SN ACTIVITY
1.1 Access to the water and its surrounding area is safe and satisfactory for
plant operation and maintenance with floor gratings, trench covers, hand
rails in position and secure and no debris lying about.
1.5 Check name plate is clearly visible, permanently fixed and that the details
are correct.
1.6 Paint work and finishing are complete and satisfactory.
1.8 Is the motor environment likely to deteriorate to such on extent that the
motor condition and performance a may be adversely affected?
1.9 Check that motor is undamaged, fitted and satisfactorily mounted with
foundation bolt tight.
1.10 Check that motor is uncompleted, free to rotate and as far as practicable
that nothing is catching internally.
1.11 Check all bolted joints and cover plates on the stator frame and heat
exchanger to ensure that:
a. Oil grade :
b. Oil Level :
c. Oil Quantity :
d. Oil Analysis :
(if applicable)
e. Method of lubrication :
f. Check all filler caps in position and secure.
g. Where removable inspection caps are fitted, ensure that these are in
position and secure.
h. Check oil rings are free to rotate.
i. Check oil wipers and vents are satisfactory.
j. Where fitted check oil flow sight glasses are securely fitted, undamaged
and that the glasses are clean.
1.13.2 BALL/ROLLER BEARINGS
a. Size and details D.E. –
N.D.E -
b. Grease grade.
c. Check that the bearings are greased.
1.13.3
TITLING PAD TYPE THRUST AND JOURNAL BEARINGS
a. Oil grade.
b. Oil Level
c. Oil Quantity
d. Oil analysis (if applicable)
e. Method of lubrication
f. Carry out checks as per item f to item j of 1.13.1 and work the same
below.
f g h i j Item as in 1.13.1
Mark if satisfactory
1.14 OIL COOLER/BEARING JACKET (WHERE FITTED)
a. Check that pipe work, valves, flow indicators etc. are installed as per
manufactures recommendations and relevant system drawings.
b. Ensure that all pipe work and fittings are fitted satisfactorily and adequately
supported.
a. Check that the air tubes are clean, clear and not chocked.
c. Check that fan covers and shields are securely fitted and all joints are
tightened.
1.16 AIR COOLER WATER COOLED
Item of
Mark if
Satisfactory
1.17 Check that any special tools etc. which are to be supplied under the terms
of contract are available and undamaged.
Record results below and state the method used to obtain them:
METHOD:
RESULTS:
1.19.1 Check that the motor frame, terminal box and table earthing connections
are complete, secure and tight.
1.19.2 Check terminal connections are adequately shrouded and/or electrical
clearance are satisfactory.
1.19.3 Check terminal box is clean and dry.
1.19.4 Check gasket is in good conditions and correctly fitted and the buzz lid
secure with all fastenings in position.
1.19.5 Check terminal box breathers (if provided ) are secure charged and dry.
1.19.6 Check that terminal box pressure relief diaphragm (if fitted ) are complete
and correctly fitted.
Repeat items listed under 1.19 from 1.19.1 to 1.19.6 applied to above and
work below:
Item as 1.19
Mark if
Satisfactory
1.21.3 Check gasket is in good condition and the link box lid is securely tightend
with all fastenings in position.
1.21.5 Check pressure relief diaphragms (if fitted) is intact and correctly fitted.
1.21.6 Check C.T.s are correctly fitted, checked, tested and securely wired up.
1.22.3 Check gasket is in good condition and the box lid is tight with all fastenings
in position.
1.23.1 Ensure that rotor winding temperature detectors are checked / tested and
calibrated.
1.23.2 Check terminal box for tightness of all connections gasket and lik cover
fitting.
1.24 CHECK MOTOR AIR GAP READINGS: (IF PROVISION IS MADE FOR
THIS PURPOSE)
Alternatively ensure that readings are available. Record them below and
obtain signature of competent person who has witnessed or carried out the
observations.
Signature
____________________
SETTING
Differential Protection
ANY OTHERS
Carry out IR test 2.5 KV d.c. taking readings at one minute and ten minutes
after the initial application of the test voltage and compute the polarization
Index (P.I).
Rw = Pt (KV + 1)
Values for Pt are given in Apeendix-2 and should be used to determine Rw.
If the PI is greater than 1.5 and the 10 minutes IR is higher then or equal to
Rw then the machine may be energized without drying out.
2.1.2 Using very low inductive resistance equipment, measure and record the
stator winding d.c. references.
R- Y - ohms.
Y- B- ohms.
B- R- ohms.
Ambient – temperature
2.2.1 Measure and record heater element I.R. (all of them if more then one is
fitted):
IR = M ohms.
IR = M ohms.
STANDARD CHECKLIST: SYSTEM COMMISSIONING SHEET 12 OF 21
STATION:
Date:
UNIT: _____
PLANT ITEM: H.V. SQUIRREL CAGE INDUCTION
Ref. No.:
MOTOR
STATUS
SN ACTIVITY
2.2.2 Measure all record the heater element resistance (all of them if more then
one is fitted) :
IR = ohms.
IR = ohms.
2.3.2 Where fitted, check the shaft earthing brush for freedom of movement and
for good connection to earth.
2.3.4 Check bearing pedestal insulation resistance using L.V. test set (Megger
on 100V mange for example) lifting the earth brush/earth strap as
necessary and replacing after test.
IR should be at least 1.0 M ohms and preferably more for a now machine
in clean condition.
2.4.1 Check that safety clearance certificate and safety clearance notification
issued and effective for switchgear, cables and motor.
2.4.2 Check section 1 of this S.C.L. are complete.
2.4.3 If motor heater is fitted, check and record the circuit IR from the source of
supply.
2.4.4 Energize the motor heater circuit for the first time and if practicable and
safe measure current drawn is nominal and satisfactory. It may be left in
service or switched off as specified by manufacturer.
IR = M ---
2.4.7 Check safety notices and barriers erected as necessary.
2.4.8 Check motor uncoupled, free to rotate and any loose parts of the coupling
removed or securely fitted so as to be clear of all rotating parts.
2.4.9 Check cooling water services to the motor and its auxiliaries are in
operation and effective.
STANDARD CHECKLIST: SYSTEM COMMISSIONING SHEET 14 OF 21
STATION:
Date:
UNIT: _____
PLANT ITEM: H.V. SQUIRREL CAGE INDUCTION
Ref. No.:
MOTOR
STATUS
SN ACTIVITY
2.0 TEST PROCEDURE
2.5.4 Ensure all links are in position and switch on the control and indication
supplies (and any auxiliary supplies if applicable)
2.5.5 Check that the spring is charged and the white indication lamp is
illuminated.
2.5.9 Check local red lamp is on and that the spring recharges.
2.5.14 Trip the OCB from remote and check lamp indications.
2.5.15 Close from remote and trip the OCB from emergency stop push button.
2.6.3 Request control room to close OCB to energize the motor for the first time
(observe indications and starting current).
2.6.4 Check motor no load current is satisfactory and confirm the direction of
rotation. If direction is reverse stop the motor immediately and obtain
permit to work for reversing the direction of rotation.
a. Time / Date.
b. System voltage.
c. System Frequency.
d. Starting current.
g. Running current.
h. Motor speed.
i. Bearing vibrations.
V H A
D.E.
N.D.E.
STANDARD CHECKLIST: SYSTEM COMMISSIONING SHEET 18 OF 21
STATION:
Date:
UNIT: _____
PLANT ITEM: H.V. SQUIRREL CAGE INDUCTION
Ref. No.:
MOTOR
STATUS
SN ACTIVITY
2.0 TEST PROCEDURE
2.6.7 Remarks :
2.6.10 When the motor is shut down record the run down time.
2.6.11 Rack out the OCB into isolated position and check all indications lamps.
APPENDIX – 3.0
APPENDIX – 3.1
DE-COUPLED RUN
REMARKS:
Signature
Name Remarks
& Date
Contractor-Erection (M & P)
JSWERL – Erection (Mech)
JSWERL – Electrical
JSWERL – C & I
JSWERL – TS
JSWERL - Commissioning