CL-NG-6460-002-035 Page Number: Checklist of Circuit Switchers Commissioning 1 of 2
1.0 Equipment General Data and Information
Substation Bay/Panel Equipment Serial No
2.0 Mechanical Checks and Visual Inspections
Item Description Done Remarks
1. Perform mechanical checks and inspection of isolating disconnect. 2. Perform mechanical checks and adjustments on interrupter unit according to the manufacturer’s instructions. 3. Check the low SF6 target at the interrupter units. 4. Check interrupter position indicator operation.
3.0 Electrical Tests
Item Description Done Remarks
1. Resistance of main current path (terminal to terminal) at 100 Amps DC. 2. Functional check of all electrical interlocks. 3. Measure motor starting and running current. 4. Check position-signaling contacts (if applicable). 5. For motor operating mechanisms: a. Check mechanism cabinet properly grounded. b. Check correct setting of motor limit switched (open/close). c. Check correct operation of all auxiliary “a” and “b” contacts. d. Measure switches opening and closing times and motor current at rated voltage (for fast acting disconnects and grounding switches perform a timing test with an electronic oscillograph). e. Minimum voltage operation (close and open) at 90V DC. f. Functional check of thermostat and space heaters. Measure heater current. g. Insulation test all control and power wiring/cables at 500V DC Archiving System Website: http://AMAS NATIONAL GRID
Title: Index Number:
Checklist of Circuit Switchers Commissioning CL-NG-6460-002-035
Page Number: 2 of 2
h. Check that in the manual mode, insertion of the operating
handle automatically disconnects the motor DC supply. 6. Check shunts trip device operation. 7. Verify proper operation sequence of interrupters and disconnects. 8. Insulation power factor test of the interrupters. 9. Timing test of the interrupter contacts with electronic oscillograph.