Substation
Bay/Panel
Equipment Serial No
Wiring:
a) Check all control and instruments cables are properly
shielded, and the cable shield is grounded at the LCC only.
b) Check that all wiring is heat resistant and flame retardant,
with maximum temperature of 90C° and rated 600/1000V,
stranded annealed copper conductor.
c) Check color coding of control cabinet wiring.
d) Check that all circuit wiring terminations are identified by a
permanent marking at each termination with a non-
adhesive ferrule or plastic sleeve marker in accordance with
schematic drawing.
e) Check AC circuit terminals and DC circuit terminals are
fitted with non-inflammable transparent plastic covers, to
10. prevent accidental contact with live parts.
f) Check that all phases are marked, and circuit labelling has
been installed as per specifications.
g) Check that 10% spare terminals from each type are
provided.
h) Check the cable tag at GIS side and LCC side.
i) Check that the wiring between devices and terminal blocks
is carried in troughs or in neatly formed packs, which shall
be tied or otherwise secured at frequent intervals to prevent
undue stress on equipment or connection. Check
connections across portions, which are hinged or otherwise
movable, are made with flexible wires formed to distribute
the bending stress. Check no wires are teed or jointed
between terminal points.
Ensure that all disconnect switches are provided with viewing
windows or mechanical indicators for verification of contact
11.
positions and that all grounding switch positions can be visually
verified from ground level.
Check and confirm the three-phase test adaptor and bushing
12. for HV test on GIS have been provided. (as per Scope Of
Work).
Check and confirm there are no any sharp edges for the cable
13.
trays or other metallic parts.
Check the labelling and phasing marking on the cable head
14.
compartments.
Grounding:
a) Check all grounding points are connected as per the
approved detailed design.
15.
b) Check that all auxiliary equipment such as mechanism
boxes and control cabinets are provided with separate
grounding connector.
NATIONAL GRID SA
NG-6460-002-027.
Test all Meters and attach all their test forms and checklists
5. (CL-NG-6460-002-103 to 109 if applicable) with GIS checklist
CL-NG-6460-002-027.
Test Annunciator and attach its test form and checklist CL-
6.
NG-6460-002-080 with GIS checklist CL-NG-6460-002-027.
Test Circuit Breaker and attach the test results and checklist
7. of circuit breaker CL-NG-6460-002-032 with GIS checklist CL-
NG-6460-002-027.
Disconnect Switches and Grounding Switches:
a) Perform 10kV HV test for all ES insulators.
8.
b) Attach the test results and checklist CL-NG-6460-002-034
with GIS checklist CL-NG-6460-002-027.
Current Transformers:
a) Witness Current Transformers tests as per WI-NG-6460-
9. 002-023.
b) Attach the test results and checklist CL-NG-6460-002-023
with GIS checklist CL-NG-6460-002-027.
Voltage Transformers:
a) Witness voltage transformers tests as per WI-NG-6460-
10. 002-024.
b) Attach the test results and checklist CL-NG-6460-002-024
with GIS checklist CL-NG-6460-002-027.
11. Perform contact resistance test as per factory conditions.
Perform scheme and function test and attach the test results
12. and checklist CL-NG-6460-002-084 with GIS checklist CL-
NG-6460-002-027.
Interlocking:
a) Check that the interlocking conditions table is approved
and review before checking interlocking scheme and
operation.
b) Ensure that the manual operation of disconnect and
grounding switches is only possible under electrical
interlocking release conditions.
c) Ensure that the electrical interlock schemes are fail-safe
13. to prevent loss of interlock function upon loss of control
voltage.
d) Check the availability of mechanical interlocking between
disconnect and grounding switch.
e) Check electrical interlocking between line VT and
respective line grounding / earthing switch through under
voltage relay. (as per design).
f) Check all interlocking circuits in schematic drawings of
equipment.
NATIONAL GRID SA