Professional Documents
Culture Documents
Eng. Mukama, E.
Outline
It should be strong enough to support the load of wet concrete (2400 kg/m 3)
It must not be able to deflect under load.
It must be accurately set out. Fresh Concrete will take the shape of the
formwork, which must therefore be of correct shape size and in the right
position.
It must have grout tight joints. Grout leakage can cause honeycombing of
the surface and produce fins which have to be removed.
Form sizes should be designed so that the maximum sizes can easily be
handled by hand or by a mechanical lifting device.
Materials must be chosen so that can be easily fixed using wire, nails or
wood screw.
Use nails atleast two and half times the thickness of member being nailed in
length.
The design of formwork units should be such that they can easily be
assembled and dismantled without any member being trapped.
8.3 Formwork Materials
1) Rough or Smooth Timber
Timber with Moisture Content of 15 – 20%
Very dry timber may absorb moisture from concrete hence
reducing strength; the formwork may swell giving
unaccounted shape.
Moist timber may shrink resulting into open joints and a
leakage of grounds.
Plywood
formwork
Steel
formwork
Plastic formwork
Mould oil or Emulsions
Alleviate two defects on finished concrete.
a) Blow holes – small holes caused by air being trapped between formwork and
concrete face.
b) Uneven colour – Caused by irregular absorption of water from the wet concrete by
the formwork material.
Mould oil - applied to the inside surface of the formwork. Excessive amounts
can cause retardation of the setting of cement.
Should not be used in conjunction with steel forms since they encourage rusting.
Both mould oils and emulsion act as release agents. Apply only to formwork not
to the reinforcement. This may cause reduction in bonding.
8.4 Types of Formwork
1. Foundation Formwork
If subsoil is firm and hard, it may be possible to excavate the trench or
pit for the foundation to the size and depth required and cast the
concrete against the excavated faces.
Side and end panels will be required and these should be firm strutted
against the excavation faces to resist horizontal pressure of the wet
concrete and to retain formwork in correct positions
Ties will be required across the top of the form as a top restraint, and
these can be utilized to form the kicker for the reinforcement concrete
column or as a template for casting in the holding down bolts for
precast concrete or steel.
Typical Foundation Formwork
Figure: House foundation with wooden formwork
2. Column Formwork
The faces are held together with collars of timber or metal called yokes
in the case of timber and clamps when made of metal.
The spacing of the yokes or clamps should vary with the anticipated
Typical Column Formwork Details
Concrete pressure
The actual pressure will vary according to;
a) Rate of placing - the faster the rate, the higher the
pressure.
b) Type of Mix being used – the richer the mixer, the
greater the pressure.
c) Method of placing – If vibrations are used pressure can
increase up to 50% over hand placing and compacting.
d) Air temperature – the lower the temperature, the slower
is the hydration process and consequently higher
pressures are encountered.
3. Beam Formwork
Soffit boards should be fixed inside the beam so that the later can be
removed at an early date, to enable flow of air around the new concrete
and speed up the hardening process and also release the formwork for re-
use at the earlier possible time.
Generally the beam form is also used to support the slab formwork and
the two structural members are then cast together.
Typical Simple Beam Formwork Details
4. Suspended formworks
Structural steel work is normally encased with concrete to
protect it against corrosion and fire.
Erect one side of the wall formwork and ensure that it is correctly
aligned, plumbed and strutted.
Keeping the forms parallel and the correct distance from one another
is very important.
This is achieved by:
Precast concrete spacer blocks which are cast in.
Steel space tubes which are removed after casting and curing, the voids
created being made good or
Using one of the many proprietary wall tie spacers.
6.1 Wall formwork - Climbing formwork
This is a method of casting a wall in a set of vertical lift heights
using the same forms in a repetitive fashion thus obtaining
maximum usage from a minimum number of forms.
The forms are then removed and fixed to the newly cast concrete.
After each casting and curing of concrete, the forms are removed
and raised to form the next lift until the required height has been
reached.
Typical Climbing Formwork Arrangement
7. Sliding formwork
This is a system of formwork which slides continuously up
the face of the wall being cast by climbing up and being
supported by a series of hydraulic jacks operating on
jacking rods
All joints and holes should be benched to ensure that they are grout
tight.