for hardcore for lean for rcc floor for wall rcc for plastering Total

133.9 44.6 133.9 104.0 71.5


stone 133.9 134 m3 11loads
sand 20.0 57.2 44.4 2.3 124 m3 9loads
aggregate 40.0 114.4 88.8 243 m3 17loads
cement 175.4 751.8 583.9 19.5 1,531 bags
re bars
8mm 6,090.0 6,090 kg 1,570pcs
panel 117.6 453.6 571 m2
0
0
for hardcore for lean for rcc floor for wall masonry for plastering Total

38.4 17.9 38.4 23.4 110.5


stone 38.4 29.3 68 m3 6loads
sand 8.1 16.5 9.8 3.5 38 m3 3loads
aggregate 16.1 33.0 49 m3 4loads
cement 70.7 138.2 74.9 30.1 314 bags
re bars
10mm 1,274.0 1,274 kg 182pcs
panel 69.4 69 m2
0
0
for beams for column
for hardcore found wall for lean for rcc floor for wall hcb for plastering Total unit
rcc rcc

11.4 11.9 5.3 4.0 1.9 11.4 148.2 148.2


stone 11.4 14.8 26 m3 2loads
sand 3.6 2.4 2.0 1.0 5.1 5.9 4.7 25 m3 2loads
aggregate 4.8 3.0 1.4 10.3 19 m3 1loads
cement 35.6 21.1 25.3 12.3 52.6 45.9 44.5 237 bags
re bars
8mm 209.0 209 kg 44pcs
10mm 464.2 464 kg 63pcs
12mm 467.2 467 kg 63pcs
panel 49.4 38.4 88 m2
HCB 1,852.5 1,853 pcs
for beams for column
for hardcore found wall for lean for rcc floor for wall hcb for plastering Total unit
rcc rcc

3.1 4.8 0.9 1.6 1.0 1.9 60.0 60.0


stone 3.1 6.0 9 m3 1loads
sand 1.4 0.4 0.8 0.5 0.8 2.4 1.9 8 m3 1loads
aggregate 0.8 1.2 0.7 1.7 4 m3 0loads
cement 14.4 3.5 10.2 6.1 8.6 18.6 18.0 79 bags
re bars
8mm 189.4 189 kg 40pcs
10mm 200.8 201 kg 27pcs
panel 20.0 19.2 39 m2
HCB 750.0 750 pcs
for beams for column
for hardcore found wall for lean for rcc floor for wall hcb for plastering Total unit
rcc rcc

3.1 4.8 0.9 1.6 1.0 1.9 60.0 60.0


stone 3.1 6.0 9 m3 1loads
sand 1.4 0.4 0.8 0.5 0.8 2.4 1.9 8 m3 1loads
aggregate 0.8 1.2 0.7 1.7 4 m3 0loads
cement 14.4 3.5 10.2 6.1 8.6 18.6 18.0 79 bags
re bars
8mm 55.0 55 kg 12pcs
10mm 816.0 816 kg 110pcs
panel 20.0 19.2 39 m2
HCB 750.0 750 pcs
for pole mesh wire column gate foundation Total unit

9.8 492.0 8.6 1.6 51.9


stone 20.8 21 m3 2loads
sand 4.4 3.9 8 m3 1loads
aggregate 8.4 7.8 16 m3 1loads
cement 55.1 34.1 31.2 120 bags
re bars
8mm 476.5 113.8 590 kg 125pcs
10mm 1,488.7 136.2 1,625 kg 219pcs
panel 0 m2
HCB 0 pcs
Mesh wire 565.8 566 m
Gate
2m*2.5m 3.0 3 pcs
1m*2m 2.0 2 pcs
for hardcore for lean for rcc floor ditch Total

0.8 2.4 0.9


stone 0.0 0 m3 0loads
sand 0.4 1.0 0.4 2 m3 0loads
aggregate 0.7 2.1 0.8 4 m3 0loads
cement 3.1 13.5 5.1 22 bags
re bars
8mm 0 kg
10mm 0 m2
panel 0
HCB 0
Mesh wire
Gate
2m*2.5m
1m*2m
stone 266.8 m3 22load
sand 213.2 m3 15load
aggregate 340.4 m3 24load
cement 2,382.6 bags
re bars
8mm 8,407.7 kg 1,774pcs
10mm 3,105.9 kg 419pcs
12mm 545.6 kg 51pcs
panel 806.8 m2 1,009pcs
HCB 3,352.5 pcs
Mesh wire 565.8 m 11roll
Gate
2m*2.5m 3.0 pcs
1m*2m 2.0 pcs
ct wp genh gh toilet total
dl 14 8 8 2 8 40
mason 2 2 2 1 1 8
carpenter 1 1 2 1 1 6
bar Bender 0.25 0.25 1.5 0.5 0.5 3