Professional Documents
Culture Documents
PAGE No 1 of 9
AL SHAFAR GENERAL CONTRACTING LLC. REV 0
DATE 05/01/2017
SAFETY, HEALTH AND ENVIRONMENTAL PROCEDURE
Project Name: Festival Living Stream-02 HSE-RA 053
Job Description: Floor Screed
Index:
Form 1 Task Analysis Initiation
Form 2 Risk Assessment Process As per Risk Assessment Procedure.
Form 3 Written Safe Work Procedure Result
AUTHORISATION
Prepared by: Approved by
Signature Date Signature Date
HSE Manager Project Manager
Impact
SEQUENCE OF TASK STEPS POTENTIAL INJURIES OR HAZARDS RECOMMENDED CONTROLS
H, S, E
1. Pre-use inspection and use of all Failure of equipment, will cause injuries to Faulty equipment to be repaired/maintained or replaced.
equipment. persons and / or property damage. Guards to be on all Machinery and appropriate PPE to be
Fuel/oil leaks could cause environmental worn.
concerns. H, S, E Engine ran machinery to have fire extinguishers available
locally.
Drip trays/heavy gauge plastic to be insitu in case of leaks
and spill kit to be within the project for accidental spills.
2. Wear appropriate Personal Protective Failure to use Personal Protective Equipment
Equipment. will cause injuries to employees.
Gloves.
Safety boots. Enforce the use of Personal Protective Equipment AT ALL
H
Overalls. times
Hard hat.
Hearing protection.
Eye protection
3. Use trained employees only Failure may result in injuries to persons and Enforce the use of competent persons only throughout the
H, S
property damage. project.
4. Manoeuvring of equipment Faulty of equipment result in injuries to person Equipment driver / operator must hold the valid driving
(mobile pump, concrete truck) and property damage. Oil leaks from the lifting license and vehicle registration.
equipment causing spillage / Environmental Equipment to be inspected by approved third party and
damage. H,S,E checked by operator prior to use
Speed limit of 25Kph on site to be imposed.
Reverse alarm and flagman required for manoeuvring onsite
5. Pouring of concrete Failure may result in injuries to person and H,S,E Proper handling of concrete and safe work procedure for the
property damage. Equipment collision / Health application to be ensure.
and environmental damage Approved method statement must be in place prior to start
the work activity
Use the appropriate PPE.
2 Major – (MTC) 2 Major > 500 AED, No delay 2 Happens occasionally 2 Major Effect - Long term > greater 1 month
3 LTI 3 Major > 10 000 AED, one day delay 3 Happened before
4 Disabling Injuries 4 Serious > 100, 000 AED, >1 day delay 4 Happens regularly
5 Fatality 5 Severe > 1, 000, 000 AED, Weeks delay. 5 Daily occurrence
Risk Rating = A + B + C + D.
Result Classification:
* RR = Risk Rating
1. OBJECTIVE
1. To prevent injuries to employees and / or property damage incidents.
2. PROCEDURE
1. Do pre-use inspection of all equipment to be used and replace or repair faulty items.
2. Use trained competent employees only.
3. Use appropriate Personal Protective Equipment i.e.:
3.1. Hardhat.
3.2. Safety boots.
3.3. Overalls.
3.4. Eye protection.
3.5. Face protection
1. Must have PPE – safety footwear, gloves, hardhat, goggles, face musk, protective clothing etc.
2. Must have appropriate tools and equipment in good condition.
3. Must have weatherproof covers for materials and equipment, waste containers, warning tape.
4. Consider risks and hazards in work area. Refer any concerns to supervisor. Are relevant permits in place?
5. Check if it is necessary to secure area adjacent to work. Refer to supervisor if appropriate.
6. Arrange for transport of materials and equipment to site via supervisor.
7. Ensure materials and equipment are secure or removed when site unattended, eg overnight or during breaks.
Hazards
Harm
Potential Death, Minor/major cuts and contusion, loss of limbs, fractures, damage to respiratory system, electric shock.
Persons in danger
Control measures
No lone working
1. Appropriate PPE must be worn by all workers on site & special PPE should be provided for those who are directly involved in this
activity.
2. Site Induction and tool box talks should be given prior to start job.
3. Equipment to be used in screed finishing should be inspected and must be safe for use.
4. Employees shall be educated in keeping out of possible crash of equipment and collapse onto operatives.
5. Permit to work system should be in place and permit to work system should be followed by all supervisors and engineers.
6. Daily, weekly and monthly inspection to be done regularly any defect found must be reported immediately.
7. Only personnel involve in the screed finishing activities are allowed inside the barricaded area.
8. Enforce the use of competent persons only.
9. Tag out and Log out system must be applied.
10. Ensure proper cable management is being applied.
11. All hand and power tools must be inspected before use
12. All lifting device to be use must be inspected by third party and certified safe for use.
13. Skid loader, dumper etc. to be use for transporting screed must be certified.
14. Competent operator only will use.
15. All operatives should wear PPE as per the job nature.
16. Maintain work area isolated with means of barricade and appropriate signage should be in place.
17. Remind personnel through toolbox talk to observe proper positioning when working
18. All the work should be done under the competent supervision.