Professional Documents
Culture Documents
Polytechnic
Prepared by Sanjoy Pondit, Lecturer, Department of Electrical Engineering, Ghatal Govt. Polytechnic
Unit IV: Testing & maintenance of Transformer Ghatal Govt. Polytechnic
In measuring the cold resistance for the purpose of temperature-rise determination, special
efforts shall be made to determine the average winding temperature accurately. Thus, the
difference in temperature between the top and bottom oil should be small. To obtain this result
more rapidly, the oil may be circulated by a pump.
II) Measurement of Voltage Ratio and Check of Phase Displacement
The voltage ratio shall be measured on each tapping. The polarity of single-phase transformers
and the connection symbol of three-phase transformers shall be checked.
III) Measurement of Short-Circuit Impedance and Load Loss
The short-circuit impedance and load loss for a pair of windings shall be measured at rated
frequency with approximately sinusoidal voltage applied to the terminals of one winding, with
the terminals of the other winding short-circuited, and with possible other windings open-
circuited. The supplied current should be equal to the relevant rated current (tapping current)
but shall not be less than 50 percent thereof. The measurements shall be performed quickly so
that temperature rises do not cause significant errors. The difference in temperature between
the top oil and the bottom oil shall be small enough to enable the mean temperature to be
determined accurately. If the cooling system is OF or OD, the pump may be used to mix the oil.
The measured value of load loss shall be multiplied with the square of the ratio of rated current
(tapping current) to test current. The resulting figure shall then be corrected to reference
temperature. The I2R loss (R being dc resistance) is taken as varying directly with the winding
resistance and all other losses inversely with the winding resistance.
On transformers having a tapped winding with tapping range exceeding ±5 percent, the short-
circuit impedance shall be measured on the principal tapping and the two extreme tapping.
On a three-winding transformer, measurements are performed on the three different two-
winding combinations. The results are re-calculated, allocating impedances and losses to
individual windings. Total losses for specified loading cases involving all these windings are
determined accordingly.
IV) Measurement of No-load Loss and Current
The no-load loss and the no-load current shall be measured on one of the windings at rated
frequency and at a voltage corresponding to rated voltage if the test is performed on the principal
tapping, or to the appropriate tapping voltage if the test is performed on another tapping. The
remaining winding or windings shall be left open-circuited and any windings which can be
connected in open delta shall have the delta closed.
The transformer shall be approximately at factory ambient temperature. For a three-phase
transformer the selection of the winding and the connection to the test power source shall be
made to provide, as far as possible, symmetrical and sinusoidal voltages across the three wound
limbs.
The test voltage shall be adjusted according to a voltmeter responsive to mean value of voltage
but scaled to read the r.m.s. voltage of a sinusoidal wave having the same mean value. The
reading of this voltmeter is U′.
At the same time, a voltmeter responsive to the r.m.s. value of voltage shall be connected in
parallel with the mean-value voltmeter and its indicated voltage U shall be recorded.
Prepared by Sanjoy Pondit, Lecturer, Department of Electrical Engineering, Ghatal Govt. Polytechnic
Unit IV: Testing & maintenance of Transformer Ghatal Govt. Polytechnic
When a three-phase transformer is tested, the voltages shall be measured between line
terminals, if a delta connected winding is energized, and between phase and neutral terminals if
a YN or ZN connected winding is energized.
The test voltage wave shape is satisfactory if the readings U′ and U are equal within 3 percent.
The measured no-load loss is Pm, and the corrected no load loss is taken as:
𝑃𝑜 = 𝑃𝑚 (1 + 𝑑)
𝑈 ′ −𝑈
𝑑 = 𝑈 ′ (usually negative)
If the difference between voltmeter readings is larger than 3 percent, the validity of the test is
subject to agreement.
The r.m.s. value of no-load current is measured at the same time as the loss. For a three-phase
transformer, the mean value of readings in the three phases is taken.
V) Dielectric tests
The standard dielectric requirements are verified by dielectric tests. They shall, where applicable
and not otherwise agreed upon, be performed in the sequence as given below.
Switching impulse test (SI) for the line terminal:
The test is intended to verify the switching impulse withstand strength of the line terminals and
its connected winding(s) to earth and other windings, the withstand strength between phases
and along the winding(s) under test.
The test is an essential requirement for transformers subjected to a long-duration induced
AC withstand voltage (ACLD) test.
Lightning impulse test (LI) for the line terminals:
The test is intended to verify the impulse withstand strength of the transformer under test, when
the impulse is applied to its line terminals. If the lightning impulse test includes impulses chopped
on the tail (LIC), the impulse test is modified according to clause Test with lightning impulse
chopped on the tail.
Lightning impulse test (LI) for the neutral terminal:
The test is intended to verify the impulse withstand voltage of the neutral terminal and it’s
connected winding(s) to earth and other windings, and along the winding(s) under test. This test
is required if a standard impulse withstand voltage for the neutral is specified.
Separate source AC withstand voltage test (applied potential test):
The test is intended to verify the AC withstand strength of the line and neutral terminals and their
connected windings to earth and other windings.
Short-duration induced AC withstand voltage test (ACSD):
The test is intended to verify the AC withstand strength of each line terminal and it’s connected
winding(s) to earth and other windings, the withstand strength between phases and along the
winding(s) under test. For Um > 72.5 kV, the test is normally performed with partial discharge
measurements to verify partial discharge free operation of the transformer under operating
conditions. By agreement between supplier and purchaser, the partial discharge measurements
may also be performed for Um ≤ 72.5 kV.
long-duration induced AC voltage test (ACLD):
This test is not a design proving test, but a quality control test, and is intended to cover temporary
over voltages and continuous service stress. It verifies partial discharge-free operation of the
transformer under operating conditions.
Prepared by Sanjoy Pondit, Lecturer, Department of Electrical Engineering, Ghatal Govt. Polytechnic
Unit IV: Testing & maintenance of Transformer Ghatal Govt. Polytechnic
Prepared by Sanjoy Pondit, Lecturer, Department of Electrical Engineering, Ghatal Govt. Polytechnic
Unit IV: Testing & maintenance of Transformer Ghatal Govt. Polytechnic
Prepared by Sanjoy Pondit, Lecturer, Department of Electrical Engineering, Ghatal Govt. Polytechnic
Unit IV: Testing & maintenance of Transformer Ghatal Govt. Polytechnic
In practice, the impulse shape may deviate from the standard impulse when testing low-voltage
windings of high rated power and windings of high input capacitance. The impulse test is
performed with negative polarity voltages to avoid erratic flash overs in the external insulation
and test circuit. Waveform adjustments are necessary for most test objects. Experience gained
from results of tests on similar units or eventual pre-calculation can give guidance for selecting
components for the wave shaping circuit.
The test sequence consists of one reference impulse at 75% of full amplitude followed by the
specified number of voltage applications at full amplitude (according to IEC 60076-3 three full
impulses). The equipment for voltage and current signal recording consists of digital transient
recorder, monitor, computer, plotter and printer. The recordings at the two levels can be
compared directly for failure indication. For regulating transformers one phase is tested with the
on-load tap changer set for the rated voltage and the two other phases are tested in each of the
extreme positions.
Temperature rise test of oil & winding
The standard method for determination of the steady-state temperature-rise of oil-immersed
transformers on the test floor is the equivalent test in short-circuit connection.
Alternatively it may be agreed, in special cases, to perform a test with approximately rated
voltage and current by connection to a suitable load. This is mainly applicable to transformers
with low rated power.
A ‘back-to-back’ method may also be agreed. In this method, two transformers, one of which is
the transformer under test, are connected in parallel and excited at the rated voltage of the
Prepared by Sanjoy Pondit, Lecturer, Department of Electrical Engineering, Ghatal Govt. Polytechnic
Unit IV: Testing & maintenance of Transformer Ghatal Govt. Polytechnic
transformer under test. By means of different voltage ratios or an injected voltage, rated current
is made to flow in the transformer under test.
Test to Steady State by Short-Circuit Method
During this test the transformer is not subjected to rated voltage and rated current
simultaneously, but to the calculated total losses, previously obtained by two separate
determinations of losses, namely load loss at reference temperature, and no-load loss.
The purpose of the test is twofold,
To establish the top oil temperature-rise in steady-state condition with dissipation of total
losses.
To establish the average winding temperature rise at rated current and with the top oil
temperature rise as determined above.
This is achieved in two steps:
a) Total loss injection: First the top oil and average oil temperature-rises are established when
the transformer is subjected to a test voltage such that the measured active power is equal to
the total losses of the transformer.
The test current will be above rated current to the extent necessary for producing an additional
amount of loss equal to the no-load loss, and the winding temperature rise will be
correspondingly elevated.
The oil temperature and cooling medium temperature are monitored, and the test is continued
until a steady-state oil temperature rise is established.
The test may be terminated when the rate of change of top oil temperature-rise has fallen below
1 k/h and has remained there for a period of 3 h. If discrete readings have been taken at regular
intervals, the mean value of the readings during the last hour is taken as the result of the test. If
continuous automatic recording is applied, the average value during the last hour is taken.
b) Rated current injection: When the top oil temperature rise has been established, the test shall
immediately continue with the test current reduced to rated current for the winding combination
connected. This condition is maintained for 1 h, with continuous observation of oil and cooling
medium temperatures.
Different methods of determining temp rise:
Back to back or Sumpner's test:
A load test on a transformer is necessary if its maximum temperature rise is to be determined. A
small transformer can be put on full load by means of a suitable load impedance. But for large
transformers, full load test is difficult, since it involves considerable waste of energy and a
suitable load, capable of absorbing full load power, is not easily available. However, large
transformers can be put on full load by means of Sumpner's or back to back test. The Sumpner's
test can also be used for calculating the efficiency of a transformer, though the latter can be
determined accurately from open-circuit and short circuit tests.
The back to back test on single-phase transformers requires two identical units. Fig. 1.33
illustrates the circuit for two single-phase transformers, where two primaries connected in
parallel, are energised at rated voltage and rated frequency. With secondaries open, the watt
meter W, records the core losses of both the transformers. The two secondaries are connected
in series with their polarities in phase opposition, which can be checked by means of a voltmeter.
The range of this voltmeter connected across terminals ab, should be double the rated voltage
Prepared by Sanjoy Pondit, Lecturer, Department of Electrical Engineering, Ghatal Govt. Polytechnic
Unit IV: Testing & maintenance of Transformer Ghatal Govt. Polytechnic
of either transformer secondary. Zero voltmeter reading (Vab= 0) indicates the secondaries are
connected in opposition. Now, if the terminals ab are short-circuited, the current in the
secondary would be zero because Vab=0 and the wattmeter reading W₁ remains unaltered. In
case the voltmeter reads the sum of the two secondary voltages, the secondaries are in the same
phase. In order to bring them in phase opposition, terminals ad should be joined together to
result in zero voltage across terminals bc.
Prepared by Sanjoy Pondit, Lecturer, Department of Electrical Engineering, Ghatal Govt. Polytechnic
Unit IV: Testing & maintenance of Transformer Ghatal Govt. Polytechnic
windings. Net power input to the two transformers is (2Pc +2Psc). If temperature rise of the two
transformers is to be measured, then the two transformers are kept under rated loss conditions
for several hours till maximum stable temperature is reached.
If 2Io, is the no load current, then for the assumed directions of I o, and I2, the primary current of
transformer 1 is less (difference of I1 and Io) than the primary current of transformer 2 (sum of Io,
and I1). Therefore, the two transformers do not operate under identical conditions-one may have
slightly less temperature than the other.
Open delta test:
For performing the load test on single-phase transformers, two identical units are essential,
whereas the load test on three-phase transformers can be carried out on a single unit. For this
test, the primary and secondary windings are connected in delta, whatever the actual
transformer connections may be. The low-voltage winding is excited at normal voltage and
normal frequency. The wattmeters W₁ and W₂ record the total core loss. The h.v. winding in open
delta, is connected to auxiliary single-phase supply of any convenient frequency. The voltage
injected in the open delta is adjusted till full load current flows in it. Transformer action sets up
full load current in the l.v. winding also. As before, the readings of watt meters W₁ and W₂ are
unaffected and watt meter W, records the ohmic losses in all the three phases. Note that the
magnitude of the low-injected voltage in the open delta is equal to (full load current) 3ZeH, where
ZeH is the per phase equivalent leakage impedance on h.v. side. This method of load testing may
be called dummy load test on a three-phase transformer. In Figure, upper diagram shows l.v.
winding in delta, whereas the lower diagram shows its h.v. winding in open delta.
Prepared by Sanjoy Pondit, Lecturer, Department of Electrical Engineering, Ghatal Govt. Polytechnic
Unit IV: Testing & maintenance of Transformer Ghatal Govt. Polytechnic
Prepared by Sanjoy Pondit, Lecturer, Department of Electrical Engineering, Ghatal Govt. Polytechnic
Unit IV: Testing & maintenance of Transformer Ghatal Govt. Polytechnic
Prepared by Sanjoy Pondit, Lecturer, Department of Electrical Engineering, Ghatal Govt. Polytechnic
Unit IV: Testing & maintenance of Transformer Ghatal Govt. Polytechnic
(f) Yearly Maintenance: Following things should be observed and carried out in yearly
maintenance:
(i) Check foundation for cracking and settling. A slight shift of the transformers may break
bushings or connecting oil or water lines. See that rail stops are firmly in place to hold transformer
in position on the rail. Check transfer car and matching of its rails with transformer deck rails at
each positions, weld metal work as needed.
(ii) Clean dirt and oil from radiating surfaces. Repaint as necessary stop excessive vibration of
radiator tubes, tighten loose or vibrating parts. Check for unusual internal noises Inspect oil and
water piping valves, and plugs. Manipulate radiator cut-off valves to see that they are in
operating condition and secure in the open position see that all oil drain valves which can be
operated without wrenches are plugged or locked to prevent unauthorized opening.
(iii) See that relief diaphragm is in operating condition and closes tightly. The non-shattering type
diaphragm should be actuated to see that it is not stuck shut from rust or paint. Make that
material used in shattering-type diaphragm is not too thick or tough to be broken by reasonable
internal pressure. See that screens and baffles in the vents or breathers are not obstructed or
broken. If breathers are of dehydrating type, check chemicals and replace it, if depleted.
(iv) Clean dirty gauge glasses and connections. Check oil level indicators and relays for proper
operation. Replenish oil if below normal. Drain out and replace bushing oil if dirty or discoloured.
(v) Check external supply and drain piping for leaks. Flush out cooling coils of heat exchanger
water passages with air and water.
Test coils for leaks by applying air pressure to coils and absorbing for bubbles rising in oil and
drop in air pressure with supply valve closed, or use a hydrostatic pressure test. A pressure of
about 75 pounds per square inch is recommended. If water scale is present, circulate a solution
of 25 per cent hydrochloric acid and water through the coils until clean. The flush out thoroughly.
Clean external surfaces of coils.
(vi) Check water flow indicators and relays for proper operation.
(vii) Clean and test water tubes similar to cooling coil, check for oil and water leaks.
(viii) Check motors and control.
(ix) Check calibration of temperature indicators and relays, check and clean relay contacts and
operating mechanism.
(x) Check setting and operation of regulator and relay, see that gauges are indicating properly.
(xi) Check for gas leaks dry applying liquid soap on all joints valves, connections etc., with gas
pressures raised to the maximum recommended by the transformers manufacture.
(xii) Clean porcelain with water, chloroethylene, or other suitable cleaner. Repair chipped spots
by painting with lacquer such as red glyptal. Inspect gaskets for leaks tighten bolts, check power
factor, check oil sample from bottom of bushing for dielectric strength and presence of water
which may be entering at top. Replace or replenish oil, if necessary.
(xiii) Check top settings and adjustment at terminal board to see that they agree with diaphragms.
Check insulation resistance of wiring with devices connected. Check ratio and phase-angle
adjustments of potential devices if changes have been made in secondary connections and
burden. Tighten connections, including potential device top, into bushing.
Prepared by Sanjoy Pondit, Lecturer, Department of Electrical Engineering, Ghatal Govt. Polytechnic
Unit IV: Testing & maintenance of Transformer Ghatal Govt. Polytechnic
(xvi) Tighten all bus and ground connections. Refinish joint contact surfaces if they have been
overheating. Inspect ground cable to see that it is not loose or broken.
(xv) Lower the oil level to atleast the top of the core. Inspect for saludge on core and windings.
Inspect under side of cover for moisture and rust and clean up. Check connections at terminal
board, tighten all bolted connections, core bolts, etc., within reach.
(xvi) Inspect contacts and clean if reachable on internal inspection. If not reachable for visual
inspection, check each position with wheatstone bridge across winding to detect poor contact.
Work adjusted back and forth over complete range several times.
(xvii) Check contact pressure. Check contact operating mechanism. Tighton connections and
other bolts.
(xviii) Chcck condition of contacts and refinish of burned or corroded.
(xix) Check contact springs, operating rods and levers, chock closing and operating positions with
respect to position of main contacts.
(xx) Inspect fuses or circuit breakers on all power, control and alarm supplies to auxiliary
equipment and devices.
(xxi) Check the insulation resistance between each winding and between each winding and
ground.
(xxii) Check the dielectric strength of insulating oil in the main and auxiliary tanks and oil filled
bushings.
(xxiii) Check earth resistance.
(xxiv) Check lighting arrestors.
(xxv) Check for ceiling arrangement for fitting.
(xxvi) Run tap changer or regulator through several complete cycles by both control relay and
manual control and observe contacts and mechanism for proper operation.
(g) Two-yearly Maintenance: Two-yearly Maintenance includes:
(i) Internal inspection of the core.
(ii) Filter oil and fill filtered oil in the tank and conservator of the oil.
(iii) Checks mentioned in yearly maintenance.
(h) Five-yearly Maintenance: Five-yearly maintenance includes:
(i) Carry out overall inspection of the transformer including tighting of core and coils as
mentioned earlier in yearly maintenance.
(ii) Clean the transformer with dry transformer oil.
(iii) Open tank for cleaning and reassembling.
(i) Unscheduled Maintenance: Unscheduled maintenance is the type of maintenance which is
not schedule as per instructions mentioned in the manual by company. It includes:
(i) If the transformer has been properly maintained and not overheated and barring internal
failure, it should not require untanking within the normal life. If sludge has been allowed to from
due to overheating and oxidation of the oil, transformer should be untanked and the core, coils
Prepared by Sanjoy Pondit, Lecturer, Department of Electrical Engineering, Ghatal Govt. Polytechnic
Unit IV: Testing & maintenance of Transformer Ghatal Govt. Polytechnic
oil passages, tank and water cooling coils are washed down with clean oil under pressure to
remove sludge and other accumulations which prevent proper circulation of the oil. Inflammable
liquids should not be used in cleaning the core, coils or inside of tank. While untanked, check for
loose laminations, core bolts insulating blocks etc. and other pertinent features on the check list,
(ii) The necessity for filtering and/or reclaiming the insulating oil will depend on the results
obtained from the oil dielectric and oil acidity tests. It may be more economical to replace the oil
in small transformers rather than filters and reclaim it.
The acidity of the insulating oil in the main tank should be checked at intervals of not more than
five years. Transformers operating at high temperature or showing signs of sludging or dark
colour of the oil should be checked more frequently. Oil may be checked in the field with a
dielectric test kit or samples sent to laboratory.
Major substations having transformer rated 1 MVA and above are usually attended at all times
such installations can have hourly, weekly, monthly inspection.
Medium size transformers, between 0.6 MVA and 1 MVA are used in smaller substations. They
can also have daily, weekly and monthly inspection.
Small transformers below 500 kVA are often installed in unattended sub-stations. Such
transformers can have quarterly maintenance.
Prepared by Sanjoy Pondit, Lecturer, Department of Electrical Engineering, Ghatal Govt. Polytechnic