Professional Documents
Culture Documents
- Original 06.10.2021
PREPARED BY APPROVED BY
Initial
Standard Operating Procedure
Title: Squirrel cage Induction motor
OBJECTIVE
To provide procedure for preventive maintenance of squirrel cage induction motor which helps to
increase the reliability, availability, avoid from unplanned shutdown and breakdown which cause
high loss to the company by plant stoppage.
SCOPE
This procedure is applicable to the process of carrying out preventive maintenance of squirrel
cage induction motor.
RESPONSIBIITY
These documents should act as a legal binding towards the process.
The site electrical engineer.
FLOW CHART
Flow chart for preventive maintenance of squirrel cage induction motor.
Standard Operating Procedure
Title: Squirrel cage Induction motor
PREVENTIVE MAINTENANCE
Wear Suitable PPE and Perform
Quick Equipment Check
PROCEDURE
MOUNTING OF MOTOR
Check the mounting of motor i.e nuts and bolts
Check motor bearing by listening the noise or if the motor taking high current despite of good IR &
resistance value.
Check motor shaft if there is alignment problem while connecting shaft mechanical rotating part.