Professional Documents
Culture Documents
In this method statement, I will show you how to properly install the
temporary ladder access scaffolding and walkway.
1. Title
3. Materials
3.1 Cuplock scaffolding materials
3.2 Conventional scaffolding tubes and couplers
3.3 Wooden boards
3.4 Aluminum ladders
3.5 Pulley and hand tools
4. Equipment and Tools
4.1 Lifting
4.2 Ladder( For access and egress during offloading on Truck or
trailer only)
4.3 Forklift/telehandler
4.4 Trucks/Pick Up
4.5 Hand tools
5. Methodology
Step 1 – Scaffold base to be prepared firm and level by the main
contractor. The foundation for the scaffold should be maintained in an
adequate condition during the life of the scaffold.
Step 2 – Scaffold base will be installed, using adjustable jacks on
timber sole boards. (Ref. Fig:1)
Step 3 – Standards will be placed upon the adjustable jacks and
connected with ledgers. This will be repeated until all standards are
installed for the base lift (Ref. Fig:1, 2 & 3)
Step 4 – Once the grid layout (Grid 2.5m x 2.5m) has been formed,
the next level of ledgers will be installed
Step 7 – The scaffolders will access the scaffold deck via ladder,
inserting the handrail, whilst at all times maintaining safe systems of
work (SG4) and utilizing safety harness.
Step 8 – The ladder is then installed to the full height of the scaffold
which is 28m, followed by all guard-rails and toe-boards needed at this
level. Ladders will be fixed at an angle of 75 degrees (4:1) and will
project at least 1.05m above the working platform.
Step 9 – Steps 4-8 will be repeated until the ladder tower has been
erected up to the required height.
Step 11 – Scaffold inspected, tagged, and handed over as fit for use.
Step 4 – Once the transoms are fixed, scaffolding boards which are 4
boarded platforms are to be fixed to the transoms using board
retaining couplers (BRC).
Step 6 – Scaffold inspected, tagged, and handed over as fit for use.