NATIONAL GRID

Title: Index Number:


CL-NG-6460-002-022
Check List of Neutral Earthing Resistor (NER) Commissioning Page Number:
1 of 2

1.0 Equipment General Data and Information

Substation
Bay/Panel
2.0Equipment Serial No
Check List of NER Commissioning and Testing

Item Description Done Remarks

1. Visual inspection for any insulator broken.


2. Check nameplate and data.
Check the value of resistance and current ratings against
3.
the specifications.
Checks that the earthing with solderless connectors and
suitable for termination of copper conductor of size 240
mm2 for 40 kA and below.
4.
Check the grounding resistance of the enclosure earth
terminal and resistor earth terminal. Confirm the continuity
and tightness of the Bolt & Nut.

Check the resistor rated for 5 Seconds unless specified in


5.
data schedule.

6. Test associated NCT & power cable.


Main circuits Resistance measurement test at ambient
temperature. The resistor provided in the NER panel/box
7.
shall be measured (after disconnecting the leads) and it
should match with the name plate.
8. Insulation resistance measurement test at 5kV DC

Cleaning of all internal as well as external to NER before


9.
energization.

Check that the enclosure earth terminal and resistor earth


10. terminal are separate to allow the possibility of
disconnection during testing.

Archiving System Website: http://AMAS


NATIONAL GRID

Title: Index Number:


CL-NG-6460-002-018
Checklist for Commissioning of Oil-Immersed Power Transformer Page Number:
2 of 2

Check if heater circuit is provided, it cutoff automatically,


11. when Transformer is in service and cut in automatically,
when transformer is taken out of service.

CSD Contractor T&C Contractor


Name
Sign.