Millennium Erectors Corporation

9445 Retiro St., Guadalupe, Makati City

Project : Oriental Gardens Makati (Lilac Tower) Report No. 063


Location : Don Chino Roces Ave. corner Export Drive, Makati City Date April 25, 2014
Contract Package Shift Day
Working Time : from 7:00AM to 4:00PM Weather Sunny

Daily Construction Report


MANPOWER
Staff NO MH NO MH Equipments NO HRS.
1. Project Manager 1 8 1. Leadman 3 24 1. Cut off machine 1 8
2. QA/QC 2 16 2. Carpenter 2 16 2. Mini Dump Truck 1 8
3. Site Engineer 2 16 3. Mason 5 40 3. Circular Saw 1 8

4. Electrical Engineer 1 8 4. Tile Setter 3 24 4. Service Vehicle 1 8


5. Mechanical Coordinator 1 8 5. Welder 1 8 5. Power Washer 2 16
6. Cost Engineer 0 0 6. Laborer 53 424 6. Grinder 6 48
7. Safety Officer 1 13 Total 67 536 7. Auto level 1 8
8. Project Nurse 0 0 TRADECON 8. Mech.Concrete Vib. 1 8

9. CAD Operator 1 8 KALAYAAN 4 32 9. Hammer Drill & Rotary 10 80


10. Timekeeper 1 10 ICC 18 144 10. Chipping Gun 1 8
11. Foreman 1 8 ROSTRAM 3 24 11. Welding machine 5 40
Total 11 95 S&H 12 96 12. Gondola 0 0
ARLO 9 72 13. Hand Drill 6 48

General Services NO MH YYD 2 16 14. Cutting Tools 2 16

1. Spot Checker 2 26 V. ROQUE 14 112 15. Vacuum Cleaner 2 16


2. Electrician 1 13 G. S. GO 4 32
3. Electrical Aide 2 26 CARSON 0 0

4. Line and Grade 0 0 CARDRIAN 0 0


5. L&G Helper 1 13 POLYGON 0 0
6. Warehouse Man 1 13 STELSEN 1 8
7. Warehouse Aide 1 13 SCHINDLER 3 24
8. Pump Tender 1 13 Total 70 560
9. Utility 3 39 SUBCON
Total 12 156 FIVE STAR 1 8

CHER 21 168

Operator NO MH FRANCISCAN 2 16
1. Driver 1 13 BIO 101 0 0

Total 1 13 MIGHTY 29 232


FMPI 1 8

Total 194 1552 Prepared by :

NO MH ___________________________

Description of Activities Performed Today: MEC


GRAND TOTAL 285 2352
1. Masonry works @ GF to 32nd floor
2. Painting works Interior @ 31st -32nd floor
3. Installation/Rectification of tiles @ 24th - 32nd floor Received by:

4.Puchlisting @ 9th-32nd floor

5. Ceiling works @ 32nd floor __________________________________


6. Painting works @ common areas DAAA
7. Rectification of Epoxy paint @ stair 1 & Common areas
8. Painting of Main Doors & T/B 31st-32nd
Millennium Erectors Corporation
9445 Retiro St., Guadalupe, Makati City

Project : Oriental Gardens Makati (Lilac Tower) Report No. 002


Location : Don Chino Roces Ave. corner Export Drive, Makati City Date August 24, 2011
Contract Package Shift Night
Working Time : from to Weather

Daily Construction Report


MANPOWER
Staff NO MH General Services NO MH Operator NO MH
1. Project Manager 1. Time Keeping 1. Driver

2. Superintendent 2. Warehouse 2. Tadano Oprt.


3. Site Engineer 3. Line & Grade 3. Backhoe Optr.

4. Quality Control 4. Electrician 4. Mini Loader Optr

5. Office Engineer 5. Utility 5. Genset Optr.

6. Autocad Operator 6. Leadman 6. Bulldozer Optr.

7. Safety Officer 7. Vibratory Roller Optr.


8. Project Nurse 8. Dumptruck Optr.

Total 0 0 Total 0 0 Total 0 0

Carpenter NO MH Welder NO MH Labor NO MH


1. Curanto 1. 1.

2. Total 2.
3. 3.
4. Steelman NO MH 4.

5. 1.

Total 0 0 Total 0 0 Total 0 0

Grand Total 0 0

Equipments NO HRS. Equipments NO HRS.


1. Backhoe
2. Mini Loader

3. L-300 FB

Description of Activities Performed Today:

Remarks:

Prepared by: Received by:

Jose P. Maaliw
MEC DAAA
\ NO MH
1. 5 87
Total 5 87