INTERNATIONAL RESCUE COMMITTEE, ETHIOPIA PROGRAMME.

(IRC)

Labor cost unit rate for construction of civil,


Electrical and plumbing works in MD,BM,
Kobe, Buramino and Halewoyne camps UNIT Rate BKM/MD/Kobe+
(ETB)
S. BKM/MD 15% contractor
DESCRIPTION UNIT (30% tax )
No. / profit+15% vat +
I MAN POWER 2% TOT
1 Skilled labor daily 160
2 Semi-skilled labor daill 80
3 Unskilled labor daily 55
II 1.EXCAVATION AND EARTH WORK
Site clearing to remove top soil with average
1.1 m2 10 14 14
depth of 20cm
Trench Excavation around foundation ffor
1.2
ordinary soil
1.2.1 Up to 1m m3 75 107 107
1.2.2 1m-2m m3 92 130 131
1.2.3 2m-3m m3 110 156 157
1.2.4 >3m m3 140 199 200
Trench Excavation around foundation for Soft
1.3
rock soil
1.3.1 Up to 1m m3 92 130 130
1.3.2 1m-2m m3 110 156 156
1.3.3 2m-3m m3 138 195 195
1.3.4 >3m m3 157 223 223
Trench Excavation around foundation for Hard
1.4 0
rock
1.4.1 Up to 1m m3 220 312 312
1.4.2 1m-2m m3 275 391 391
1.4.3 2m-3m m3 367 521 521
1.4.4 >3m m3 458 651 651
Bulk Excavation around foundation for ordinary
1.5 0 0
soil
1.5.1 Up to 1m m3 55 78 78
1.5.2 1m-2m m3 65 92 92
1.5.3 2m-3m m3 80 114 114
1.5.4 >3m m3 90 128 128
Bulk Excavation around foundation for Soft
1.6
rock soil
1.6.1 Up to 1m m3 69 98 98
1.6.2 1m-2m m3 85 120 120
1.6.3 2m-3m m3 100 142 142
1.6.4 >3m m3 122 174 174
1.7 Excavation around foundation for hard rock 0 0
1.7.1 Up to 1m m3 275 391 391
1.7.2 1m-2m m3 306 434 434
1.7.3 2m-3m m3 344 488 488
1.7.4 >3m m3 393 558 558
1.8 Back fill and compaction at every 20cm layer m3 37 52 52
1.9 Back fill around foundation in hard rock m3 69 98 98
Cart away to minimum distance 500m from the
1.1 m3 37 53 53
site
1.11 Hard coring including blinding (15-25cm depth) m2 38 54 54
III Construction Work 0 0
1 CONCRETE WORK 0 0
Concrete Mixing & casting(using liberator&
1.1 0 0
concrete Mixer)
1.1.1 Lean concrete(3-5cm)thick m2 35 50 50

EH DOLO ADO FIELD OFFICE 09/19/2021 1]


INTERNATIONAL RESCUE COMMITTEE, ETHIOPIA PROGRAMME.
(IRC)
BKM/MD/Kobe+
S. BKM/MD 15% contractor
DESCRIPTION UNIT (30% tax )
No. / profit+15% vat +
1.1.2 Lean concrete(6-8cm)thick m2 41 58 2% 58
TOT
1.1.3 Floor slab (mass concrete) 8cm m2 61 87 87
1.1.4 Floor slab (mass concrete)10cm m2 70 99 99
1.1.5 Floor slab (mass concrete)15cm m2 82 116 116
1.1.6 Concrete work 20cm m2 98 139 139
1.1.7 Concrete work 25cm m2 123 174 174
1.1.8 Concrete work 30cm m2 148 211 211
1.1.9 Concrete work 50cm* m3 490 696 696
1.1.10 Beams, Foundation column, footing& etc m3 375 533 533
1.1.11 Lintel ,toptie beam& etc m3 445 633 633
1.2.1 columns up 2.8m m3 516 732 732
1.2.2 Columns above 2.8m m3 544 773 773
1.2.3 Sheerwall upm to 3.0m m3 516 732 732
1.2.4 Sheerwall above 3.0m m3 544 773 773
Mass concrete specially for construction of tap
1.2.5 m3 490 696 696
stands
2 Reinforcement bar bending, cutting, fixing kg 2.75 3.9 4
3 MASONRY WORK 0 0
3.1 Stone masonry work 40cm m3 190 270 270
3.2 Stone masonry work 50cm m3 169 240 240
3.3 Stone masonry work 60cm m3 152 216 216
3.4 Sandwiched concrete masonry m3 271 385 385
4 Stone masonry forSuperstructures 0 0
4.1 Stone masonry work 40cm m3 203 288 288
4.2 Stone masonry work 50cm m3 200 284 284
4.3 Stone masonry work 60cm m3 197 280 280
4 BLOCK WORK
4.1 10cm HCB block work m2 54 77 77
4.2 15cm HCB block work m2 60 85 86
4.3 20cm HCB block work m2 68 96 97
5 Carpentry and ROOFING WORK 0 0
CIS roofing work include mount eucalyptus
5.1 truss, zigba purlin, valley cover (measure m2 30 43 43
horizontal projection)
5.2 Gutter fixing ml 11 15 15
5.3 Down pipe fixing ml 11 15 15
5.4 Faciaboard fixing ml 12 17 17
Chip wood Ceiling work include ceiling button &
5.5 m2 45 64 64
corner list)
5.6 Eve work with ribbed sheet and celing buttens m2 21 29 30
Form work toptie beam, lintel, shear wall,
5.7 m2 74 105 106
suspended slab, etc
Form work grade beam, column, floor slab,
5.8 m2 54 77 77
footings, etc
6 DOORS & WINDOW 0 0
6.1 Fixing of metal doors Pcs 54 77 77
6.2 Fixing of metal window Pcs 54 77 77
6.4 Painting of metal doors and windows in 3 coats m2 12 17 17
7 FINISHING WORK 0 0
7.1 Three coats of plastering m2 70 100 100
7.2 Pointing work include chiseling 0 0
7.2.1 To HCB wall m2 25 36 36
7.2.2 To stone masonry wall m2 30 43 43

EH DOLO ADO FIELD OFFICE 09/19/2021 2]


INTERNATIONAL RESCUE COMMITTEE, ETHIOPIA PROGRAMME.
(IRC)
BKM/MD/Kobe+
S. BKM/MD 15% contractor
DESCRIPTION UNIT (30% tax )
No. / profit+15% vat +
7.3 3-5cm thick cement screed work m2 48 67 2% 68
TOT
7.4 Pavement 60cm wide ml 23 32 32
7.5 Edge work around doors and windows ml 14 20 20
8 GLAZING WORK 0 0
8.1 Glazing work (cutting and fixing) m2 23 32 32
9 PAINTING WORK 0 0
9.1 Three coats of plastic, oil paint work m2 14 20 20
IV ELECTRICAL INSTALATION 0 0
1 Electrical installation 0 0
1.1 Light point, holder and switch fixing Pcs 27 38 38
Fixing electrical fixtures TV point, telephone
1.2 Pcs 22 31 31
point, breaker, socket, including wiring
1.3 Fixing conduit and electric pulling ml 5 8 8
Electric cable laying using conduit including
1.4 ml 11 15 15
excavation & back filling work
Plumbing and Sanitary Work (by considering
V 0 0
necessary fittings )
1 Pipe laying 0 0
1.1 ½'' up to 2'' m 6 9 9
1.2 3"- 4" m 8 11 11
1.3 6" m 11 15 15
1.4 HDPE 3" and 4" m 6 9 9
1.5 PVC pipe installation m 5 6 6
2 Trench excavation for pipe laying 0 0
2.1 Trench excavation soft rock(0.8x0.8m) ml 110 156 157
2.2 Trench excavation hard rock rock(0.8x0.8m) ml 176 250 252
3 Fixing Sanitary Fixtures 0 0
3.1 Shower plate Pcs 108 153 154
3.2 Sink Pcs 108 153 154
3.3 Hand washing basin Pcs 108 153 154
3.4 Shower head Pcs 54 76 77
3.5 Water closet with flash Pcs 135 192 193
VI Fence Work 0 0
Fixing barbed wire (the work includes excavation
of 40cmX40cmX40cm pit, erecting angle iron
with 2m spacing, tying seven rows with 30cm
1 ml 27 38 39
spacing and cris cross diagonal barbed wire)
-measurement taken spacing of angle iron as one
unit
Fixing mesh wire (the work includes excavation
of 40cmX40cmX40cm pit, erecting angle iron
2 ml 23 32 32
with 2m spacing, tying mesh wire)-measurement
taken spacing of angle iron as one unit
3 Fence Work with wooden poles and CIS fixing m2 27 38 39
VII Others 0 0
Construction wall by CIS the price includes
1 fixing of reinforcing wood and maintain CIS by m2 30 43 43
roof nail
Constructing masonry steps for accessing
2 m3 160 227 229
purpose
3 Filling masonry/ concrete ring beam by sand m3 28 40 40
4 Production of HCB Pcs 2 3 3
5 Rock fill in gabion m3 135 192 193

EH DOLO ADO FIELD OFFICE 09/19/2021 3]


INTERNATIONAL RESCUE COMMITTEE, ETHIOPIA PROGRAMME.
(IRC)
BKM/MD/Kobe+
S. BKM/MD 15% contractor
DESCRIPTION UNIT (30% tax )
No. / profit+15% vat +
6 Installation of main gate pcs 135 192 2%193
TOT
Demolishing 0 0 0
1 Demolishing masonry structures m3 56 80 80 113.714
2 Demolishing HCB structures m2 28 40 40 56.8568
3 Demolishing CIS structures m2 22 31 31 43.6579
4 Demolishing RCC structures m3 68 96 97 137.066

EH DOLO ADO FIELD OFFICE 09/19/2021 4]