Professional Documents
Culture Documents
Document Title:
REVISION HISTORY
CIVIL /
MARK DATE DESCRIPTION MEPF
STRUCTURAL
A1 1st Submission
GENERAL CONTRACTOR
Prepared By: NGCB CQC
Project Manager
Approved By:
Sr. Project Manager
EELHI
MGB-MS-020-AR-004 Page 1
TABLE OF CONTENT
1. PURPOSE
2. SCOPE OF WORK and APPLICATION
3. REFERENCES
4. DEFINITIONS AND ABBREVIATIONS
5. SPECIFICATION CLAUSE
6. RESOURCES AND MOBILIZATION
7. CONSTRUCTION EQUIPMENT
8. PERSONNEL
9. MATERIALS
10. CONSTRUCTION PROCEDURE AND METHODOLOGY
11. TESTING AND INSPECTION
12. RESPONSIBILITY
13. DESIGN DRAWINGS
14. QUALITY ASSURANCE
15. HEALTH AND SAFETY
16. ORGANIZATIONAL CHART
17. INSPECTION
18. ATTACHEMENTS
___________________________________________________________________________
1. PURPOSE
This method of statement defines the installation of tiles works to be conducted in the site are in
acquiescence with the Approved for Construction Drawings, Architectural Works Technical
Specification and Material approvals. Where the materials to be install are compliant with the
approve design and using recognized/standard installation practices that are safe and in accordance
with the Project Safety Plan and Associated Safety Procedures. To ensure the work procedures are
complied with the Project Quality Plan, its associated quality procedures and an approved Inspection
and Test Plan for the works.
3. REFERENCES
This method statement has been prepared with reference to the following documents:
Approved For Construction Drawings issued by EELHI approved by Architectural Works
Design Consultant
Submitted approved Shop Drawings
Submitted approved Materials
Approved Project Safety Plan and associated safety procedures
Approved Project Quality Plan and associated quality procedures
Approved Inspection Test Plan
MGB-MS-020-AR-004 Page 2
4. DEFINITIONS and ABREVIATIONS
GL - Gridline
EL - Elevation
ITP - Inspection Test Plan
NCR - Non Compliance Report
NSC - Nominated Subcontractors
PPE - Personal Protective Equipment
SRF - Submittal Review Form
5. SPECIFICATION CLAUSE
The specification requirements for the Installation of Tiles are described within Project Technical
Specification of Structural Works and For Construction Design Drawings as follows:
All materials to be used shall be approved by the designer and comply as required on the above
stated for construction drawings.
According to the work program and planned site access availability, appropriate staff, labors,
equipment and materials will mobilized on the site to set off the said work (“INSTALLATION OF
TILES”) through approved “For Construction Drawing issued by EELHI and approved by the
Architectural Works Design Consultant.
The actual mobilization of staff, workers, equipment and materials, the delivery schedule will be
dependent on site accessibility. Actual site access will need to be notified by the NGCB at least 2
weeks before the actual execution of the works.
It is agreed that the General Contractor (NGCB) will be responsible for the provision of appropriate
temporary construction power and water supplies and lighting system.
7. CONSTRUCTION EQUIPMENT
The typical construction equipment requirements are as listed below and will be used up to the
completion of the activities.
MGB-MS-020-AR-004 Page 3
8. PERSONNEL
Installation of Reinforcement bars, forms, and concrete placing will be organized from central
location by Project Construction Team, both General Contractor and Nominated Subcontractor. It is
planned that the installation will be conducted by the followings:
Finishing Manager
Site Architect/Engineer
Surveyor
Quality Control Architect/Engineer
Safety Officer
Foreman and Leadman for the supervision of Installation of Tiles
Tile Setter
Lineman for Lay-out and Elevations
The above mentioned personnel shall be fully competent and trained to carry out all works
associated with Installation of tiles. They shall have attended the required contractor’s safety
induction and will abide the Health and Safety Plan, policy and procedures as well as Environmental
plan.
9. MATERIALS
All materials delivered to the site will be inspected by EELHI Engineers In-charge, to check that it is
in accordance with the site requirement and conform to the approved design and material
qualification. Delivered tiles shall be inspected before installation; rejected tiles delivery shall not be
accepted and shall be returned to supplier’s facility. Non-compliance to remove rejected delivery will
constitute the issuance of Non Compliance Report from EELHI.
The inward inspection of materials will be carried out in accordance with the relevant of a QA/QC
procedures and or Quality Plans approved by EELHI.
EELHI Engineers has the authority to perform any inspection for the storage of materials from his
own point of view for the checking of material quality or the quantity to maintain the quality
compliance and sufficiency of materials in the site.
Note: No materials shall be permitted to enter and/or installed inside the jobsite without
inspection and approval from CQC & EELHI Engineers upon arrival at jobsite.
The construction procedures and methods described herein are based upon the scope and
application of the method statement summarized in section 2 of this method statement and the work
methods are structured accordingly.
Prior to the commencement of installation of tiles the following are required to be carried out:
Check the approved design and the drawings for the lay-out of tiles are issued with
Approved for Construction status, and in accordance with document control procedure.
Check and review approved lay-out, elevation and embedded items for MEPF.
Check the site access availability, clean and safe.
Check the quantity of tiles and other miscellaneous materials have been ordered and
inspected at NGCB site warehouse are available/ready to use in the site.
Fill cracks, holes and depressions in concrete substrates for tile floors installed with trowel
able leveling.
Where indicated, prepare substrates to receive waterproofing by applying a reinforced
mortar bed that complies with ANSI A108.1A and is slope 1:50 towards drain.
For tile exhibiting color variations, verify that tile has been factory blended and packaged
so tile units taken from one package show same range of colors as those taken from other
MGB-MS-020-AR-004 Page 4
packages and matched approved samples. If not factory blended, either returns to
manufacturer or blend tiles at project site before installing.
All delivered materials shall be inspected upon arrival at the site. The inspection shall be
advised in advance as required by the ITP.
The delivered materials shall be inspected in accordance with the appropriate Quality
Plans and Procedures.
The delivered materials shall be in accordance with the approved design technical
specification, approved for construction drawings and approved material submittal.
Material approvals in form of approved SRF and all pertinent documents and certifications
shall be available throughout incoming of material inspection.
The materials shall be free from defects or damage.
Any materials delivered in the site that are not complying with the approved material
submittals and structural technical specification or rejected by EELHI Engineer shall either
be returned to the point of supply or stored in the site at a suitable quarantine store. NCR
shall be raised for all such materials.
MGB-MS-020-AR-004 Page 5
11. RESPONSIBILITY
The QA/QC Head (NGCB) is the overall responsible body for the implementation and execution of
the works. At the same time, maintaining construction’s quality assurance and quality control
program and quality standards.
The General Contractor (NGCB) will be responsible for all construction activities in the site and will
directly supervise through Construction Supervisors, Foreman and skilled workers at the site. The
QA/QC Head (NGCB) will be responsible for arranging and controlling the inspection and testing
activities.
Notwithstanding the above, it is the responsibility of each individual employed in the project to take
due care to ensure their own personal safety and that of their work colleagues.
17. ATTACHEMENTS
Checklist for inspection of incoming material for Installation of Tiles
Inspection Check list for Installation of Tiles
MGB-MS-020-AR-004 Page 6