Structural Specifications
6,000 psi. @ 28 days G.F to 13th Flr. (For all concrete mix of all structural members as shown in the plans)
5,000 psi. @ 28 days 13th Flr. to 22nd Flr. (For all concrete mix of all structural members as shown in the plans)
4,000 psi. @ 28 days 22nd Flr. and above (For concrete mix of all structural members, all foundation works & all bored piles )
3,000 psi. @ 28 days (For all concrte mix of all non-structural elements as shown in the plans)
Cement Factor
Design Strenth 3/4 in. PCD 3/4 in. ORD
6,000 psi 19.00 Bags 18.00 Bags
5,000 psi 17.00 Bags 16.00 Bags
4,000 psi 14.50 Bags 12.75 Bags
3,000 psi 11.50 Bags 10.00 Bags
Ground to Roof
Ground Floor
Description Volume Quantity of Cement
Curbs, upstands & zocalos 0.20 m3 2.30 Bags
Wall Footings 2.35 m3 34.08 Bags
Column bases,isolated ftgs.&pedestals 392.27 m3 5,687.92 Bags
Ground beams/FTB 69.64 m3 1,009.78 Bags
Mat Foundations 372.32 m3 5,398.64 Bags
Slab on grade 174.39 m3 2,528.66 Bags
Columns 33.52 m3 636.88 Bags
RC Walls 6.10 m3 115.90 Bags
Lift Walls 12.56 m3 238.64 Bags
Shear Walls 71.59 m3 1,360.21 Bags
Staircases 2.31 m3 43.89 Bags
Total 1,137.25 m3 17,056.89 Bags
2nd Floor
Description Volume Quantity of Cement
Parapet and planter walls 0.93 m3 10.73 Bags
Curbs, upstands & zocalos 6.57 m3 75.54 Bags
Columns 28.22 m3 536.18 Bags
RC Walls 25.67 m3 487.69 Bags
Lift Walls 15.53 m3 295.07 Bags
Shear Walls 62.19 m3 1,181.58 Bags
Suspended Slabs 102.67 m3 1,950.67 Bags
Beams & Girders 75.59 m3 1,436.23 Bags
Staircases 2.69 m3 51.05 Bags
Total 320.05 m3 6,024.75 Bags
3rd Floor
Description Volume Quantity of Cement
Parapet and planter walls 0.93 m3 10.73 Bags
Curbs, upstands & zocalos 6.57 m3 75.54 Bags
Columns 28.22 m3 536.18 Bags
RC Walls 25.67 m3 487.69 Bags
Lift Walls 15.53 m3 295.07 Bags
Shear Walls 62.19 m3 1,181.58 Bags
Suspended Slabs 96.81 m3 1,839.36 Bags
Beams & Girders 75.97 m3 1,443.40 Bags
Staircases 2.69 m3 51.05 Bags
Total 314.57 m3 5,920.61 Bags
4th Floor
Description Volume Quantity of Cement
Parapet and planter walls 0.93 m3 10.73 Bags
Curbs, upstands & zocalos 6.57 m3 75.54 Bags
Columns 25.45 m3 483.55 Bags
RC Walls 25.67 m3 487.69 Bags
Lift Walls 15.53 m3 295.07 Bags
Shear Walls 62.19 m3 1,181.58 Bags
Suspended Slabs 99.34 m3 1,887.48 Bags
Beams & Girders 77.94 m3 1,480.88 Bags
Staircases 2.69 m3 51.05 Bags
Total 316.31 m3 5,953.58 Bags
5th Floor
Description Volume Quantity of Cement
Parapet and planter walls 0.93 m3 10.73 Bags
Curbs, upstands & zocalos 6.57 m3 75.54 Bags
Columns 25.45 m3 483.55 Bags
RC Walls 25.67 m3 487.69 Bags
Lift Walls 15.53 m3 295.07 Bags
Shear Walls 62.19 m3 1,181.58 Bags
Suspended Slabs 99.34 m3 1,887.48 Bags
Beams & Girders 77.94 m3 1,480.88 Bags
Staircases 2.69 m3 51.05 Bags
Total 316.31 m3 5,953.58 Bags
6th Floor
Description Volume Quantity of Cement
Parapet and planter walls 0.93 m3 10.73 Bags
Curbs, upstands & zocalos 6.57 m3 75.54 Bags
Columns 25.45 m3 483.55 Bags
RC Walls 25.67 m3 487.69 Bags
Lift Walls 15.53 m3 295.07 Bags
Shear Walls 62.19 m3 1,181.58 Bags
Suspended Slabs 99.34 m3 1,887.48 Bags
Beams & Girders 80.44 m3 1,528.37 Bags
Staircases 2.69 m3 51.05 Bags
Total 318.81 m3 6,001.07 Bags
7th Floor
Description Volume Quantity of Cement
Parapet and planter walls 0.93 m3 10.73 Bags
Curbs, upstands & zocalos 6.57 m3 75.54 Bags
Columns 34.21 m3 649.99 Bags
RC Walls 30.80 m3 585.22 Bags
Lift Walls 17.86 m3 339.33 Bags
Shear Walls 71.52 m3 1,358.82 Bags
Suspended Slabs 99.34 m3 1,887.48 Bags
Beams & Girders 82.13 m3 1,560.43 Bags
Staircases 3.22 m3 61.27 Bags
Total 346.58 m3 6,528.82 Bags
8th Floor
Description Volume Quantity of Cement
Curbs, upstands, zocalos & seatwalls 3.14 m3 36.11 Bags
Columns 26.38 m3 501.22 Bags
26th Floor
Description Volume Quantity of Cement
Parapet and planter walls 3.20 m3 36.74 Bags
Curbs, upstands & zocalos 3.39 m3 38.93 Bags
Columns 19.22 m3 278.69 Bags
RC Walls 30.18 m3 437.54 Bags
Lift Walls 13.33 m3 193.30 Bags
Shear Walls 61.88 m3 897.26 Bags
Suspended Slabs 107.05 m3 1,552.28 Bags
Beams & Girders 84.17 m3 1,220.46 Bags
Staircases 2.61 m3 37.86 Bags
Total 325.02 m3 4,693.06 Bags
27th Floor
Description Volume Quantity of Cement
Parapet and planter walls 3.20 m3 36.74 Bags
Curbs, upstands & zocalos 3.39 m3 38.93 Bags
Columns 16.29 m3 236.21 Bags
RC Walls 30.18 m3 437.54 Bags
Lift Walls 13.33 m3 193.30 Bags
Shear Walls 61.88 m3 897.26 Bags
Suspended Slabs 107.05 m3 1,552.28 Bags
Beams & Girders 84.17 m3 1,220.46 Bags
Staircases 2.61 m3 37.86 Bags
Total 322.09 m3 4,650.57 Bags
28th Floor
Description Volume Quantity of Cement
Parapet and planter walls 3.20 m3 36.74 Bags
Curbs, upstands & zocalos 3.39 m3 38.93 Bags
Columns 16.29 m3 236.21 Bags
RC Walls 30.18 m3 437.54 Bags
Lift Walls 13.33 m3 193.30 Bags
Shear Walls 61.88 m3 897.26 Bags
Suspended Slabs 107.05 m3 1,552.28 Bags
Beams & Girders 84.17 m3 1,220.46 Bags
Staircases 2.61 m3 37.86 Bags
Total 322.09 m3 4,650.57 Bags
29th Floor
Description Volume Quantity of Cement
Parapet and planter walls 3.20 m3 36.74 Bags
Curbs, upstands & zocalos 3.39 m3 38.93 Bags
Columns 14.17 m3 205.47 Bags
RC Walls 30.18 m3 437.54 Bags
Lift Walls 13.33 m3 193.30 Bags
Shear Walls 61.88 m3 897.26 Bags
Suspended Slabs 107.05 m3 1,552.28 Bags
Beams & Girders 82.75 m3 1,199.88 Bags
Staircases 2.61 m3 37.86 Bags
Total 318.55 m3 4,599.25 Bags
30th Floor
Description Volume Quantity of Cement
Parapet and planter walls 3.20 m3 36.74 Bags
Curbs, upstands & zocalos 3.39 m3 38.93 Bags
Structural Specifications
6,000 psi. @ 28 days G.F to 13th Flr. (For all concrete mix of all structural members as shown in the plans)
5,000 psi. @ 28 days 13th Flr. to 22nd Flr. (For all concrete mix of all structural members as shown in the plans)
4,000 psi. @ 28 days 22nd Flr. and above (For concrete mix of all structural members, all foundation works & all bored piles )
3,000 psi. @ 28 days (For all concrte mix of all non-structural elements as shown in the plans)
Cement Factor
Design Strenth 3/4 in. PCD 3/4 in. ORD
6,000 psi 19.00 Bags 18.00 Bags
5,000 psi 17.00 Bags 16.00 Bags
4,000 psi 14.50 Bags 12.75 Bags
3,000 psi 11.50 Bags 10.00 Bags
Ground to Roof
Ground Floor
Description Volume Quantity of Cement
Curbs, upstands & zocalos 0.20 m3 2.30 Bags
Wall Footings 2.35 m3 34.08 Bags
Column bases,isolated ftgs.&pedestals 392.27 m3 5,687.92 Bags
Ground beams/FTB 69.64 m3 1,009.78 Bags
Mat Foundations 372.32 m3 5,398.64 Bags
Slab on grade 174.39 m3 2,528.66 Bags
Columns 33.52 m3 636.88 Bags
RC Walls 6.10 m3 115.90 Bags
Lift Walls 12.56 m3 238.64 Bags
Shear Walls 71.59 m3 1,360.21 Bags
Staircases 2.31 m3 43.89 Bags
Total 1,137.25 m3 17,056.89 Bags
2nd Floor
Description Volume Quantity of Cement
Parapet and planter walls 0.93 m3 10.73 Bags
Curbs, upstands & zocalos 6.57 m3 75.54 Bags
Columns 28.22 m3 536.18 Bags
RC Walls 25.67 m3 487.69 Bags
Lift Walls 15.53 m3 295.07 Bags
Shear Walls 62.19 m3 1,181.58 Bags
Suspended Slabs 102.67 m3 1,950.67 Bags
Beams & Girders 75.59 m3 1,436.23 Bags
Staircases 2.69 m3 51.05 Bags
Total 320.05 m3 6,024.75 Bags
3rd Floor
Description Volume Quantity of Cement
Parapet and planter walls 0.93 m3 10.73 Bags
Curbs, upstands & zocalos 6.57 m3 75.54 Bags
Columns 28.22 m3 536.18 Bags
RC Walls 25.67 m3 487.69 Bags
Lift Walls 15.53 m3 295.07 Bags
Shear Walls 62.19 m3 1,181.58 Bags
Suspended Slabs 96.81 m3 1,839.36 Bags
Beams & Girders 75.97 m3 1,443.40 Bags
Staircases 2.69 m3 51.05 Bags
Total 314.57 m3 5,920.61 Bags
4th Floor
Description Volume Quantity of Cement
Parapet and planter walls 0.93 m3 10.73 Bags
Curbs, upstands & zocalos 6.57 m3 75.54 Bags
Columns 25.45 m3 483.55 Bags
RC Walls 25.67 m3 487.69 Bags
Lift Walls 15.53 m3 295.07 Bags
Shear Walls 62.19 m3 1,181.58 Bags
Suspended Slabs 99.34 m3 1,887.48 Bags
Beams & Girders 77.94 m3 1,480.88 Bags
Staircases 2.69 m3 51.05 Bags
Total 316.31 m3 5,953.58 Bags
5th Floor
Description Volume Quantity of Cement
Parapet and planter walls 0.93 m3 10.73 Bags
Curbs, upstands & zocalos 6.57 m3 75.54 Bags
Columns 25.45 m3 483.55 Bags
RC Walls 25.67 m3 487.69 Bags
Lift Walls 15.53 m3 295.07 Bags
Shear Walls 62.19 m3 1,181.58 Bags
Suspended Slabs 99.34 m3 1,887.48 Bags
Beams & Girders 77.94 m3 1,480.88 Bags
Staircases 2.69 m3 51.05 Bags
Total 316.31 m3 5,953.58 Bags
6th Floor
Description Volume Quantity of Cement
Parapet and planter walls 0.93 m3 10.73 Bags
Curbs, upstands & zocalos 6.57 m3 75.54 Bags
Columns 25.45 m3 483.55 Bags
RC Walls 25.67 m3 487.69 Bags
Lift Walls 15.53 m3 295.07 Bags
Shear Walls 62.19 m3 1,181.58 Bags
Suspended Slabs 99.34 m3 1,887.48 Bags
Beams & Girders 80.44 m3 1,528.37 Bags
Staircases 2.69 m3 51.05 Bags
Total 318.81 m3 6,001.07 Bags
7th Floor
Description Volume Quantity of Cement
Parapet and planter walls 0.93 m3 10.73 Bags
Curbs, upstands & zocalos 6.57 m3 75.54 Bags
Columns 34.21 m3 649.99 Bags
RC Walls 30.80 m3 585.22 Bags
Lift Walls 17.86 m3 339.33 Bags
Shear Walls 71.52 m3 1,358.82 Bags
Suspended Slabs 99.34 m3 1,887.48 Bags
Beams & Girders 82.13 m3 1,560.43 Bags
Staircases 3.22 m3 61.27 Bags
Total 346.58 m3 6,528.82 Bags
8th Floor
Description Volume Quantity of Cement
Curbs, upstands, zocalos & seatwalls 3.14 m3 36.11 Bags
Columns 26.38 m3 501.22 Bags
26th Floor
Description Volume Quantity of Cement
Parapet and planter walls 3.20 m3 36.74 Bags
Curbs, upstands & zocalos 3.39 m3 38.93 Bags
Columns 19.22 m3 278.69 Bags
RC Walls 30.18 m3 437.54 Bags
Lift Walls 13.33 m3 193.30 Bags
Shear Walls 61.88 m3 897.26 Bags
Suspended Slabs 107.05 m3 1,552.28 Bags
Beams & Girders 84.17 m3 1,220.46 Bags
Staircases 2.61 m3 37.86 Bags
Total 325.02 m3 4,693.06 Bags
27th Floor
Description Volume Quantity of Cement
Parapet and planter walls 3.20 m3 36.74 Bags
Curbs, upstands & zocalos 3.39 m3 38.93 Bags
Columns 16.29 m3 236.21 Bags
RC Walls 30.18 m3 437.54 Bags
Lift Walls 13.33 m3 193.30 Bags
Shear Walls 61.88 m3 897.26 Bags
Suspended Slabs 107.05 m3 1,552.28 Bags
Beams & Girders 84.17 m3 1,220.46 Bags
Staircases 2.61 m3 37.86 Bags
Total 322.09 m3 4,650.57 Bags
28th Floor
Description Volume Quantity of Cement
Parapet and planter walls 3.20 m3 36.74 Bags
Curbs, upstands & zocalos 3.39 m3 38.93 Bags
Columns 16.29 m3 236.21 Bags
RC Walls 30.18 m3 437.54 Bags
Lift Walls 13.33 m3 193.30 Bags
Shear Walls 61.88 m3 897.26 Bags
Suspended Slabs 107.05 m3 1,552.28 Bags
Beams & Girders 84.17 m3 1,220.46 Bags
Staircases 2.61 m3 37.86 Bags
Total 322.09 m3 4,650.57 Bags
29th Floor
Description Volume Quantity of Cement
Parapet and planter walls 3.20 m3 36.74 Bags
Curbs, upstands & zocalos 3.39 m3 38.93 Bags
Columns 14.17 m3 205.47 Bags
RC Walls 30.18 m3 437.54 Bags
Lift Walls 13.33 m3 193.30 Bags
Shear Walls 61.88 m3 897.26 Bags
Suspended Slabs 107.05 m3 1,552.28 Bags
Beams & Girders 82.75 m3 1,199.88 Bags
Staircases 2.61 m3 37.86 Bags
Total 318.55 m3 4,599.25 Bags
30th Floor
Description Volume Quantity of Cement
Parapet and planter walls 3.20 m3 36.74 Bags
Curbs, upstands & zocalos 3.39 m3 38.93 Bags
2.30 0.20
14,659.07 1,010.97
2,395.52 126.08
17,056.89 1,137.25
86.27 7.50
5,938.48 312.55
6,024.75 320.05
86.27 7.50
5,834.34 307.07
5,920.61 314.57
5,867.31 308.81
5,953.58 316.31
86.27 7.50
5,867.31 308.81
5,953.58 316.31
86.27 7.50
5,914.80 311.31
6,001.07 318.81
86.27 7.50
6,442.55 339.08
6,528.82 346.58
36.11 3.14
6,250.24 328.96
75.67 6.58
6,492.35 341.70
6,568.03 348.28
75.67 6.58
6,439.40 338.92
6,515.08 345.50
75.67 6.58
6,439.40 338.92
6,515.08 345.50
75.67 6.58
6,433.69 338.62
75.67 6.58
6,278.09 369.30
6,353.77 375.88
75.67 6.58
6,278.09 369.30
6,353.77 375.88
75.67 6.58
6,278.09 369.30
6,353.77 375.88
75.67 6.58
6,211.62 365.39
6,287.30 371.97
75.67 6.58
6,287.30 371.97
75.67 6.58
6,211.62 365.39
6,287.30 371.97
75.67 6.58
6,149.40 361.73
6,225.08 368.31
75.67 6.58
6,127.00 360.41
6,202.68 366.99
75.67 6.58
6,127.00 360.41
75.67 6.58
4,698.98 324.07
4,774.66 330.65
75.67 6.58
4,684.14 323.04
4,759.82 329.62
75.67 6.58
4,684.14 323.04
4,759.82 329.62
75.67 6.58
4,617.38 318.44
4,693.06 325.02
4,617.38 318.44
4,693.06 325.02
75.67 6.58
4,574.90 315.51
4,650.57 322.09
75.67 6.58
4,574.90 315.51
4,650.57 322.09
75.67 6.58
4,523.57 311.97
4,599.25 318.55
75.67 6.58
75.67 6.58
4,514.41 311.34
4,590.09 317.92
75.67 6.58
4,488.71 309.57
4,564.38 316.15
114.31 9.94
5,291.58 364.94
5,405.89 374.88
199,137.36 12,063.16
70,315.39 3,700.81
55,872.54 3,286.62
70,462.90 4,859.51
2,486.53 216.22
199,137.36 12,063.16