Rate analysis for 10 Sq.m.

area (Site clearance)


Cutting of grass,removing roots,making all level as per drawing & specification
S.N. Description Category Unit rate per unit Quantity Amount Remarks
1 Labour Unskilled No. 870 0.23 200.1
Tools & plant 3% 6.003

Actual
amount (Nrs.) 206.103
contractor overhead charge 15% 30.91545
Total amount
(Nrs.) 237.0185
for 1 sq.m.(Nrs.) 23.701845

Rate analysis for 1 cu.m. volume (E/W in excavation)


10m carry & disposal ,1.5m lift
S.N. Description Category Unit rate per unit Quantity Amount Remarks
1 Labour Unskilled No. 870 0.7 609
Tools & plant 3% 18.27

Actual
amount (Nrs.) 627.27
contractor overhead charge 15% 94.0905
Total amount
(Nrs.) 721.3605

Rate analysis for 1 cu.m. volume (9'' brick works)


Carry up to 30m distance
S.N. Description Category Unit rate per unit Quantity Amount Remarks
1 Labour Unskilled No. 870 2.2 1914
Mason Skilled No. 1185 1.5 1777.5
Bricks No. 18 560 10080
cement MT 16000 0.07 1120
sand cu.m. 3532 0.3 1059.6
water litre 20 100 2000
Tools & plant 3% 57.42

Actual
amount (Nrs.) 18008.52
contractor overhead charge 15% 2701.278
Total amount
(Nrs.) 20709.8

Rate analysis for 1 cu.m. volume (RCC works)


carry up to 30m distance (Concrete mixing ratio 1:2:4) M15
S.N. Description Category Unit rate per unit Quantity Amount Remarks
1 Labour Unskilled No. 870 4 3480
Mason Skilled No. 1185 1 1185
cement MT 16000 0.32 5120
agg 40mm cu.m. 3532 0.52
agg 20mm cu.m. 3532 0.22
agg 10mm cu.m. 3532 0.11
sand cu.m. 3532 0.445 1571.74
water litre 20 150 3000
Tools & plant 3% 104.4

Actual
amount (Nrs.) 14461.14
contractor overhead charge 15% 2169.171

Total amount
(Nrs.) 16630.31