Faculty

Architecture, Planning and


Surveying (FSPU)
Program
Diploma in Quantity Surveying
Course
Measurement of Construction
Works IV
Code
DQS251
Credit Hour
04
Semester
04
Lecturer
Mohammad Nasharudine Bin
Shuib
1. To determine element and components that
involved to the PC Sum and Prov. Sum
2. To measure according to the latest
standard method of measurement
SMM2
3. To protect the interest of the client and the
contractor
4. To minimize future disagreement
1. Some aspects of a building project are not measured in
detail but are included in the bills as LUMP SUM items.

2. These sums of money are intended to cover specialist work


not normally undertaken by the general contractor: PRIME
COST SUMS.

3. PC Sums cover work undertaken by nominated


subcontractors, nominated suppliers and statutory
undertakings. Based on quotations for items of work.

4. Work which cannot entirely foreseen, defined or detailed at


the time that the tendering documents are issued:
PROVISIONAL SUMS.
The Provisional Sums shall be expended as directed by the Superintending Officer /
Architect or deducted in whole or in part if not expended

Telephone Rental and Call Charges

Landscaping Works

Relocation of Existing Services & Decanting Works

Signage

Upgrading The Existing Sewerage Treatment Plant

Sanitary Plumbing for Existing Building

Extension of TNB Sub-Station


PRIME COST SUM AND
PROVISIONAL SUM
MEASUREMENT RULES

SECTION A
GENERAL RULES
Preliminaries, Prime Cost Sum & Provisional Sum

Section A : General Rules

A.8 – Provisional Sum or Prime Cost Sum

1. Where this document requires provisional or prime cost sums to


be given in accordance with this clause, the choice of terms shall
be made in conformity with the following definitions unless
otherwise provided in the conditions of contract:

a. The term ‘provisional sum’ is defined as a sum provided


for work or for costs which cannot entirely be foreseen,
defined or detailed at the time the tender documents are
issued.

8
Preliminaries, Prime Cost Sum & Provisional Sum

9
ITEM DESCRIPTION UNIT AMOUNT (RM)

PROVISIONAL SUMS

Notes:
The Provisional Sums shall be expended as directed by the
Superintending Officer (S.O.) / Architect or deducted in whole
or in part if not expended

Guard House

A Allow a Provisional Sums of Ringgit Malaysia: Fifty


Thousand Only (RM50,000.00) for Guard House. SUM 50,000.00
Preliminaries, Prime Cost Sum & Provisional Sum

11
ITEM DESCRIPTION UNIT AMOUNT (RM)

PROVISIONAL SUMS

Notes:
The Provisional Sums shall be expended as directed by the
Superintending Officer (S.O.) / Architect or deducted in whole
or in part if not expended

TNB Sub-Station (Double Chamber)

A Allow a Provisional Sums of Ringgit Malaysia: One


Hundred Twenty Thousand Only (RM120,000.00) for TNB
Sub-Station (Double Chamber). SUM 120,000.00
Preliminaries, Prime Cost Sum & Provisional Sum

13
ITEM DESCRIPTION UNIT AMOUNT (RM)

PROVISIONAL SUMS

Notes:
The Provisional Sums shall be expended as directed by the
Superintending Officer (S.O.) / Architect or deducted in whole
or in part if not expended

Built-in Furniture

A Allow a Provisional Sums of Ringgit Malaysia: Seven


Hundred Fifty Thousand Only (RM750,000.00) for Built-in
Furniture. SUM 750,000.00
Preliminaries, Prime Cost Sum & Provisional Sum

15
ITEM DESCRIPTION UNIT AMOUNT (RM)

PROVISIONAL SUMS

Notes:
The Provisional Sums shall be expended as directed by the
Superintending Officer (S.O.) / Architect or deducted in whole
or in part if not expended

Landscaping Works

A Allow a Provisional Sums of Ringgit Malaysia: Two


Hundred Ten Thousand Only (RM210,000.00) for
Landscaping Works. SUM 210,000.00
ITEM DESCRIPTION UNIT AMOUNT (RM)
PROVISIONAL SUMS

Notes:
The Provisional Sums shall be expended as directed by the
Superintending Officer (S.O.) / Architect or deducted in whole
or in part if not expended

Interior Design Works


A Allow a Provisional Sums of Ringgit Malaysia: Two
Hundred Fifty Thousand Only (RM250,000.00) for Built-in
Furniture. SUM 250,000.00

Internal Signages and Graphic


B Allow a Provisional Sums of Ringgit Malaysia: One
Hundred Thirty Thousand Only (RM130,000.00) for
Internal Signages and Graphic. SUM 130,000.00

Landscaping Works
C Allow a Provisional Sums of Ringgit Malaysia: Two
Hundred Ten Thousand Only (RM210,000.00) for
Landscaping Works. SUM 210,000.00

Total: 590,000.00
The Prime Cost Sums shall be expended as directed by the Superintending Officer/Architect
or deducted in whole or in part if not expended

Electrical Installations

MATV, CCTV and PA System.

Air-Conditioning and Mechanical Ventilation System

Fire Fighting System

Hot Water System

Lift and Escalator System


PRIME COST SUM AND
PROVISIONAL SUM
MEASUREMENT RULES

SECTION A
GENERAL RULES
Preliminaries, Prime Cost Sum & Provisional Sum

Section A : General Rules

A.8 – Provisional Sum or Prime Cost Sum

1. Where this document requires provisional or prime cost sums to be


given in accordance with this clause, the choice of terms shall be
made in conformity with the following definitions unless otherwise
provided in the conditions of contract:

b. The term ‘prime cost sum’ is defined as a sum provided for


work or services to be executed by a nominated sub-
contractor, a government or a statutory authority or for
materials or goods to be obtained from a nominated
supplier. Such sum shall be deemed to be exclusive of any
profit required and/or attendance to be provided by the
main contractor and provision shall be made for the
addition thereof where applicable.

21
Preliminaries, Prime Cost Sum & Provisional Sum

MAIN
CONTRACTOR

NOMINATED DOMESTIC

SUB- SUB-
SUPPLIER SUPPLIER
CONTRACTOR CONTRACTOR

22
Preliminaries, Prime Cost Sum & Provisional Sum

• Work or services to be executed by a NOMINATED SUB-


CONTRACTOR, a government or a statutory authority
• Work or services (supply and install) done by third party or sub-
contractor nominated by client/employer
• For example Electrical Works, Air-Conditioning Installation, and

1 etc.
• Allow for profit in percentage (%)
• Allow for Attendance in Lump Sum

• Materials or goods to be obtained from a NOMINATED SUPPLIER


• Materials or goods to be supplied (supply only) by third party or
supplier, nominated by nominated by client/employer.
• The main contractor will done the installation works for the
2 supplied items/works.
• Only allow for profit in percentage (%)

23
Preliminaries, Prime Cost Sum & Provisional Sum

24
ITEM DESCRIPTION UNIT AMOUNT (RM)

PRIME COST SUMS

Notes:
The Prime Cost Sums shall be expended as directed by the
Superintending Officer (S.O.) / Architect or deducted in whole
or in part if not expended

Fire Fighting System

A Allow a Prime Cost Sums of Ringgit Malaysia: One Million


Six Hundred Fifty Thousand Only (RM1,650,000.00) for
Fire Fighting System. SUM 1,650,000.00

Allow for profit ……….% %

Allow for attendance L.S.


Preliminaries, Prime Cost Sum & Provisional Sum

26
ITEM DESCRIPTION UNIT AMOUNT (RM)

PRIME COST SUMS

Notes:
The Prime Cost Sums shall be expended as directed by the
Superintending Officer (S.O.) / Architect or deducted in whole
or in part if not expended

Hot Water System

A Allow a Prime Cost Sums of Ringgit Malaysia: Six Hundred


Fifty Thousand Only (RM650,000.00) for Hot Water
System. SUM 650,000.00

Allow for profit ……….% %

Allow for attendance L.S.


Preliminaries, Prime Cost Sum & Provisional Sum

28
ITEM DESCRIPTION UNIT AMOUNT (RM)

PRIME COST SUMS

Notes:
The Prime Cost Sums shall be expended as directed by the
Superintending Officer (S.O.) / Architect or deducted in whole
or in part if not expended

Air-Conditioning and Ventilation System

A Allow a Prime Cost Sums of Ringgit Malaysia: One Million


Two Hundred Fifty Thousand Only (RM1,250,000.00) for
Air-Conditioning and Ventilation System.
SUM 1,250,000.00
Allow for profit ……….%
%
Allow for attendance
L.S.
Preliminaries, Prime Cost Sum & Provisional Sum

30
ITEM DESCRIPTION UNIT AMOUNT (RM)

PRIME COST SUMS

Notes:
The Prime Cost Sums shall be expended as directed by the
Superintending Officer (S.O.) / Architect or deducted in whole
or in part if not expended

Dental Chair and Equipments

A Allow a Prime Cost Sums of Ringgit Malaysia: Six Hundred


Seventy Four Thousand Only (RM674,000.00) for Dental
Chair and Equipments (Supply Only). SUM 674,000.00

Allow for profit ……….% %


ITEM DESCRIPTION UNIT AMOUNT (RM)
PROVISIONAL SUMS

Notes:
The Provisional Sums shall be expended as directed by the
Superintending Officer (S.O.) / Architect or deducted in whole
or in part if not expended

Interior Design Works


A Allow a Provisional Sums of Ringgit Malaysia: Two
Hundred Fifty Thousand Only (RM250,000.00) for Built-in
Furniture. SUM 250,000.00

Internal Signages and Graphic


B Allow a Provisional Sums of Ringgit Malaysia: One
Hundred Thirty Thousand Only (RM130,000.00) for
Internal Signages and Graphic. SUM 130,000.00

Landscaping Works
C Allow a Provisional Sums of Ringgit Malaysia: Two
Hundred Ten Thousand Only (RM210,000.00) for
Landscaping Works. SUM 210,000.00

Total: 590,000.00
ITEM DESCRIPTION UNIT AMOUNT (RM)
PRIME COST SUMS

Notes:
The Prime Cost Sums shall be expended as directed by the
Superintending Officer (S.O.) / Architect or deducted in whole or in
part if not expended.

Dental Chair and Equipments


A Allow a Prime Cost Sums of Ringgit Malaysia: Six Hundred
Seventy Four Thousand Only (RM674,000.00) for Dental Chair
and Equipments (Supply Only). SUM 674,000.00

Allow for profit ……….% %

Air-Conditioning and Ventilation System


B Allow a Prime Cost Sums of Ringgit Malaysia: One Million Two
Hundred Fifty Thousand Only (RM1,250,000.00) for Air-
Conditioning and Ventilation System. SUM 1,250,000.00

Allow for profit ……….% %

Allow for attendance L.S.

TOTAL: