2.0 RESPONSIBLITIES
- Anyone working in testing location during commission stage must follow the safety
requirements as per SEC rules and CSD employees are responsible for applying
safety rules in all places which they working in.
- Project site engineer is responsible for committing the contractor to prepare testing
and commissioning places to be done in proper climate conditions as per Company
policies, procedures and accepted temperatures the relays, devices and test
equipment can be tested or operated within it.
- Any of CSD staff is responsible for testing activities according to approved
specification and design and he shall not start any test for any Line & Cable
Differential Protection Relay (87L/87C) until providing the following:
- Its responsibility of the commissioning contractors to provide all testing Line &
Cable Differential Protection Relay (87L/87C) with its valid calibration certificates
that will maybe require applying the testing / commissioning procedure in proper
manner.
- Its responsibility of the CSD Engineer/Technician to check and witness all activities
required for Line & Cable Differential Protection Relay (87L/87C) following all of
this work instruction.
- CSD Engineer/Technician is responsible for recording status of any test for Line &
Cable Differential Protection Relay (87L/87C) in its check list and test form as per
the following work instruction.
- Each check list and test form shall be signed by CSD engineer/technician and
testing contractor engineer.
Reference / criteria
Item Description
limit
1. General Visual Inspection WI-NG-6460-002-056
Reference / criteria
Item Description
limit
WI-NG-6460-002-057
1. General electrical tests & WI-NG-6460-002-
058
Check Measurements:
2.
Secondary & primary values of V and I for all phases.
3. Check Differential Protection
3.1 Check I –DIFF > pick up and its time
3.2 Check Under switch on condition if applicable
3.3 Check I –DIFF >> pick up and its time
3.4 Bias Characteristic Testing
3.5 Unrestrained Current Pick-up Test and its time
3.6 Check Inrush restrain current
2nd harmonic blocking test: Inject one phase current as an
3.6.1 example (1A - 60 HZ and 0.22 A - 120 HZ) the relay will
not trip because of second harmonic inrush block
Cross blocking test: Inject one phase current as an
example ( 1A - 60 HZ and 0.22 A - 120 HZ) and another
3.6.2
phase by (1A – 60 HZ) The relay will trip after the
summation of time by cross blocking with 2nd harmonic
3.7 Check 5th harmonic test
4. Check Thermal over load protection
4.1 Check with memory
Check with memory without preload Before injection you
4.1.1
a. Calculate the trip time for thermal relay must reset the
Archiving System Website: http://AMAS TP-NG-6250-001-007
NATIONAL GRID
4.0 REFERENCES
Index Number /
Title
Reference Number
PR-NG-6460-002 Project Commissioning Procedure
WI-NG-6460-002-056 Protection Relays general mechanical checks & visual inspection
WI-NG-6460-002-057 Protection Relays general electrical tests
WI-NG-6460-002-058 Guidelines for Testing Digital & Numerical Protection & Control
Relays and IEDs
WI-NG-6460-002-064 Over-current & Earth Fault Protection Relay
CL-NG-6460-002-72 Checklist for Line & Cable Differential Protection (87L87C)
This document shall comply in accordance with the existing Company’s Rules and Regulations.
Any modifications therein found not conformance with the document shall be declared invalid.
For clarification and verification on this document, contact the following:
Substation
Bay/Panel
Equipment Serial No