2.0 RESPONSIBILITIES
- Anyone working in testing location during the commissioning stage must follow the
safety instructions as per SEC rules and CSD employees are responsible for
applying safety rules in all places which they are working in.
- Project site engineer is responsible for committing the contractor to prepare testing
and commissioning places to be done in proper climate conditions as per Company
policies, procedures and accepted temperatures the relays, devices and test
equipment can be tested or operated within it.
- CSD staff are responsible for witnessing the activities according to approved
specification and design
- CSD employee shall not start any test until the T&C Contractor engineer providing
the following:
o The T&C Contractor Engineer certification from the manufacturer of the Partial
Discharge (PD) measuring unit.
o Test forms.
o The Manufacturer written confirmation must be provided during the base design
that all cable terminations and joints shall be performed under the direct strict
supervision of terminations and joints manufacturer according to TES-P-104.04
o Factory Tests Results.
o Approved drawings.
o Test equipment valid calibration certificates.
o Contractor engineer pre-qualification certificate.
o Technical Data Schedule
CSD employee is responsible to check and witness all activities required for
13.8KV and 33KV XLPE Power Cables following all of this work instruction.
- CSD employee is responsible for recording the status of any test 13.8KV and
33KV XLPE Power Cables in its checklist and test form as per this work
instruction.
- CSD employee shall refer to the Technical Data Schedule, and the approved High
Voltage test procedure, especially in case of any dispute about test values.
Table No. 1: Test Voltage Levels Test Voltage Levels for 13.8 KV and 33 KV Power
Cables Power Cables
High Voltage Test Partial Discharge
U U0 Apply 2 U0 Measure PD at
Voltage Test Time Period
for 10 s 1.73 U0
kV kV kV Minutes kV kV
13.8 8 24 60 16 13.8
33 19 57 60 38 33
Note:
U0 is the rated voltage between conductor and earth or metal screen for which the cable
is designed.
U is the rated voltage between conductors for which the cable is designed.
The test voltage to be applied shall be subject to agreement among CSD, T&C Contractor
and Cable Supplier.
4.0 REFERENCES
Index / Reference
Title
Number
PR-NG-6460-002 Project Commissioning Procedure
Checklist for Commissioning of 13.8kV and 33kV XLPE Power
CL-NG-6460-002-041
Cables
IEEE Std 1185-2010 IEEE Recommended Practice for Cable Installation in Generating
Stations and Industrial Facilities
IEC 60060-3 First IEC 60060-3 High-Voltage Test Techniques Part 3: Definitions and
edition 2006-02 requirements for on-site testing - Edition 1.0
IEC 60502-2 Edition Power cables with extruded insulation and their accessories for
3.0 2014-02 rated voltages from 1 kV (Um = 1,2 kV) up to 30 kV (Um = 36 kV)
IEC 61442 Second Test methods for accessories for power cables with rated voltages
edition 2005-03 from 6 kV (Um = 7,2 kV) up to 30 kV (Um = 36 kV)
11-TMSS-04 11kV, 13.8kV, 33kV & 34.5kV Medium Voltage Power Cables
TCS-P-104.03 Trenches and ducts
TES-P-104.05 Cable Installations, Engineering Requirements
IEC 60229 Edition 3.0 Electric cables – Tests on extruded oversheaths with a special
2007-10, protective function
IEC 60885-3:2015 Electrical test methods for electric cables –
Part 3: Test methods for partial discharge measurements on
lengths of extruded power cables
IEEE Std 400.2–2004 IEEE Guide for Field Testing of Shielded Power
Cable Systems Using Very Low Frequency (VLF)
Substation
Bay/Panel
Equipment Serial No