CL-NG-6460-002-023 Check List of Current Transformers Commissioning Page Number: 1 of 3
1.0 Equipment General Data and Information
Substation Bay/Panel Equipment Serial No 2.0 Mechanical Checks and Visual Inspections
Item Description Done Remarks
1. Inspect for physical damage or defects. 2. Check name plate and information with drawings and specifications as specified in Data Schedule. 3. Check secondary terminals are of non-captive pan head screw type and accept copper cable of adequate size with a minimum 4 mm2. Check facility of shorting, isolating and grounding of secondary terminals inside terminal box. Check marking of primary and secondary terminals and polarity as per standard. Check the degree of protection of enclosure for secondary terminal box. 4. Check free standing CT is provided with one ground pad. 5. Check all secondary circuit wiring ferruling at the end of each wire and check it is identified indicating local device number and terminal number. 6. Check facility of changing ratio from secondary terminal blocks in panels for multi ratio CT. 7. Check that outdoor secondary wiring terminations are installed in moisture proof enclosures. 8. Check tightness of all bolted connections (torque wrench method). 9. Check secondary wiring is correctly color coded and size of wires is as specified (minimum 2.5 mm2 within panels). 10. Check proper lugs have been used on terminations according to SEC specification (ring type lugs).
3.0 Electrical Tests
Archiving System Website: http://AMAS NATIONAL GRID
Title: Index Number:
CL-NG-6460-002-023 Check List of Current Transformers Commissioning Page Number: 2 of 3
Item Description Done Remarks
1. Insulation resistance test, as following: a. Primary to ground 5kV DC for one minute. b. Primary to secondary 2.5kV DC for one minute. c. Secondary to ground and core to core 1kV DC for one minute. 2. Excitation characteristics Test 3. Winding resistance (Rct) measurement. (Ambient temperature shall be recorded; winding resistance shall be referred to 75°C). 4. Polarity test. 5. Check Turns ratio error by current primary injection. 6. Core identification test by primary injection. 7. Determination of knee point voltage (Vk) for class P, C or K. Check that (Vk) is matched with approved design. 8. Loop resistance measurement test (burden test). 9. Verify secondary circuits, terminals, and shorting/isolating links by primary injection of CTs. Installation of CT direction is as per the approved drawings and required weather proof labels are available, and check single point earth for each CT circuit. 10. High voltage test: During normal HV tests on switchgear or GIS the CTs are included in the HV test. CT secondary shall be shorted to ground and isolated from relays and meters. 11. During stability test of power transformer, test all BCT's (bushing current transformers). That means primary injection test, turns ratio, check secondary circuits related to BCT by checking short & isolate facility, measure currents at each point of all loops and compare between measured values and expected values.
CSD Contractor T&C Contractor
Name Sign.
Archiving System Website: http://AMAS
NATIONAL GRID
Title: Index Number:
CL-NG-6460-002-023 Check List of Current Transformers Commissioning Page Number: 3 of 3