You are on page 1of 4

ACESCo Std.

No: 10031-9-VGS-G000-00610-02

REVISED AS PER GECOL/ACESCo COMMENTS –


2 Z.Y. M.C M.C E.C. 12.02.2009
FOR APPROVAL
1 REVISED AS PER GECOL/ACESCo COMMENTS Z.Y. M.C M.C E.C. 24.12.2008
0 FOR APPROVAL Z.Y. M.C M.C E.C. 27.11.2008
REVISION DESCRIPTION BY CHECK APPROVED APPROVED DATE
OWNER :

GENERAL ELECTRIC COMPANY OF LIBYA


ZWITINA 2X285 MW GAS TURBINE PROJECT

CONSULTANT :

Arabian Consulting & Engineering Services Co.

TITLE :

STANDARD INSPECTION AND TEST PLAN


ITP No: 936
UNIT AUXILIARY TRANSFORMERS
SUB-CONTRACTOR : MAIN CONTRACTOR :

PROJECT DOC. NO:

SIZE JOB NO. AREA DEPT. CODE DESIGN REV


SCALE
This Drawing/Document is the property of
ENKA TEKNIK and it cannot be used,
reproduced or loaned to third parties without
the written permission of ENKA TEKNIK 4 7 4 0 0 3 2 0 T - 9 7 5 05 2 NTS
FORMS INDEX

LIST OF ATTACHED FORMS

No. Form No. Rev. Description


1. ITP - 936 1 STANDART ITP:936 – UNIT AUXILIARY
TRANSFORMERS

LIST OF REFERENCED FORMS

No. Form No. Doc. Ref. Description


STANDARD INSPECTION AND TEST PLAN Document No:
47400320T97505
ITP No: 936 Date:12.02.2009
UNIT AUXILIARY TRANSFORMERS Rev.No:2
Page: 4
PROJECT NAME: ZWITINA POWER PLANT PROJECT NO:740032 DRAWING NO/ISO NO: OTHER REFERENCES:

MAIN ACTIVITY NAME: EQUIPMENT NO: UNIQUE ID:

Activity Activity Inspection/Test Reference Document Inspection and Acceptance Initials/Stamp and Date Report
No. Description Requirements ENKA TEKNİK QC. Client GECOL/ACES Co. Rep. Reference No.:
936-1 Visual and Dimensional Inspection Acc. Unit Auxiliary TR’s • Outline Drawings * W W
Technical Spec

936-2 Measurement of Voltage Ratio and Check of Vector Acc. Unit Auxiliary TR’s • IEC 60076-1 * W W
Relationship Technical Spec

936-3 Measurement of Impedance Voltage and Load Loss Acc. Unit Auxiliary TR’s • IEC 60076-1 * W W
Technical Spec

936- 4 Measurement No- Load Loss and Exciting Current Acc. Unit Auxiliary TR’s • IEC 60076-1 * W W
Technical Spec

936- 5 Short Duration AC Test (Induced Over Voltage Test) - • IEC 60076-3 * W W

936- 6 Separate Source Over Voltage Withstand Test - • IEC 60076-3 * W W

936-7 Measurement of Winding Resistance - • IEC 60076-1 * W W

936- 8 Partial Discharge Measurement - • IEC 60076-3 * W W

936- 9 Operation Tests of Off –Load Tap Changer - • IEC 60076-1 * W W

936-10 Lighting Impulse Test - • IEC 60076-4 * W W

936-11 Temperature rise test - • IEC 60076-2 * W W

Sub -contractor QC Date & Signature /Stamp No. Enka Teknik QC Date & Signature /Stamp No. Client GECOL/ACES Co. Rep. Date & Signature / Stamp No.
STANDARD INSPECTION AND TEST PLAN Document No:
47400320T97505
ITP No: 936 Date:12.02.2009
UNIT AUXILIARY TRANSFORMERS Rev.No:2
Page: 4
936-12 Pressure test - • IEC 60076 * W W

936-13 Insulation resistance test - • IEC 60076-3 * W W

936-14 Sound level test - • IEC 60076-10 * W W

936-15 TYPE TESTS • IEC 60076-1 * R R


- Short Ckt Withstand Test
- Dielectric Test
- Induced HV Test
- Zero-Sequence Impedance
- Determination of Capacitances windings-to-
earth, and between windings
- Measurement of harmonics of no-load
current
- Measurement of the power taken by the fan
and oil pump motors
- Measurement of insulation resistance to
earth of the windings, and/or measurement
of dissipation factor of the insulation system
capacitances

Note : Above mentioned tests shall be carried out by manufacturer.


Legend : S - Surveillance Inspection W - Witness Inspection Point H - Mandatory Hold Point For Inspection R - Record Review
* Report or Certificate to be provided.

Sub -contractor QC Date & Signature /Stamp No. Enka Teknik QC Date & Signature /Stamp No. Client GECOL/ACES Co. Rep. Date & Signature / Stamp No.