 15% contractor's overhead 1271.48
Per sqm. Per sft. Total 9748.04
847.66 78.79

54. Form work for trench shuttering upto 1.5 to 3.0m depth and transporting u (100 sq.m./ 1075.8 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.500 Nos. 908.00 454.00
b) Coolies 1.000 Nos. 667.00 667.00 1121.00
Materials Planks 4.160 Sq M 578.78 2407.72
Walling
Strut Wood
(Normal)* 0.254 Cub M 44452.80 11277.68 13685.40
Actual rate 14806.40
Rate 15% contractor's overhead 2220.96
Per sqm. Per sft. Total 17027.36
148.06 13.76

55. Form work for open trench protection depth over 3.0m and transporting u ( 100 sq.m./ 1075.8 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Coolies 1.750 Nos. 667.00 1167.25 2075.25
Materials Planks 4.160 Sq M 578.78 2407.72
Walling
Strut Wood
(Local/Nor
mal) 0.254 Cub M 44452.80 11277.68 13685.40
Actual rate 15760.65
Rate 15% contractor's overhead 2364.10
Per sqm. Per sft. Total 18124.75
157.61 14.65
G. Roof Covering
56. CGI Sheet Roofing with supplying all materials (26 Gauge medium CGI) (10sq.m / 107.58 sq. ft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.100 Nos. 908.00 998.80
b) Unskilled 1.250 Nos. 667.00 833.75 1832.55
CGI Sheet
(26 Gauge) 12.000 Sq M 369.44 4433.30
8mm Nut
Materials Bolt 30.000 Nos. 28.00 840.00
J-Hook 25.000 Nos. 19.00 475.00
Bitumin
washer 25.000 Nos. 3.00 75.00 5823.30
Actual rate 7655.85
Rate 15% contractor's overhead 1148.38
Per sqm. Per sft. Total 8804.23
765.59 71.16

57.Fixing GI plain Sheet (0.28mm) Ridge cover with supplying all materials (10Rm / 3.28 ft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.000 Nos. 908.00 1816.00
b) Unskilled 3.000 Nos. 667.00 2001.00 3817.00
GI Sheet
(28Gauge) 12.000 R M 304.63 3655.56
8mm Nut
Materials Bolt L.S. 28.00 28.00 3683.56
Actual rate 7500.56
Rate 15% contractor's overhead 1125.08
Per Rm. Per rft. Total 8625.64
750.06 228.68

58. Coloured CGI Sheet (26 Gauge medium) Roofing with supplying all materi(10sq.m / 107.58 sq. ft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.100 Nos. 908.00 998.80
b) Unskilled 1.250 Nos. 667.00 833.75 1832.55
CGI
Sheet(0.35
* mm th total) 12.000 Sq M 455.56 5466.73
8mm Nut
Materials Bolt 30.000 Nos. 28.00 840.00
J-Hook 25.000 Nos. 19.00 475.00
Bitumin
washer 25.000 Nos. 3.00 75.00 6856.73
Actual rate 8689.28
Rate 15% contractor's overhead 1303.39
Per sqm. Per sft. Total 9992.68
868.93 80.77
* 0.37mm base metal thickness(i.e.add 2mm for total thickness)

59.Fixing Coloured GI plain Sheet (0.35mm) Ridge cover with supplying all m
(10Rm / 3.28 ft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.000 Nos. 908.00 1816.00
b) Unskilled 3.000 Nos. 667.00 2001.00 3817.00
GI
Sheet(0.43
mm) 12.000 R M 439.11 5269.32
8mm Nut
Materials Bolt L.S. 28.00 28.00 5297.32
Actual rate 9114.32
Rate 15% contractor's overhead 1367.15
Per Rm. Per rft. Total 10481.47
911.43 277.88

60.1:1:3 (Lime surki brk agg)10cm thick Lime concrete terracing work with
(10sq.m
sup / 107.58 sq. ft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 12.000 Nos. 667.00 8004.00 9366.00
Brick Agg. 1.250 Cub M 1155.77 1444.71
Materials Lime 1.500 Cub M 16800.00 25200.00
Surki 0.400 Cub M 1541.03 616.41 27261.12
Actual rate 36627.12
Rate 15% contractor's overhead 5494.07
Per sqm. Per sft. Total 42121.19
3662.71 340.46

H. Wood Work
61. 20 cm thick wood Ceiling work, plankings with 40x20mm Biding Joint wit(10sq.m / 107.58 sq. ft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.880 Nos. 908.00 1707.04
b) Unskilled 1.500 Nos. 667.00 1000.50 2707.54
Wood Saal 0.260 Cub M 194040.00 50450.40
Materials Nails
40mm 0.400 Kg. 109.00 43.60
screw 160.000 Nos. 1.00 160.00 50654.00
Actual rate 53361.54
Rate 15% contractor's overhead 8004.23
Per sqm. Per sft. Total 61365.77
5336.15 496.02

62. Sal wood work for choukosh[0.9x2.1m size &0.1x0.075m sec( 1cu.m./ 35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 34.000 Nos. 908.00 30872.00
b) Coolies 3.400 Nos. 667.00 2267.80 33139.80
Materials Sal wood 1.100 Cub M 194040.00 213444.00
Hold fast 92.000 Nos. 17.29 1590.29
Screw 184.000 Nos. 1.00 184.00 215218.29
Actual rate 248358.09
Rate 15% contractor's overhead 37253.71
Per cum. Per cft. Total 285611.80
248358.09 7039.63

63. 38 mm thick Salwood solid pannel shutter (size 1.07m x 1.98Rate analysis for 2.114 sq.m. / 22.7255 sft.
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.000 Nos. 908.00 9080.00
b) Coolies 1.000 Nos. 667.00 667.00 9747.00
Materials Sal wood 0.084 Cub M 194040.00 16299.36
100mm
hinges 6.000 Nos. 27.00 162.00
150mm
tower bolt 1.000 No 65.00 65.00
300mm
tower bolt 1.000 No 103.00 103.00
300mm
locking set 1.000 No 252.00 252.00
Handles
(Good
Quality) 2.000 Nos. 46.00 92.00
Screw nails 1.000 LS 20.00 20.00 16993.36
Actual rate 26740.36
Rate 15% contractor's overhead 4011.05
Per sqm. Per sft. Total 30751.41
12649.18 1175.79

64 . Openable glazed shutter with 38 x 75mm sal wood frame & 3 mm thick glass
(for rate analysis 1.829 x 1.22 = 2.23 sq m / 23.97 sft. )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 9.000 Nos. 908.00 8172.00
b) Coolies 0.900 Nos. 667.00 600.30 8772.30
Materials Sal wood 0.049 Cub M 194040.00 9507.96
3 mm glass 1.085 sq.m. 537.50 583.19
75mm
hinges 8.000 Nos. 15.00 120.00
100mm
tower bolt 4.000 Nos. 39.00 156.00
Handles
(Good
Quality) 2.000 Nos. 46.00 92.00
Screw nails 1.000 LS 20.00 20.00 10479.15
Actual rate 19251.45
Rate 15% contractor's overhead 2887.72
Per sqm. Per sft. Total 22139.16
8632.94 802.47

65 . Openable glazed shutter with 38 x 75mm sal wood frame & 4 mm thick glass
(for rate analysis 1.829 x 1.22 = 2.23 sq m / 23.97 sft. )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 9.000 Nos. 908.00 8172.00
b) Coolies 0.900 Nos. 667.00 600.30 8772.30
Materials Sal wood 0.049 Cub M 194040.00 9507.96
4 mm glass 1.085 sq.m. 688.00 746.48
75mm
hinges 8.000 Nos. 15.00 120.00
100mm
tower bolt 4.000 Nos. 39.00 156.00
Handles
(Good
Quality) 2.000 Nos. 46.00 92.00
Screw nails 1.000 LS 20.00 20.00 10642.44
Actual rate 19414.74
Rate 15% contractor's overhead 2912.21
Per sqm. Per sft. Total 22326.95
8706.16 809.27

66. Openable glazed shutter with 38 x 75mm sal wood frame &5 mm thick glass
(for rate analysis 1.829 x 1.22 = 2.23 sq m / 23.97 sft. )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 9.000 Nos. 908.00 8172.00
b) Coolies 0.900 Nos. 667.00 600.30 8772.30
Materials Sal wood 0.049 Cub M 194040.00 9507.96
5 mm glass 1.085 sq.m. 924.50 1003.08
75mm
hinges 8.000 Nos. 15.00 120.00
100mm
tower bolt 4.000 Nos. 39.00 156.00
Handles
(Good
Quality) 2.000 Nos. 46.00 92.00
Screw nails 1.000 LS 20.00 20.00 10899.04
Actual rate 19671.34
Rate 15% contractor's overhead 2950.70
Per sqm. Per sft. Total 22622.04
8821.23 819.97

67 . Openable glazed shutter with 38 x 75mm sal wood frame & 6 mm thick glass
(for rate analysis 1.829 x 1.22 = 2.23 sq m / 23.97 sft. )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 9.000 Nos. 908.00 8172.00
b) Coolies 0.900 Nos. 667.00 600.30 8772.30
Materials Sal wood 0.049 Cub M 194040.00 9507.96
6 mm glass 1.085 sq.m. 1075.00 1166.38
75mm
hinges 8.000 Nos. 15.00 120.00
100mm
tower bolt 4.000 Nos. 39.00 156.00
Handles
(Good
Quality) 2.000 Nos. 46.00 92.00
Screw nails 1.000 LS 20.00 20.00 11062.34
Actual rate 19834.64
Rate 15% contractor's overhead 2975.20
Per sqm. Per sft. Total 22809.83
8894.46 826.78

68. Flush shutter 38mm thick sal wood frame with 4mm thick commercial plywood on both side of shutter
(for rate analysis 1.092 x 2.058 = 2.245sq m/24.13 sft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 7.000 Nos. 908.00 6356.00
b) Coolies 0.700 Nos. 667.00 466.90 6822.90
Materials Sal wood 0.0346 Cub M 194040.00 6713.78
4mm
com.plywoo
d 4.650 sq.m. 247.25 1149.71
100mm
hinges 3.000 Nos. 27.00 81.00
150mm
tower bolt 2.000 Nos. 65.00 130.00
Mortish
lock 1.000 Nos. 404.00 404.00
Screw nails 1.000 LS 20.00 20.00 8498.50
Actual rate 15321.40
Rate Rate 15% contractor's overhead 2298.21
Per sqm. Per sft. Total 17619.61
6824.68 634.38

69.3. Flush shutter 38mm thick sal wood frame with 3mm thick teak plywood on both side of shutter
(for rate analysis 1.092 x 2.058 = 2.245sq m/24.13 sft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 7.000 Nos. 908.00 6356.00
b) Coolies 0.700 Nos. 667.00 466.90 6822.90
Materials Sal wood 0.0346 Cub M 194040.00 6713.78
3mm teak
ply 4.650 sq.m. 602.00 2799.30
100mm
hinges 3.000 Nos. 27.00 81.00
150mm
tower bolt 2.000 Nos. 65.00 130.00
Mortish
lock 1.000 Nos. 404.00 404.00
Screw nails 1.000 LS 20.00 20.00 10148.08
Actual rate 16970.98
Rate Rate 15% contractor's overhead 2545.65
Per sqm. Per sft. Total 19516.63
7559.46 702.68

70. a.38mm thick sal wood shutter with 28 Gauge GI Plain Sheet on both side of shutter
(for rate analysis 1.092 x 2.058 = 2.245sq m/24.13 sft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 7.000 Nos. 908.00 6356.00
b) Coolies 0.700 Nos. 667.00 466.90 6822.90
Materials Sal wood 0.0346 Cub M 194040.00 6713.78
28 Gauge
GI Sheet 4.650 sq.m. 74.98 348.68
100mm
hinges 3.000 Nos. 27.00 81.00
150mm
tower bolt 2.000 Nos. 65.00 130.00
Mortish
lock 1.000 Nos. 404.00 404.00
Screw nails 1.000 LS 20.00 20.00 7697.46
Actual rate 14520.36
Rate Rate 15% contractor's overhead 2178.05
Per sqm. Per sft. Total 16698.42
6467.87 601.21

71. G.I. mosquito proof wire mess (24gauge) shutter works with 38mm thick sal wood frame
(for rate analysis 1.092 x 2.058 = 2.245sq m/24.13 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 5.000 Nos. 908.00 4540.00
b) Coolies 0.500 Nos. 667.00 333.50 4873.50
Materials Sal wood 0.026 Cub M 194040.00 5045.04
24 gau.GI
wiremess 2.130 sq.m. 116.00 247.08
100mm
hinges 3.000 Nos 27.00 81.00
150mm
tower bolt 2.000 Nos 65.00 130.00
Handles
(Good
Quality) 2.000 Nos 46.00 92.00
Spring
(simple) 1.000 No 173.00 173.00
Screw nails 1.000 LS 15.00 15.00 5783.12
Actual rate 10656.62
Rate 15% contractor's overhead 1598.49
Per sqm. Per sft. Total 12255.11
4746.82 441.24

72 . Fixed glazed shutter with 3 mm thick glass (for 1 sq.m 10.76 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.060 Nos. 908.00 54.48
b) Coolies 0.006 Nos. 667.00 4.00 58.48
3 mm thick
Materials glass 1.000 S.m. 537.50 537.50
wooden
listy 4.050 m 28.00 113.40
Screw nails 1.000 LS 15.00 15.00 665.90
Actual rate 724.38
Rate Rate 15% contractor's overhead 108.66
Per sqm. Per sft. Total 833.04
724.38 67.32

73. Fixed glazed shutter with 4 mm thick glass (for 1 sq.m 10.76 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.060 Nos. 908.00 54.48
b) Coolies 0.006 Nos. 667.00 4.00 58.48
4 mm thick
Materials glass 1.000 S.m. 688.00 688.00
wooden
listy 4.050 m 28.00 113.40
Screw nails 1.000 LS 15.00 15.00 816.40
Actual rate 874.88
Rate Rate 15% contractor's overhead 131.23
Per sqm. Per sft. Total 1006.11
874.88 81.31

74. Fixed glazed shutter with 5 mm thick glass ( for 1 sq.m 10.76 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.060 Nos. 908.00 54.48
b) Coolies 0.006 Nos. 667.00 4.00 58.48
5 mm thick
Materials glass 1.000 S.m. 924.50 924.50
wooden
listy 4.050 m 28.00 113.40
Screw nails 1.000 LS 15.00 15.00 1052.90
Actual rate 1111.38
Rate Rate 15% contractor's overhead 166.71
Per sqm. Per sft. Total 1278.09
1111.38 103.29

75. Fixed glazed shutter with 6 mm thick glass (for 1 sq.m 10.76 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.060 Nos. 908.00 54.48
b) Coolies 0.006 Nos. 667.00 4.00 58.48
6 mm thick
Materials glass 1.000 S.m. 1075.00 1075.00
wooden
listy 4.050 m 28.00 113.40
Screw nails 1.000 LS 15.00 15.00 1203.40
Actual rate 1261.88
Rate Rate 15% contractor's overhead 189.28
Per sqm. Per sft. Total 1451.16
1261.88 117.28

76 . Wooden partition with frames of 38x75 mm sections on 0.61x0.915m rooms fixed with commercial ply both side fixing w
9.75mx3.65m=35.58sqm (382.84sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 23.000 Nos. 908.00 20884.00
b) Coolies 2.300 Nos. 667.00 1534.10 22418.10

Materials Wood Local 0.350 Cum 44452.80 15558.48


4mm ply 75.000 sqm 247.25 18543.75
wooden
listy 100.000 Rm 28.00 2800.00
Ordinary
nails 2.000 Kg 109.00 218.00 37120.23
Actual rate 59538.33
Rate Rate 15% contractor's overhead 8930.75
Per sqm. Per sft. Total 68469.08
1673.37 155.52

77 . Wooden partition with frames of 38x75 mm sections on 0.61x0.915m rooms fixed with
12mm thick hard board both side fixing with listy
9.75mx3.65m=35.58sqm (382.84sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 23.000 Nos. 908.00 20884.00
b) Coolies 2.300 Nos. 667.00 1534.10 22418.10
Materials Wood 0.340 Cum 44452.80 15113.95
Hard board 75.000 sqm 451.50 33862.50
wooden
listy 100.000 Rm 28.00 2800.00
Ordinary
nails 2.000 Kg 109.00 218.00 51994.45
Actual rate 74412.55
Rate Rate 15% contractor's overhead 11161.88
Per sqm. Per sft. Total 85574.43
2091.42 194.37

78. Wooden partition with frames of 38x75 mm sections on 0.61x0.915m rooms fixed with
19mm thick planks both side in lap joint
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 30.000 Nos. 908.00 27240.00
b) Coolies 3.000 Nos. 667.00 2001.00 29241.00

Materials Wood Local 1.767 Cum 44452.80 78548.10


wooden
listy 100.000 Rm 28.00 2800.00
Ordinary
nails 2.000 Kg 109.00 218.00 81566.10
Actual rate 110807.10
Rate Rate 15% contractor's overhead 16621.06
Per sqm. Per sft. Total 127428.16
3114.31 289.43

79 . False ceiling with 50x75 mm sections sisau wood with 600x900mm openings fixed with 4mm thick Commercial plywoo
9.75mx3.65m=35.58sqm (382.84sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 23.000 Nos. 908.00 20884.00
b) Coolies 2.300 Nos. 667.00 1534.10 22418.10

Materials Sisau Wood 0.450 Cum 92010.24 41404.61


4mm Ply 37.500 sqm 247.25 9271.88
wooden
listy 100.000 Rm 28.00 2800.00
Ordinary
nails 1.500 Kg 109.00 163.50 53639.98
Actual rate 76058.08
Rate Rate 15% contractor's overhead 11408.71
Per sqm. Per sft. Total 87466.80
2137.66 198.67

80. False ceiling with 50x75 mm sections sal wood with 600x900mm openings fixed with 3mm thick Asbetos plain sheets
9.75mx3.65m=35.58sqm (382.84sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 23.000 Nos. 908.00 20884.00
b) Coolies 2.300 Nos. 667.00 1534.10 22418.10
Sisau
Materials Wood 0.450 Cum 92010.24 41404.61
3mm
asbetos
sheet 37.500 sqm 329.26 12347.25
wooden
listy 100.000 Rm 28.00 2800.00
Ordinary
nails 1.500 Kg 109.00 163.50 56715.36
Actual rate 79133.46
Rate Rate 15% contractor's overhead 11870.02
Per sqm. Per sft. Total 91003.48
2224.10 206.70

81. False ceiling with 50x75 mm sections sisau wood with 600x900mm openings fixed with 12mm thick Hard board
9.75mx3.65m=35.58sqm (382.84sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 23.000 Nos. 908.00 20884.00
b) Coolies 2.300 Nos. 667.00 1534.10 22418.10

Materials Sisau Wood 0.450 Cum 92010.24 41404.61


Hard board
12 mm 37.500 sqm 451.50 16931.25
wooden
listy 100.000 Rm 28.00 2800.00
Ordinary
nails 1.500 Kg 109.00 163.50 61299.36
Actual rate 83717.46
Rate Rate 15% contractor's overhead 12557.62
Per sqm. Per sft. Total 96275.08
2352.94 218.67

82 . Wooden rafter/purlins/beams making and fixing of saal wo (1cum=35.28cft)


Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 17.650 Nos. 908.00 16026.20
b) Coolies 1.760 Nos. 667.00 1173.92 17200.12
Materials Wood saal 1.050 Cum 194040.00 203742.00
Ordinary
nails 3.000 Kg 109.00 327.00 204069.00
Actual rate 221269.12
Rate Rate 15% contractor's overhead 33190.37
Per cum. Per cft. Total 254459.49
221269.12 6271.80

83 . Wooden trussmaking and fixing of saal wood. (1cum=35.28cft)


Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 17.650 Nos. 908.00 16026.20
b) Coolies 26.000 Nos. 667.00 17342.00 33368.20
Materials Wood Saal 1.050 Cum 194040.00 203742.00
Steel plates 1.000 LS 200.00 200.00
Nut bolts 1.000 LS 200.00 200.00
Ordinary
nails 3.000 Kg 109.00 327.00 204469.00
Actual rate 237837.20
Rate Rate 15% contractor's overhead 35675.58
Per cum. Per cft. Total 273512.78
237837.20 6741.42

84 . 25mm x150mm salwood eaves board making and fixing (10sqm=107.6sft)


Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.430 Nos. 908.00 1298.44
b) Coolies 0.143 Nos. 667.00 95.38 1393.82
Materials Wood saal 0.275 Cum 194040.00 53361.00
Ordinary
nails 1.000 Kg 109.00 109.00 53470.00
Actual rate 54863.82
Rate Rate 15% contractor's overhead 8229.57
Per sqm. Per sft. Total 63093.39
5486.38 509.89

85. 16-20 mm dia ms rod fixing on windows (1MT)


Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 20.000 Nos. 908.00 18160.00
b) Coolies 20.000 Nos. 667.00 13340.00 31500.00
Materials MS rod 1.050 MT 75000.00 78750.00 78750.00
Actual rate 110250.00
Rate Rate 15% contractor's overhead 16537.50
Per MT Per kg. Total 126787.50
110250.00 110.25

I. Flooring works

86. 38mm(11/2") thick 1:2:4 Cement Concrete FLooring and finishing with
(forneat
10 sqm
cement
/107.58
coat sft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.250 Nos. 908.00 1135.00
b) Coolies 2.000 Nos. 667.00 1334.00 2469.00
Materials Cement 0.130 MT 15940.00 2072.20
Sand 0.180 Cub M 2787.12 501.68
12 mm
aggregate 0.360 Cub M 2716.56 977.96 3551.84
Actual rate 6020.84
Rate 15% contractor's overhead 903.13
Per sqm. Per sft. Total 6923.97
602.08 55.97
Note :Similar Works
87. 50mm(2") thick 1:2:4 Cement Concrete FLooring and finishing with(for
neat
10 sqm/ 107.58 sft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.250 Nos. 908.00 1135.00
b) Coolies 2.500 Nos. 667.00 1667.50 2802.50
Materials Cement 0.170 MT 15940.00 2709.80
Sand 0.230 Cub M 2787.12 641.04
12 mm
aggregate 0.460 Cub M 2716.56 1249.62 4600.46
Actual rate 7402.96
Rate 15% contractor's overhead 1110.44
Per sqm. Per sft. Total 8513.40
740.30 68.81

88. 75mm(3") thick 1:2:4 Cement Concrete FLooring and finishing with(for
neat10c sqm /107.58 sft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.250 Nos. 908.00 1135.00
b) Coolies 3.000 Nos. 667.00 2001.00 3136.00
Materials Cement 0.260 MT 15940.00 4144.40
Sand 0.340 Cub M 2787.12 947.62
20 mm
aggregate 0.680 Cub M 2716.56 1847.26 6939.28
Actual rate 10075.28
Rate 15% contractor's overhead 1511.29
Per sqm. Per sft. Total 11586.57
1007.53 93.65

5mm thick 1:1 white cement & marble chipping surface course including by rubbing & polish
to finish
(10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.500 Nos. 908.00 2270.00
b) Coolies 16.000 Nos. 667.00 10672.00 12942.00
Materials Cement 0.065 mt 15940.00 1036.10
Sand 0.088 cub m 2787.12 245.27
12.5mm
aggregate 0.176 cub m 2716.56 478.11
White
cement 0.061 Mt 26375.00 1608.88
Marble
chips 0.061 Mt 13728.00 837.41
Axalic acid 0.365 kg 115.00 41.98
Wax polish 0.118 kg 200.00 23.60
Turpentine 0.538 lit. 229.00 123.20
Carborendo
m stone 1.000 LS 150.00 150.00 4544.54
Actual rate 17486.54
Rate 15% contractor's overhead 2622.98
Per sqm. Per sft. Total 20109.52
1748.65 162.54

90. 25mm thick mosaic flooring with 6mm thick 1:1 white cement & marble chipping over
19mm c/s plaster surface with rubbing & polish to finish
(10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 3.500 Nos. 908.00 3178.00
b) Coolies 36.000 Nos. 667.00 24012.00 27190.00
Materials Cement 0.121 mt 15940.00 1928.74
Sand 0.165 cub m 2787.12 459.87
White
cement 0.069 Mt 26375.00 1819.88
Marble
chips 3mm 0.047 Mt 13728.00 645.22
Axalic acid 0.340 kg 115.00 39.10
Wax polish 0.110 kg 200.00 22.00
turpentine 0.500 lit. 229.00 114.50
Carborendo
m stone 1.000 LS 150.00 150.00 5179.31
Actual rate 32369.31
Rate 15% contractor's overhead 4855.40
Per sqm. Per sft. Total 37224.70
3236.93 300.89

91. 20mm thick mosaic flooring with 6mm thick 1:1 white cement & marble chipping over
12.5mm1:2 c/s plaster surface with rubbing & polish to finish
(10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 3.500 Nos. 908.00 3178.00
b) Coolies 36.000 Nos. 667.00 24012.00 27190.00
Materials Cement 0.089 mt 15940.00 1418.66
Sand 0.122 cub m 2787.12 340.03
White
cement 0.089 Mt 26375.00 2347.38
Marble
chips 3mm 0.061 Mt 13728.00 837.41
Axalic acid 0.365 kg 115.00 41.98
Wax polish 0.118 kg 200.00 23.60
turpentine 0.538 lit. 229.00 123.20
Carborendo
m stone 1.000 LS 150.00 150.00 5282.25
Actual rate 32472.25
Rate 15% contractor's overhead 4870.84
Per sqm. Per sft. Total 37343.09
3247.22 301.84

92. 20mm terrazo tile over 20mm1:4 c/s plaster surface with rubbing & polish(10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.000 Nos. 908.00 1816.00
b) Coolies 12.600 Nos. 667.00 8404.20 10220.20
Materials Cement 0.081 mt 15940.00 1291.14
Sand 0.220 cub m 2787.12 613.17
20mm
terrazotile 11.000 Sq M 516.00 5676.00
Axalic acid 0.365 kg 115.00 41.98
Wax polish 0.118 kg 200.00 23.60
turpentine 0.538 lit. 229.00 123.20
Carborendo
m stone 1.000 LS 150.00 150.00
Rubbing
unskilled
labour 13.500 Nos. 667.00 9004.50 16923.58
Actual rate 27143.78
Rate 15% contractor's overhead 4071.57
Per sqm. Per sft. Total 31215.35
2714.38 252.31

93. 15mm thick marble (450x450mm) over 20mm1:2 surki with rubbing (10
& poli
sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.000 Nos. 908.00 1816.00
b) Coolies 8.000 Nos. 667.00 5336.00 7152.00
Materials Lime 0.091 Cub M 16800.00 1528.80
25mm
marble 11.000 Sq M 1644.75 18092.25
Surki 0.183 Cub M 1541.03 282.01
Axalic acid 0.370 kg 115.00 42.55
Wax polish 0.118 kg 200.00 23.60
turpentine 0.538 lit. 229.00 123.20
Carborendo
m stone 1.000 LS 150.00 150.00
Rubbing
unskilled
labour 13.500 Nos. 667.00 9004.50 29246.91
Actual rate 36398.91
Rate 15% contractor's overhead 5459.84
Per sqm. Per sft. Total 41858.75
3639.89 338.34

94. Porcelain glazed tile over 20mm1:4 c/s mortar (10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 13.000 Nos. 908.00 11804.00
b) Coolies 4.500 Nos. 667.00 3001.50 14805.50
Materials Cement 0.056 mt 15940.00 892.64
Sand 0.152 cub m 2787.12 423.64
White
cement 3.228 kg 26.38 85.14
Porcelain
glaged tile 11.000 Sq M 709.50 7804.50 9205.92
Actual rate 24011.42
Rate 15% contractor's overhead 3601.71
Per sqm. Per sft. Total 27613.13
2401.14 223.20

95. 50 mm Flagstone paving on 1:4 c/s mortar (10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.000 Nos. 908.00 1816.00
b) Coolies 4.500 Nos. 667.00 3001.50 4817.50
Materials Cement 0.063 mt 15940.00 1004.22
Sand
50 mm 0.171 cub m 2787.12 476.60
thick
flagstone 11.000 Sq M 1182.50 13007.50 14488.32
Actual rate 19305.82
Rate 15% contractor's overhead 2895.87
Per sqm. Per sft. Total 22201.69
1930.58 179.46

96. 50 mm down Flagstone paving on filled sand (10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Coolies 3.000 Nos. 667.00 2001.00 2909.00
Materials Sand 0.710 cub m 2787.12 1978.86
50 mm
down
Flagstone 11.000 Sq M 1026.63 11292.88 13271.73
Actual rate 16180.73
Rate 15% contractor's overhead 2427.11
Per sqm. Per sft. Total 18607.84
1618.07 150.41

97. 37.5 mm Flagstone paving on 1:4 cement mortar (10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.000 Nos. 908.00 1816.00
b) Coolies 4.500 Nos. 667.00 3001.50 4817.50
Cement 0.060 mt 15940.00 956.40
Materials Sand 0.165 cub m 2787.12 459.87
37.5mm
Flagstone 11.000 Sq M 1021.25 11233.75 11693.62
Actual rate 16511.12
Rate 15% contractor's overhead 2476.67
Per sqm. Per sft. Total 18987.79
1651.11 153.48

98. 25 mm Flagstone paving on 1:4 cement mortar (10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Coolies 4.500 Nos. 667.00 3001.50 4363.50
Cement 0.056 mt 15940.00 892.64
Materials Sand 0.152 cub m 2787.12 423.64
25mm
Flagstone 11.000 Sq M 870.75 9578.25 10001.89
Actual rate 14365.39
Rate 15% contractor's overhead 2154.81
Per sqm. Per sft. Total 16520.20
1436.54 133.53

99. 25 mm Telia brick paving in 1:2 surki masala & tipkar in 1:2 cement mort
(10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 4.500 Nos. 908.00 4086.00
b) Coolies 4.500 Nos. 667.00 3001.50 7087.50
Materials Cement 0.016 mt 15940.00 255.04
Sand 0.110 cub m 2787.12 306.58
Lime 0.122 cub m 16800.00 2049.60
Surki 0.244 cub m 1541.03 376.01
Telia Bricks
25mm thick 440.000 Nos. 13.00 5720.00 8707.23
Actual rate 15794.73
Rate 15% contractor's overhead 2369.21
Per sqm. Per sft. Total 18163.94
1579.47 146.82

100. Brick flat soling on 1:6 cement mortar and pointing in 1:2 cement mortar (10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.250 Nos. 908.00 2043.00
b) Coolies 3.250 Nos. 667.00 2167.75 4210.75
Cement 0.078 mt 15940.00 1243.32
Materials Sand
Local 0.229 cub m 2787.12 638.25
Bricks 430.000 Nos. 14.00 6020.00 7901.57
Actual rate 12112.32
Rate 15% contractor's overhead 1816.85
Per sqm. Per sft. Total 13929.17
1211.23 112.59

101. Brick edge soling on 1:6 cement mortar and pointing in 1:2 cement mortar(10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.100 Nos. 908.00 998.80
b) Coolies 1.800 Nos. 667.00 1200.60 2199.40
Cement 0.121 mt 15940.00 1928.74
Materials Sand
Local 0.431 cub m 2787.12 1201.25
Bricks 750.000 Nos. 14.00 10500.00 13629.99
Actual rate 15829.39
Rate 15% contractor's overhead 2374.41
Per sqm. Per sft. Total 18203.80
1582.94 147.14

102. Parketting with polishing after rubbing with sand paper wo (10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.750 Nos. 908.00 1589.00
b) Coolies 0.750 Nos. 667.00 500.25 2089.25
Parkette 10.500 Sq M 1870.50 19640.25
Materials Sand paper 1.000 LS 30.00 30.00
Wax polish 1.000 LS 50.00 50.00 19720.25
machine to
Machine to r sand paper 2.000 Hrs 150.00 300.00 300.00
Actual rate 22109.50
Rate 15% contractor's overhead 3316.43
Per sqm. Per sft. Total 25425.93
2210.95 205.52

103. Dry flat brick soling works (10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.500 Nos. 908.00 454.00
b) Coolies
Local 1.000 Nos. 667.00 667.00 1121.00
Bricks 420.000 Sq M 14.00 5880.00
Materials Sand 0.710 Cum 2787.12 1978.86 7858.86
Actual rate 8979.86
Rate 15% contractor's overhead 1346.98
Per sqm. Per sft. Total 10326.83
897.99 83.47

104. Dry edge brick soling works (10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Coolies 3.250 Nos. 667.00 2167.75 3075.75
Bricks 750.000 Sq M 14.00 10500.00
Materials Sand 0.710 Cum 2787.12 1978.86 12478.86
Actual rate 15554.61
Rate 15% contractor's overhead 2333.19
Per sqm. Per sft. Total 17887.80
1555.46 144.59

105. Dry stone soling works (1Cum/35.28 Cft )


Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Coolies 3.500 Nos. 667.00 2334.50 3242.50
Stone 1.100 Sq M 2116.80 2328.48
Materials Sand 0.710 Cum 2787.12 1978.86 4307.34
Actual rate 7549.84
Rate 15% contractor's overhead 1132.48
Per Cum Per cft. Total 8682.31
7549.84 214.00

106. 125mm Edge Brick soling and pointing works in 1:3cement mortar on joint
(10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.000 Nos. 908.00 1816.00
b) Coolies 4.000 Nos. 667.00 2668.00 4484.00
Materials Cement 0.020 Mt 15940.00 318.80
Sand 0.710 Cum 2787.12 1978.86
Bricks 750.000 Nos. 14.00 10500.00 12797.66
Actual rate 17281.66
Rate 15% contractor's overhead 2592.25
Per sqm. Per sft. Total 19873.90
1728.17 160.64

107. Pointing in 1:1cement mortar on joints works on paved stone 46cm X46c(10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.500 Nos. 908.00 454.00
b) Coolies 0.500 Nos. 667.00 333.50 787.50
Materials Cement 4.200 Kg 15.94 66.95
Sand 0.003 Cum 2787.12 8.36 75.31
Actual rate 862.81
Rate 15% contractor's overhead 129.42
Per sqm. Per sft. Total 992.23
86.28 8.02

108. Filling with sand works (10 cum/ 352.8cft )


Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.000 Nos. 908.00 0.00
b) Coolies 6.500 Nos. 667.00 4335.50 4335.50
Materials Sand 11.000 Cum 2787.12 30658.32 30658.32
Actual rate 34993.82
Rate 15% contractor's overhead 5249.07
Per sqm. Per sft. Total 40242.89
3499.38 325.28

109. 15-150 mm brick bat Filling works (10 cum/ 352.8cft )


Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.000 Nos. 908.00 0.00
b) Coolies 10.000 Nos. 667.00 6670.00 6670.00
Batten
Materials Bricks 11.000 Cum 359.95 3959.45 3959.45
Actual rate 10629.45
Rate 15% contractor's overhead 1594.42
Per cum. Per cft. Total 12223.87
1062.95 30.13

110. 3mm thick thin layer cement Punning (chipping )works (10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Coolies 1.000 Nos. 667.00 667.00 1575.00
Materials Cement 53.200 Kg 15.94 848.01 848.01
Actual rate 2423.01
Rate 15% contractor's overhead 363.45
Per sqm. Per sft. Total 2786.46
242.30 22.52

J. Plasters & Pointing Work :


111. 12.5mm 1:3 cement sand plaster on ceiling (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 15.000 Nos. 908.00 13620.00
b) Coolies 20.000 Nos. 667.00 13340.00 26960.00
Materials Cement 0.625 MT 15940.00 9962.50
Sand 1.280 Cub M 2787.12 3567.51 13530.01
Actual rate 40490.01
Rate 15% contractor's overhead 6073.50
Per sqm. Per sft. Total 46563.52
404.90 37.64

112. 12.5mm 1:4cement sand plaster works on ceiling (for 100 sq.m/1075.8 sft.)
Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 15.000 Nos. 908.00 13620.00
b) Coolies 20.000 Nos. 667.00 13340.00 26960.00
Materials Cement 0.538 MT 15940.00 8575.72
Sand 1.460 Cub M 2787.12 4069.20 12644.92
Actual rate 39604.92
Rate 15% contractor's overhead 5940.74
Per sqm. Per sft. Total 45545.65
396.05 36.81

113. 12.5mm 1:4 cement sand plaster works except in ceiling (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 12.000 Nos. 908.00 10896.00
b) Coolies 16.000 Nos. 667.00 10672.00 21568.00
Materials Cement 0.538 Mt 15940.00 8575.72
Sand 1.460 Cub M 2787.12 4069.20 12644.92
Actual rate 34212.92
Rate 15% contractor's overhead 5131.94
Per sqm. Per sft. Total 39344.85
342.13 31.80

114. 12.5mm 1:6 cement sand plaster works (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 12.000 Nos. 908.00 10896.00
b) Coolies 16.000 Nos. 667.00 10672.00 21568.00
Materials Cement 0.382 Mt 15940.00 6089.08
Sand 1.570 Cub M 2787.12 4375.78 10464.86
Actual rate 32032.86
Rate 15% contractor's overhead 4804.93
Per sqm. Per sft. Total 36837.79
320.33 29.78

115. 12.5mm 1:2 Lime surki plaster works (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 12.000 Nos. 908.00 10896.00
b) Coolies 16.000 Nos. 667.00 10672.00 21568.00
Materials Lime 0.610 Cub M 16800.00 10248.00
Surki 1.220 Cub M 1541.03 1880.06 12128.06
Actual rate 33696.06
Rate 15% contractor's overhead 5054.41
Per sqm. Per sft. Total 38750.47
336.96 31.32

116. 20mm 1:3 cement sand plaster works (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 14.000 Nos. 908.00 12712.00
b) Coolies 19.000 Nos. 667.00 12673.00 25385.00
Materials Cement 0.960 Mt 15940.00 15302.40
Sand 1.950 Cub M 2787.12 5434.88 20737.28
Actual rate 46122.28
Rate 15% contractor's overhead 6918.34
Per sqm. Per sft. Total 53040.63
461.22 42.87

117. 20mm 1:4cement sand plaster works except in ceiling (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 14.000 Nos. 908.00 12712.00
b) Coolies 19.000 Nos. 667.00 12673.00 25385.00
Materials Cement 0.810 mt 15940.00 12911.40
Sand 2.200 Cub M 2787.12 6131.66 19043.06
Actual rate 44428.06
Rate 15% contractor's overhead 6664.21
Per sqm. Per sft. Total 51092.27
444.28 41.30

118. 20mm 1:6 cement sand plaster works except in ceiling (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 14.000 Nos. 908.00 12712.00
b) Coolies 19.000 Nos. 667.00 12673.00 25385.00
Materials Cement 0.570 mt 15940.00 9085.80
Sand 2.350 Cub M 2787.12 6549.73 15635.53
Actual rate 41020.53
Rate 15% contractor's overhead 6153.08
Per sqm. Per sft. Total 47173.61
410.21 38.13

119. 25mm mud plaster works with preparation of mud and surface etc. 30m lead (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 20.000 Nos. 908.00 18160.00
b) Coolies 25.000 Nos. 667.00 16675.00 34835.00
Materials Mud 3.000 Cub M 260.00 780.00
Rice straw 10.000 Kg. 5.00 50.00
Cow Dung 120.000 Kg. 4.80 576.00 1406.00
Actual rate 36241.00
Rate 15% contractor's overhead 5436.15
Per sqm. Per sft. Total 41677.15
362.41 33.69

120. 12 mm mud plaster works with preparation of mud and surface etc. 30m lead (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 15.000 Nos. 908.00 13620.00
b) Coolies 20.000 Nos. 667.00 13340.00 26960.00
Materials Mud 1.500 Cub M 260.00 390.00
Rice straw 50.000 Kg. 5.00 250.00
Cow Dung 60.000 Kg. 4.80 288.00 928.00
Actual rate 27888.00
Rate 15% contractor's overhead 4183.20
Per sqm. Per sft. Total 32071.20
278.88 25.92

K. Painting Work
121. 2 coat white washing works in ceiling on new surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.875 Nos. 908.00 1702.50
b) Coolies 1.375 Nos. 667.00 917.13 2619.63
Materials Gum 0.880 Kg. 217.00 190.96
White Lime 22.000 Kg. 21.00 462.00 652.96
Actual rate 3272.59
Rate 15% contractor's overhead 490.89
Per sqm. Per sft. Total 3763.47
32.73 3.04

122. 2 coat white washing works on other new surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Coolies 1.100 Nos. 667.00 733.70 2095.70
Materials Gum 0.880 Kg. 217.00 190.96
White Lime 22.000 Kg. 21.00 462.00 652.96
Actual rate 2748.66
Rate 15% contractor's overhead 412.30
Per sqm. Per sft. Total 3160.96
27.49 2.55

123. 3 coat white washing works in ceiling on new surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 3.750 Nos. 908.00 3405.00
b) Coolies 3.375 Nos. 667.00 2251.13 5656.13
Materials Gum 1.280 Kg. 217.00 277.76
White Lime 32.000 Kg. 21.00 672.00 949.76
Actual rate 6605.89
Rate 15% contractor's overhead 990.88
Per sqm. Per sft. Total 7596.77
66.06 6.14

124. 3 coat white washing works on other new surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 3.000 Nos. 908.00 2724.00
b) Coolies 2.700 Nos. 667.00 1800.90 4524.90
Materials Gum 1.280 Kg. 217.00 277.76
White Lime 32.000 Kg. 21.00 672.00 949.76
Actual rate 5474.66
Rate 15% contractor's overhead 821.20
Per sqm. Per sft. Total 6295.86
54.75 5.09

125. One White washing works on old surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.800 Nos. 908.00 726.40
b) Coolies 0.700 Nos. 667.00 466.90 1193.30
Materials Gum 0.400 Kg. 217.00 86.80
White Lime 10.000 Kg. 21.00 210.00 296.80
Actual rate 1490.10
Rate 15% contractor's overhead 223.52
Per sqm. Per sft. Total 1713.62
14.90 1.39

126. One coat distempering works over one coat astar (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 4.000 Nos. 908.00 3632.00
b) Coolies 4.000 Nos. 667.00 2668.00 6300.00
Materials Astar 8.000 Ltr. 286.00 2288.00
Distamper
Powder 6.500 Kg. 238.00 1547.00 3835.00
Actual rate 10135.00
Rate 15% contractor's overhead 1520.25
Per sqm. Per sft. Total 11655.25
101.35 9.42

127. Two coat distemper works over one coat astar (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 5.800 Nos. 908.00 5266.40
b) Coolies 5.800 Nos. 667.00 3868.60 9135.00
Materials Astar 8.000 Ltr. 286.00 2288.00
Distamper
Powder 11.500 Kg. 238.00 2737.00 5025.00
Actual rate 14160.00
Rate 15% contractor's overhead 2124.00
Per sqm. Per sft. Total 16284.00
141.60 13.16

128 One coat water proof cement paint works over one coat astar
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.700 Nos. 908.00 1543.60
b) Coolies 1.700 Nos. 667.00 1133.90 2677.50
Cement
Materials Paint 30.000 Ltr. 79.00 2370.00 2370.00
Actual rate 5047.50
Rate 15% contractor's overhead 757.13
Per sqm. Per sft. Total 5804.63
50.48 4.69

129. Two coat water proof cement paint works over one coat astar (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 5.000 Nos. 908.00 4540.00
b) Coolies 5.000 Nos. 667.00 3335.00 7875.00
Cement
Materials Paint 48.500 Ltr. 79.00 3831.50 3831.50
Actual rate 11706.50
Rate 15% contractor's overhead 1755.98
Per sqm. Per sft. Total 13462.48
117.07 10.88

130. One coat readymade enamel paint over one coat primer (Astar) on
(fornew
100 ssq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 8.000 Nos. 908.00 7264.00
b) Coolies 5.000 Nos. 667.00 3335.00 10599.00
Materials Primer 8.100 lit. 402.00 3256.20
Enamel 9.000 lit. 560.00 5040.00 8296.20
Actual rate 18895.20
Rate 15% contractor's overhead 2834.28
Per sqm. Per sft. Total 21729.48
188.95 17.56

131. Two coat readymade enamel paint over one coat primer (Astar) (for
on new
100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 12.000 Nos. 908.00 10896.00
b) Coolies 8.000 Nos. 667.00 5336.00 16232.00
Materials Primer 8.100 lit. 402.00 3256.20
Enamel 16.000 lit. 560.00 8960.00 12216.20
Actual rate 28448.20
Rate 15% contractor's overhead 4267.23
Per sqm. Per sft. Total 32715.43
284.48 26.44

132. One coat plastic emulsion paint over one coat primer (Astar) on(for
new100susq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 8.000 Nos. 908.00 7264.00
b) Coolies 5.000 Nos. 667.00 3335.00 10599.00
Materials Primer 8.100 lit. 286.00 2316.60
Readymade
Plastic
Emulsion
paint 9.000 lit. 562.00 5058.00 7374.60
Actual rate 17973.60
Rate 15% contractor's overhead 2696.04
Per sqm. Per sft. Total 20669.64
179.74 16.71

133. Two coat plastic emulsion paint over one coat primer (Astar) on
(for
new100s sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 12.000 Nos. 908.00 10896.00
b) Coolies 8.000 Nos. 667.00 5336.00 16232.00
Materials Primer 8.100 lit. 286.00 2316.60
Readymade
paint 16.000 lit. 562.00 8992.00 11308.60
Actual rate 27540.60
Rate 15% contractor's overhead 4131.09
Per sqm. Per sft. Total 31671.69
275.41 25.60

134. Two coat aluminium paint over one coat primer (Astar) on new(for
surface
100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.750 Nos. 908.00 9761.00
b) Coolies 10.750 Nos. 667.00 7170.25 16931.25
Materials Primer 8.100 lit. 402.00 3256.20
Aluminium
paint 10.760 lit. 583.00 6273.08
Sand paper 4.000 Nos. 6.00 24.00 9553.28
Actual rate 26484.53
Rate 15% contractor's overhead 3972.68
Per sqm. Per sft. Total 30457.21
264.85 24.62

135. One coat double boiled linseed oiling work on new surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.000 Nos. 908.00 1816.00
b) Coolies 2.000 Nos. 667.00 1334.00 3150.00
Materials Linseed oil 6.000 lit. 210.00 1260.00 1260.00
Actual rate 4410.00
Rate 15% contractor's overhead 661.50
Per sqm. Per sft. Total 5071.50
44.10 4.10

136. Two coat double boiled linseed oiling work on new surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 4.000 Nos. 908.00 3632.00
b) Coolies 4.000 Nos. 667.00 2668.00 6300.00
Materials Linseed oil 11.000 lit. 210.00 2310.00 2310.00
Actual rate 8610.00
Rate 15% contractor's overhead 1291.50
Per sqm. Per sft. Total 9901.50
86.10 8.00

137. One coat varnishing work on new surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 3.000 Nos. 908.00 2724.00
b) Coolies 2.000 Nos. 667.00 1334.00 4058.00
Materials Varnish 6.000 lit. 470.00 2820.00 2820.00
Actual rate 6878.00
Rate 15% contractor's overhead 1031.70
Per sqm. Per sft. Total 7909.70
68.78 6.39

138. Two coat varnishing work on new surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 6.000 Nos. 908.00 5448.00
b) Coolies 4.000 Nos. 667.00 2668.00 8116.00
Materials Varnish 11.000 lit. 470.00 5170.00 5170.00
Actual rate 13286.00
Rate 15% contractor's overhead 1992.90
Per sqm. Per sft. Total 15278.90
132.86 12.35

139. One coat bitumen paint work on new surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Coolies 1.000 Nos. 667.00 667.00 2029.00
Bitumen
Materials Paint 7.000 lit. 68.00 476.00
Sand paper 4.000 Nos. 6.00 24.00 500.00
Actual rate 2529.00
Rate 15% contractor's overhead 379.35
Per sqm. Per sft. Total 2908.35
25.29 2.35

140. Two coat bitumen paint work on new surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.500 Nos. 908.00 2270.00
b) Coolies 2.000 Nos. 667.00 1334.00 3604.00
Bitumen
Materials Paint 12.000 lit. 68.00 816.00
Sand paper 4.000 Nos. 6.00 24.00 840.00
Actual rate 4444.00
Rate 15% contractor's overhead 666.60
Per sqm. Per sft. Total 5110.60
44.44 4.13

141. Three coat french(chapra) polish work on new surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.000 Nos. 908.00 9080.00
b) Coolies 5.000 Nos. 667.00 3335.00 12415.00
Materials Chapra 2.000 kg 978.00 1956.00
Spirit 10.000 lit. 126.00 1260.00 3216.00
Actual rate 15631.00
Rate 15% contractor's overhead 2344.65
Per sqm. Per sft. Total 17975.65
156.31 14.53

142. One coat snowcem work after cement paint on new plastered surface
(for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 3.500 Nos. 908.00 3178.00
b) Coolies 3.500 Nos. 667.00 2334.50 5512.50
Materials Snowcem 30.000 lit. 79.00 2370.00 2370.00
Actual rate 7882.50
Rate 15% contractor's overhead 1182.38
Per sqm. Per sft. Total 9064.88
78.83 7.33

143. Two coat snowcem work after cement paint on new plastered surface
(for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 6.500 Nos. 908.00 5902.00
b) Coolies 6.500 Nos. 667.00 4335.50 10237.50
Materials Snowcem 50.000 lit. 79.00 3950.00 3950.00
Actual rate 14187.50
Rate 15% contractor's overhead 2128.13
Per sqm. Per sft. Total 16315.63
141.88 13.19

L. Pointing Works
144. Flush pointing works in 1:1 cement sand mortar on brick masonry
(forwork
100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.500 Nos. 908.00 9534.00
b) Coolies 12.000 Nos. 667.00 8004.00 17538.00
Materials Cement 0.316 mt 15940.00 5037.04
Sand 0.220 Cub M 2787.12 613.17 5650.21
Actual rate 23188.21
Rate 15% contractor's overhead 3478.23
Per sqm. Per sft. Total 26666.44
231.88 21.55
145. Ruled pointing works in 1:1 cement sand mortar on brick masonry
(forwork
100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.500 Nos. 908.00 9534.00
b) Coolies 18.000 Nos. 667.00 12006.00 21540.00
Materials Cement 0.316 mt 15940.00 5037.04
Sand 0.220 Cub M 2787.12 613.17 5650.21
Actual rate 27190.21
Rate 15% contractor's overhead 4078.53
Per sqm. Per sft. Total 31268.74
271.90 25.27

146. Flush pointin g works in 1:2 cement sand mortar on Brick masonry
(forwork
100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.500 Nos. 908.00 9534.00
b) Coolies 12.000 Nos. 667.00 8004.00 17538.00
Materials Cement 0.210 mt 15940.00 3347.40
Sand 0.290 Cub M 2787.12 808.26 4155.66
Actual rate 21693.66
Rate 15% contractor's overhead 3254.05
Per sqm. Per sft. Total 24947.71
216.94 20.17

147. Ruled pointing works in 1:2 cement sand mortar on Brick masonry
(for
work
100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.500 Nos. 908.00 9534.00
b) Coolies 18.000 Nos. 667.00 12006.00 21540.00
Materials Cement 0.210 mt 15940.00 3347.40
Sand 0.290 Cub M 2787.12 808.26 4155.66
Actual rate 25695.66
Rate 15% contractor's overhead 3854.35
Per sqm. Per sft. Total 29550.01
256.96 23.89

148. Flush pointing works in 1:3 cement sand mortar on Brick masonry
(for
work
100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.500 Nos. 908.00 9534.00
b) Coolies 12.000 Nos. 667.00 8004.00 17538.00
Materials Cement 0.155 mt 15940.00 2470.70
Sand 0.320 Cub M 2787.12 891.88 3362.58
Actual rate 20900.58
Rate 15% contractor's overhead 3135.09
Per sqm. Per sft. Total 24035.67
209.01 19.43

149. ruled pointing works in 1:3 cement sand mortar on Brick masonry(for
work
100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.500 Nos. 908.00 9534.00
b) Coolies 18.000 Nos. 667.00 12006.00 21540.00
Materials Cement 0.155 mt 15940.00 2470.70
Sand 0.320 Cub M 2787.12 891.88 3362.58
Actual rate 24902.58
Rate 15% contractor's overhead 3735.39
Per sqm. Per sft. Total 28637.97
249.03 23.15

150. Flush pointing works in 1:1:3 cement Lime sand mortar on Brick
(for
mason
100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.500 Nos. 908.00 9534.00
b) Coolies 12.000 Nos. 667.00 8004.00 17538.00
Materials Cement 0.125 mt 15940.00 1992.50
Lime 0.085 Cub M 16800.00 1428.00
Sand 0.255 Cub M 2787.12 710.72 4131.22
Actual rate 21669.22
Rate 15% contractor's overhead 3250.38
Per sqm. Per sft. Total 24919.60
216.69 20.14

151. Ruled pointing works in 1:1:3 cement Lime sand mortar on Brick
(for
mason
100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.500 Nos. 908.00 9534.00
b) Coolies 18.000 Nos. 667.00 12006.00 21540.00
Materials Cement 0.125 mt 2469.60 308.70
Lime 0.085 Cub M 16800.00 1428.00
Sand 0.255 Cub M 2787.12 710.72 2447.42
Actual rate 23987.42
Rate 15% contractor's overhead 3598.11
Per sqm. Per sft. Total 27585.53
239.87 22.30
152. Flush pointing works in 1:1 Lime Surki mortar on Brick masonry
(for
work
100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.500 Nos. 908.00 9534.00
b) Coolies 12.000 Nos. 667.00 8004.00 17538.00
Materials Lime 0.220 Cub M 16800.00 3696.00
Surki 0.220 Cub M 1541.03 339.03 4035.03
Actual rate 21573.03
Rate 15% contractor's overhead 3235.95
Per sqm. Per sft. Total 24808.98
215.73 20.05

153. Ruled pointing works in 1:1 Lime Surki mortar on Brick masonry
(forwork
100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.500 Nos. 908.00 9534.00
b) Coolies 18.000 Nos. 667.00 12006.00 21540.00
Materials Lime 0.220 Cub M 16800.00 3696.00
Surki 0.220 Cub M 1541.03 339.03 4035.03
Actual rate 25575.03
Rate 15% contractor's overhead 3836.25
Per sqm. Per sft. Total 29411.28
255.75 23.77

154. Flush pointing works in 1:2 Lime Surki mortar on Brick masonry(for
work
100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.500 Nos. 908.00 9534.00
b) Coolies 12.000 Nos. 667.00 8004.00 17538.00
Materials Lime 0.150 Cub M 16800.00 2520.00
Surki 0.290 Cub M 1541.03 446.90 2966.90
Actual rate 20504.90
Rate 15% contractor's overhead 3075.73
Per sqm. Per sft. Total 23580.63
205.05 19.06

155. Ruled pointing works in 1:2 Lime Surki mortar on Brick masonry
(forwork
100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.500 Nos. 908.00 9534.00
b) Coolies 18.000 Nos. 667.00 12006.00 21540.00
Materials Lime 0.150 Cub M 16800.00 2520.00
Surki 0.290 Cub M 1541.03 446.90 2966.90
Actual rate 24506.90
Rate 15% contractor's overhead 3676.03
Per sqm. Per sft. Total 28182.93
245.07 22.78

156. Flush ruled pointing works in 1:1 c/s mortar on random rubble masonry
(for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.000 Nos. 908.00 9080.00
b) Coolies 14.000 Nos. 667.00 9338.00 18418.00
Materials Cement 0.612 mt 15940.00 9755.28
Sand 0.430 Cub M 2787.12 1198.46 10953.74
Actual rate 29371.74
Rate 15% contractor's overhead 4405.76
Per sqm. Per sft. Total 33777.50
293.72 27.30

157. Flush ruled pointing works in 1:2 c/s mortar on random rubble masonry
(for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.000 Nos. 908.00 9080.00
b) Coolies 14.000 Nos. 667.00 9338.00 18418.00
Materials Cement 0.408 mt 15940.00 6503.52
Sand 0.570 Cub M 2787.12 1588.66 8092.18
Actual rate 26510.18
Rate 15% contractor's overhead 3976.53
Per sqm. Per sft. Total 30486.71
265.10 24.64

157. Flush ruled pointing works in 1:3 c/s mortar on random rubble masonry
(for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.000 Nos. 908.00 9080.00
b) Coolies 14.000 Nos. 667.00 9338.00 18418.00
Materials Cement 0.306 mt 15940.00 4877.64
Sand 0.630 Cub M 2787.12 1755.89 6633.53
Actual rate 25051.53
Rate 15% contractor's overhead 3757.73
Per sqm. Per sft. Total 28809.25
250.52 23.29

158. Flush ruled pointing works in 1:3cement sand mortar on ashlar masonry
(for 100wsq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 8.000 Nos. 908.00 7264.00
b) Coolies 10.000 Nos. 667.00 6670.00 13934.00
Materials Cement 0.110 mt 15940.00 1753.40
Sand 0.200 Cub M 2787.12 557.42 2310.82
Actual rate 16244.82
Rate 15% contractor's overhead 2436.72
Per sqm. Per sft. Total 18681.55
162.45 15.10

164. Pointing works in 1:3cement sand mortar on 45x45cm flagstone (for


paving
100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 5.000 Nos. 908.00 4540.00
b) Coolies 5.000 Nos. 667.00 3335.00 7875.00
Materials Cement 0.042 mt 15940.00 669.48
Sand 0.030 Cub M 2787.12 83.61 753.09
Actual rate 8628.09
Rate 15% contractor's overhead 1294.21
Per sqm. Per sft. Total 9922.31
86.28 8.02

165. Pointing works in 1:1cement sand mortar on telia bricks (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.000 Nos. 908.00 9080.00
b) Coolies 10.000 Nos. 667.00 6670.00 15750.00
Materials Cement 0.150 mt 15940.00 2391.00
Sand 0.100 Cub M 2787.12 278.71 2669.71
Actual rate 18419.71
Rate 15% contractor's overhead 2762.96
Per sqm. Per sft. Total 21182.67
184.20 17.12

166. 3mm Lime flushing plaster works (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.000 Nos. 908.00 9080.00
b) Coolies 10.000 Nos. 667.00 6670.00 15750.00
Materials Lime 0.160 cum 16800.00 2688.00 2688.00
Actual rate 18438.00
Rate 15% contractor's overhead 2765.70
Per sqm. Per sft. Total 21203.70
184.38 17.14

167. 3mm cement flushing plaster works (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.000 Nos. 908.00 9080.00
b) Coolies 10.000 Nos. 667.00 6670.00 15750.00
Materials Cement 0.518 mt 15940.00 8256.92 8256.92
Actual rate 24006.92
Rate 15% contractor's overhead 3601.04
Per sqm. Per sft. Total 27607.96
240.07 22.32

M. Water Proofing Works

168. 2 cm thick DPC in 1:2 C/S with Water Proofing Compound


(for rate(WPC)
analysis 10sq.m/ 107.58 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.750 Nos. 908.00 681.00
b) Coolies 0.800 Nos. 667.00 533.60 1214.60
Cement 0.135 MT 15940.00 2151.90
Materials Sand 0.180 cum 2787.12 501.68
WPC 2.700 Kg 289.00 780.30 3433.88
Actual rate 4648.48
Rate 15% contractor's overhead 697.27
Per sqm. Per sft. Total 5345.75
464.85 43.21

169. 2.5 cm thick DPC in 1:1.5:3 concrete with Water Proofing


(for rateCompound
analysis 10sq.m/
( 107.58 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Coolies 1.250 Nos. 667.00 833.75 1741.75
Cement ### MT 15940.00 1793.25
Materials Sand 0.113 cum 2787.12 314.94
12 mm
aggregate 0.250 cum 2716.56 679.14
WPC 2.250 Kg 289.00 650.25 3437.58
Actual rate 5179.33
Rate 15% contractor's overhead 776.90
Per sqm. Per sft. Total 5956.23
517.93 48.14

170. One coat Bitumenous paint on DPC and sand covering


(for rate analysis 10sq.m/ 107.58 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.000 Nos. 908.00 0.00
b) Coolies 0.600 Nos. 667.00 400.20 400.20
Bitumen 10.000 Kg 68.00 680.00
Materials Sand 0.020 cum 2787.12 55.74
Fire wood 30.000 Kg 20.00 600.00 1335.74
Actual rate 1735.94
Rate 15% contractor's overhead 260.39
Per sqm. Per sft. Total 1996.33
173.59 16.14

171. One Layer 500 Gauge polythene sheet for DPC (for rate analysis 10sq.m/ 107.58 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.600 Nos. 908.00 544.80
b) Coolies 0.600 Nos. 667.00 400.20 945.00
Polythene
Materials sheet 11.000 Sqm 30.00 330.00 330.00
Actual rate 1275.00
Rate 15% contractor's overhead 191.25
Per sqm. Per sft. Total 1466.25
127.50 11.85

172. One coat tar felt works with sand (for rate analysis 10sq.m/ 107.58 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.100 Nos. 908.00 998.80
b) Coolies 3.500 Nos. 667.00 2334.50 3333.30
Bitumen 15.000 Kg 68.00 1020.00
Materials Sand 0.310 cum 2787.12 864.01
Tar Felt 11.000 sqm 120.00 1320.00
Fire wood 60.000 Kg 20.00 1200.00 4404.01
Actual rate 7737.31
Rate 15% contractor's overhead 1160.60
Per sqm. Per sft. Total 8897.90
773.73 71.92
173. Two coat tar felt works with sand (for rate analysis 10sq.m/ 107.58 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.300 Nos. 908.00 2088.40
b) Coolies 4.600 Nos. 667.00 3068.20 5156.60
Bitumen 25.000 Kg 68.00 1700.00
Materials Sand 0.310 cum 2787.12 864.01
Tar Felt 22.000 sqm 120.00 2640.00
Fire wood 80.000 Kg 20.00 1600.00 6804.01
Actual rate 11960.61
Rate 15% contractor's overhead 1794.09
Per sqm. Per sft. Total 13754.70
1196.06 111.18

174. One coat damp Proof grade tar felt works with sand(for rate analysis 10sq.m/ 107.58 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.350 Nos. 908.00 2133.80
b) Coolies 4.600 Nos. 667.00 3068.20 5202.00
Bitumen 17.000 Kg 68.00 1156.00
Materials Sand 0.310 cum 2787.12 864.01
Tar Felt 11.000 sqm 120.00 1320.00
Fire wood 60.000 Kg 20.00 1200.00 4540.01
Actual rate 9742.01
Rate 15% contractor's overhead 1461.30
Per sqm. Per sft. Total 11203.31
974.20 90.56

175. Two coat damp Proof grade tar felt works with sand (for rate analysis 10sq.m/ 107.58 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 3.500 Nos. 908.00 3178.00
b) Coolies 11.700 Nos. 667.00 7803.90 10981.90
Bitumen 27.000 Kg 68.00 1836.00
Materials Sand 0.310 cum 2787.12 864.01
Tar Felt 22.000 sqm 120.00 2640.00
Fire wood 80.000 Kg 20.00 1600.00 6940.01
Actual rate 17921.91
Rate 15% contractor's overhead 2688.29
Per sqm. Per sft. Total 20610.19
1792.19 166.59

176. One coat rain seal or equivalent painting works (for rate analysis 1sq.m/ 10.758 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.162 Nos. 908.00 147.10
b) Coolies 0.540 Nos. 667.00 360.18 507.28
Rain seal
Materials paint 0.245 Ltr 673.00 164.89 164.89
Actual rate 672.16
Rate 15% contractor's overhead 100.82
Per sqm. Per sft. Total 772.99
672.16 62.48

N. Maintenance Work
177. Maintenance of wall in 1:6 C/S at corners with removal of old bricks (1Cum./35.28Cu ft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 3.530 Nos. 908.00 3205.24
b) Unskilled 7.060 Nos. 667.00 4709.02 7914.26
a) Cement 0.084 M.Ton 15940.00 1338.96
b) Sand 0.360 Cub M. 2787.12 1003.36
Materials c) Bricks 560.000 Nos. 14.00 7840.00 10182.32
Actual rate 18096.58
Rate 15% contractor's overhead 2714.49
Per Cum. Per Cu ft. Total 20811.07
18096.58 512.94

178. Maintenance of wall in 1:2 lime surki with removal of old bricks at wall c(10Cum./352.8Cu ft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 35.280 Nos. 908.00 32034.24
b) Unskilled 70.560 Nos. 667.00 47063.52 79097.76
a) Lime 1.400 Cub M. 16800.00 23520.00
Materials b) Surki 2.800 Cub M. 1541.03 4314.88
c) Bricks 5600.000 Nos. 14.00 78400.00 106234.88
Actual rate 185332.64
Rate 15% contractor's overhead 27799.90
Per Cum. Per Cu ft. Total 213132.54
18533.26 525.32

179. One coat Enamel paintings works after linseed oil flushing
(10Sqm./107.58 Sq ft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.538 Nos. 908.00 488.50
b) Unskilled 0.538 Nos. 667.00 358.85 847.35
a) Linseed
oil 0.538 Ltr 210.00 112.98
Materials b) Enamel 1.614 Ltr 560.00 903.84 1016.82
Actual rate 1864.17
Rate 15% contractor's overhead 279.63
Per Sqm. Per Sq ft. Total 2143.80
186.42 17.33

180. Dismantling of Cement Plaster and Disposing with transportation of 10m.( 1cu.m/35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: b) Unskilled 0.108 Nos. 667.00 72.04 72.04
Actual rate 72.04
Rate 15% contractor's overhead 10.81
Per Cum. Per Cu ft. Total 82.84
72.04 2.04

181. Dismantling of Tile Roof and Disposing tile/Woods with transportation ( 1cu.m/35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
a) Skilled 0.054 Nos. 908.00 49.03
Labours: b) Unskilled 0.081 Nos. 667.00 54.03 103.06
Actual rate 103.06
Rate 15% contractor's overhead 15.46
Per Cum. Per Cu ft. Total 118.52
103.06 2.92

182. Antitermite paint on wood ( 1Sqm/10.758Sqft )


Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
a) Skilled 0.220 Nos. 908.00 199.76
Labours: b) Unskilled 0.100 Nos. 667.00 66.70 266.46
a)Wood
preservative
Materials paint 0.245 Ltr. 244.00 59.78 59.78
Actual rate 326.24
Rate 15% contractor's overhead 48.94
Per Sqm. Per Sqft. Total 375.18
326.24 30.33

183. Dismantling of Mud mortared wall and Disposing with transportation of 10m
( 1cu.m/35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: b) Unskilled 1.060 Nos. 667.00 707.02 707.02
Actual rate 707.02
Rate 15% contractor's overhead 106.05
Per Cum. Per Cu ft. Total 813.07
707.02 20.04

184. Dismantling of Cement mortared wall and Disposing with transportation (of1cu.m/35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: b) Unskilled 2.120 Nos. 667.00 1414.04 1414.04
Actual rate 1414.04
Rate 15% contractor's overhead 212.11
Per Cum. Per Cu ft. Total 1626.15
1414.04 40.08

185. Dismantling of R.C.C./R.B.C. and Disposing with transportation of 10m.( 1cu.m/35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: b) Unskilled 11.000 Nos. 667.00 7337.00 7337.00
Actual rate 7337.00
Rate 15% contractor's overhead 1100.55
Per Cum. Per Cu ft. Total 8437.55
7337.00 207.96

186. Dismantling of P.C.C. and Disposing with transportation of 10m.( 1cu.m/35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: b) Unskilled 4.000 Nos. 667.00 2668.00 2668.00
Actual rate 2668.00
Rate 15% contractor's overhead 400.20
Per Cum. Per Cu ft. Total 3068.20
2668.00 75.62

O. (Iron) Steel Work


187. 3 x 20mm Metal Grill including manufacturing, fitting, painting with Aluminium paint, sand papering all complete
for 10 sq.m/107.58 sft.
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Materials Metal grill
3 x 20mm
size 10.000 sq.m 1790.95 17909.50 17909.50
Actual rate 17909.50
Rate 15% contractor's overhead 2686.43
Per sqm. Per sft. Total 20595.93
1790.95 166.48

188. 216. 4.5 x 20mm Metal Grill including manufacturing, fitting, painting with Aluminium paint, sand papering all complete
for 10 sq.m/107.58 sft.
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Materials Metal grill
4.5 x 20mm
size 10.000 sq.m 3220.70 32207.00 32207.00
Actual rate 32207.00
Rate 15% contractor's overhead 4831.05
Per sqm. Per sft. Total 37038.05
3220.70 299.38

189. Iron tubular Truss including manufacturing, welding, supply of material, painting and fixing all complete
for 18.94 kg
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: Skilled 0.687 No. 908.00 623.80 1144.72
Unskilled 0.781 No. 667.00 520.93
Materials Black Pipe 18.940 Kg. 79.00 1496.26 1496.26
Actual rate 2640.98
Rate 15% contractor's overhead 396.15
Per kg Per kg Total 3037.13
139.44 139.44
Combined 50mmf &37.5mmf Black pipe(medium Class) with necessary nutbolts & Plates.

190. GI Barbed wire fencingworks (for 100 R m/328Rft.)


Labours: a) Skilled 1.076 Nos. 908.00 977.01
b) Unskilled 5.380 Nos. 667.00 3588.46 4565.47
GI Barbed
Materials wire 110.000 Rm 13.57 1492.86
U-Hook 1.000 L.S. 150.00 150.00 1642.86
Actual rate 6208.33
Rate 15% contractor's overhead 931.25
Per Rm. Per rft. Total 7139.57
62.08 18.93

191. Barbed wire fencing in 75x100x2100 Saal wood posts with 5rows & two cross bracings all complete
(for 30 R m/98.4 Rft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00 908.00
Salwood 0.190 Cub M. 194040.00 36867.60
Materials Barbed wire 250.000 Rm 13.57 3392.86
U-Hook 77.000 Nos. 0.74 56.98 40317.44
Actual rate 41225.44
Rate 15% contractor's overhead 6183.82
Per Rm. Per rft. Total 47409.25
1374.18 418.96

P. Miscelaneous
192. M1 . Rain Water Pipe 90 mm dia. HDPE (100 RM/ 328 R Ft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 4.000 Nos. 908.00 3632.00
b) Coolies 6.000 Nos. 667.00 4002.00 7634.00
90 mm dia.
Materials HDPE Pipe 110.000 R M 200.00 22000.00
Bed Fitting 1.000 L S 5.00 5.00
Clamps 1.000 L S 10.00 10.00 22015.00
Actual rate 29649.00
15% contractor's overhead 4447.35
Rate Total 34096.35
Per Rmt. Per Rft
296.49 90.39

193. M11.Concrete Hollow Block Masonry works in 1:4 cement mo


Per sq.m
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.250 Nos. 908.00 227.00
b) Unskilled 0.250 Nos. 667.00 166.75 393.75
16"*8"*6"
hollow
block 19.000 Nos. 76.00 1444.00
Cement 0.010 MT 15940.00 159.40
Materials Sand 0.040 Cub.M. 2787.12 111.48
1714.88
Actual rate 2108.63
Rate 15% contractor's overhead 316.30
Per Sq.m. Per Sq.ft. Total 2424.93
2108.63 196.15

194. M12. 50mm thick inter locking concrete block work on 50mm
per 10 sq.m
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Unskilled 10.000 Nos. 667.00 6670.00 7578.00
Interloking
block 11.000 Sq.m 534.06 5874.66
Materials Stone dust 0.710 Cub.M. 1058.40 751.46
6626.12
Actual rate 14204.12
Rate 15% contractor's overhead 2130.62
Per sqm.. Per sqft. Total 16334.74
1420.41 132.13

195. M13. 60mm thick inter locking concrete block work on 50mm
per 10 sq.m
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Unskilled 10.000 Nos. 667.00 6670.00 7578.00
Interloking
block 11.000 Sq.m 557.28 6130.08
Materials Stone dust 0.710 Cub.M. 1058.40 751.46
6881.54
Actual rate 14459.54
Rate 15% contractor's overhead 2168.93
Per sqm. Per sqft. Total 16628.48
1445.95 134.38
7. Compound Filling with Borrowed Earth materials. ( 1cu.m/35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Coolies 1.009 Nos. 667.00 673.00 673.00

for
excavations
@3% of
labour
cost=.03*.7
Equipments *90=1.89 20.19
Truck: 6Mt
0.3 hours of
transportati
on Time of
3 Km
Distance
with20Kmp
h
speed&.221
Hrs idle 0.521 Hrs 450.00 234.45 234.45
Soil at
Materials Borrow Pit 1.100 cum 260.00 286.00 286.00
Actual rate 1213.64
15% contractor's overhead 182.05
Rate Total 1395.69
Per cum. Per cft.
1395.69 39.56 Note: 1M3 dry Soil=1200 Kg.
m trasportation

m trasportation
0m trasportation

m trasportation
trasportation
m trasportation

30m trasportation

m trasportation
30m trasportation

including 30m trasportation


m trasportation

ng 30m trasportation
g 30m trasportation

m trasportation

trasportation
trasportation
portation upto 30m
c. with transportation
oving and transportation up to 30m

o 30m & up to 0.3m Ht of beams


ommercial ply both side fixing with listy
4mm thick Commercial plywood

m thick Asbetos plain sheets


2mm thick Hard board
nd papering all complete
aint, sand papering all complete

ng all complete

You might also like