for hardcore for lean for rcc floor for wall rcc for plastering Total
133.9 44.6 133.9 104.0 71.5
stone 133.9 134 m3 11loads sand 20.0 57.2 44.4 2.3 124 m3 9loads aggregate 40.0 114.4 88.8 243 m3 17loads cement 175.4 751.8 583.9 19.5 1,531 bags re bars 8mm 6,090.0 6,090 kg 1,570pcs panel 117.6 453.6 571 m2 0 0 for hardcore for lean for rcc floor for wall masonry for plastering Total
38.4 17.9 38.4 23.4 110.5
stone 38.4 29.3 68 m3 6loads sand 8.1 16.5 9.8 3.5 38 m3 3loads aggregate 16.1 33.0 49 m3 4loads cement 70.7 138.2 74.9 30.1 314 bags re bars 10mm 1,274.0 1,274 kg 182pcs panel 69.4 69 m2 0 0 for beams for column for hardcore found wall for lean for rcc floor for wall hcb for plastering Total unit rcc rcc
11.4 11.9 5.3 4.0 1.9 11.4 148.2 148.2
stone 11.4 14.8 26 m3 2loads sand 3.6 2.4 2.0 1.0 5.1 5.9 4.7 25 m3 2loads aggregate 4.8 3.0 1.4 10.3 19 m3 1loads cement 35.6 21.1 25.3 12.3 52.6 45.9 44.5 237 bags re bars 8mm 209.0 209 kg 44pcs 10mm 464.2 464 kg 63pcs 12mm 467.2 467 kg 63pcs panel 49.4 38.4 88 m2 HCB 1,852.5 1,853 pcs for beams for column for hardcore found wall for lean for rcc floor for wall hcb for plastering Total unit rcc rcc
3.1 4.8 0.9 1.6 1.0 1.9 60.0 60.0
stone 3.1 6.0 9 m3 1loads sand 1.4 0.4 0.8 0.5 0.8 2.4 1.9 8 m3 1loads aggregate 0.8 1.2 0.7 1.7 4 m3 0loads cement 14.4 3.5 10.2 6.1 8.6 18.6 18.0 79 bags re bars 8mm 189.4 189 kg 40pcs 10mm 200.8 201 kg 27pcs panel 20.0 19.2 39 m2 HCB 750.0 750 pcs for beams for column for hardcore found wall for lean for rcc floor for wall hcb for plastering Total unit rcc rcc
3.1 4.8 0.9 1.6 1.0 1.9 60.0 60.0
stone 3.1 6.0 9 m3 1loads sand 1.4 0.4 0.8 0.5 0.8 2.4 1.9 8 m3 1loads aggregate 0.8 1.2 0.7 1.7 4 m3 0loads cement 14.4 3.5 10.2 6.1 8.6 18.6 18.0 79 bags re bars 8mm 55.0 55 kg 12pcs 10mm 816.0 816 kg 110pcs panel 20.0 19.2 39 m2 HCB 750.0 750 pcs for pole mesh wire column gate foundation Total unit
9.8 492.0 8.6 1.6 51.9
stone 20.8 21 m3 2loads sand 4.4 3.9 8 m3 1loads aggregate 8.4 7.8 16 m3 1loads cement 55.1 34.1 31.2 120 bags re bars 8mm 476.5 113.8 590 kg 125pcs 10mm 1,488.7 136.2 1,625 kg 219pcs panel 0 m2 HCB 0 pcs Mesh wire 565.8 566 m Gate 2m*2.5m 3.0 3 pcs 1m*2m 2.0 2 pcs for hardcore for lean for rcc floor ditch Total