FOR APPROVAL

PROJECT: 220MWac SAMARKAND Solar PV Plant in Uzbekistan

Project Company
(PC)

Project Management
Company
(PMC)

EPC Contractor
(EPC)

Sub-contractor

01 21 Aug 2023 First issue Khamroyev B Zheng Hongyun Yousef Al Khatib

REV DATE DESCRIPTION DONE CHECKED APPROVED

EPC DOCUMENT NUMBER DOCUMENT NAME

SKD-DEC-QAC-ITP- 054 Inspection and Test Plan (ITP) of Cable Installation


and Termination work
OWNER DOCUMENT NUMBER DOCUMENT OWNER REVISION
EPC Contractor
SKD-DEC-QAC-ITP 054 Rev.: 01

1
SKD-DEC-QAC-ITP-054
Test Plan (ITP) of Cable
Installation and
Termination work

Inspection and Test Plan of


Cable Installation and
Termination work
DONGFANG ELECTRIC INTERNATIONAL CORPORATION

Nur SAMARKAND 220MWac Solar PV Plant in Uzbekistan

2
SKD-DEC-QAC-ITP-054
Test Plan (ITP) of Cable
Installation and
Termination work

TABLE OF CONTENTS
SCOPE………………………………………………………………………………………………….....4
INSPECTION CATEGORIES……………………………………………………………………………………...4
NOTICE OF ISPECTION……………………………………………………………………………………..……4
REFERENCE DOCMENT…………………………………………………………………………………...….….4
ISPECTION AND TEST PLAN(ITP)…………………….………………………………………………………...5
ATTACHMENTS……………………………………………………………………………………………...……..5
Attachment #1 – SKD-ITP-054-001- Excavation of Cable trench with bedding……………………...9
Attachment #2 – SKD-ITP-054-002- Cable drum insulation resistance test report (IR Test )………10
Attachment #3 – SKD-ITP-054-003A- Cable Laying check list…………………………………….…11
Attachment #4 – SKD-ITP-054-003B- Cable laying Inspection report……………………………….12
Attachment #5 – SKD-ITP-054-004A- Insulation resistance test report for LV and MV cable……..13
Attachment #6 – SKD-ITP-054-004B- IR Test Report for Control and Signal cable…………...……14
Attachment #7 – SKD-ITP-054-005- Backfilling of Cable trench…………………………………...…15
Attachment #8 – SKD-ITP-054-006A-Cable Termination Checklist…………………………………..16
Attachment #9 – SKD-ITP-054-006B-Cable termination Inspection report…………………………..17
Attachment #10 – SKD-ITP-054-007-Cable splicing Checklist…………………………………………18
Attachment #11 – SKD-ITP-054-008-Fiber optic cable OTDR test report………………………...…..19
Attachment #12 – SKD-ITP-054-009-Fiber optic cable Termination Checklist………………………20

3
SKD-DEC-QAC-ITP-054
Test Plan (ITP) of Cable
Installation and
Termination work

1. SCOPE
This Inspection and Test Plan (ITP) covers the inspection and test requirements for the Cable pulling
& termination work for 220MWac SAMARKAND Solar PV Plant in Uzbekistan.
2. INSPECTION CATEGORIES
The following inspection categories shall be used to identify the extent of inspection for each
inspection activity within the ITP.
Hold Point (H)
A point which Owner and/or Contractor’s inspector shall inspect and clear the activity as per the
approved Inspection and Test Plan (ITP). Otherwise no further activity shall proceed without prior
permission by Owner.
Witness Point (W)
Witness, checking, examination and/or inspection points as appropriate.
A point at which Owner and/or Contractor’s inspector shall attend or witness the activity as per the
approved Inspection and Test Plan (ITP). After formal notification work can proceed if Owner and/or
Contractor’s inspector is not available to attend or to witness the activity on the date notified.

Spot Witness Point (SW)


A witness point at which spot inspection or spot examination is required in accordance with the
approved Inspection and Test Plan (ITP). Work may proceed through the designated spot witness point if
the inspector is not present for the continuously implemented activity. No formal notification is required
except the very first commencement of related activity.

Review Point (R)


A point at which Owner and/or Contractor’s inspector shall review the relevant documents as per the
approved Inspection and Test Plan (ITP).

Monitoring Point (M)


A point at which Owner and/or Contractor’s inspector will visit any work to inspect the ctivity during
processing as per the approved Inspection and Test Plan (ITP).
Surveillance activity, the act of monitoring or observing the status of work and materials and
analyses of records to verify whether an item or activity conforms to specified requirements may be
performed at the monitoring point.

3. NOTICE OF INSPECTION
The Contractor shall submit to Owner a notice of inspection request one (1) day before the inspection
to be carried out. The request shall contain information as follows:
Inspection item(s);
Responsibility Category (Subcontractor, Discipline);
Date, place and time of inspection;
Any other relevant information.
Look ahead schedule of inspection and test for 2 weeks will be provided to Owner as an advance
information base on the projected construction schedule. The schedule will be prepared weekly and submit
to Owner for information. Refer to attachment

4
SKD-DEC-QAC-ITP-054
Test Plan (ITP) of Cable
Installation and
Termination work

4. REFERENCE DOCUMENT
4.1 Reference Specifications and procedures
1. Inspection For Requirement
2. Material Approved Requirements

4.2 Reference Report form

1. SKD-DEC-PV-ELE-DRA-0303-04 –GENERAL OF ELECTRICAL PART IN PV FIELD


2. SKD-DEC-SS-ELE-DRA-0016 –PLAN AND BOM OF CABLE STRUCTURE SYSTEM FOR
SWITCHYARD.
3. SKD-DEC-SS-ELE-REP-0001 –LOGBOOK FOR POWER CABLES.
4. SKD-DEC-SS-ELE-DRA-0015 – PLAN AND BOM OF CABLE STRUCTURE SYSTEM FOR
SWITCHYARD.
5. SKD-DEC-PV-ELE-DRA-0302-02 –GENERAL OF ELECTRICAL PART IN PV FIELD, THE
35kV CABLE LAYING ROUTE DRAWING.
6. SKD-DEC-PV-ELE-DRA-0302-01 –GENERAL OF ELECTRICAL PART IN PV FIELD, THE
DETAILS DRAWING OF CABLE MARKING PILE IN PV FIELD.
7. SKD-DEC-PV-ELE-DRA-0307-02 –GENERAL OF ELECTRICAL PART IN PV FIELD, THE
DETAILS DRAWING OF CABLE JOINT WELL.
8. SKD-DEC-PV-ELE-DRA-0308-01 –GENERAL OF ELECTRICAL PART IN PV FIELD, THE
DETAILS DRAWING OF FIRE BLOCKING IN PV FIELD.
9. IEC-60840

5. INSPECTION AND TEST PLAN(ITP)


1. Refer to page 6-8.

6. ATTACHMENTS

Attachment #1 – SKD-ITP-054-001- Excavation of Cable trench with bedding


Attachment #2 – SKD-ITP-054-002- Cable drum insulation resistance test report (IR Test )
Attachment #3 – SKD-ITP-054-003A- Cable Laying check list
Attachment #4 – SKD-ITP-054-003B- Cable laying Inspection report
Attachment #5 – SKD-ITP-054-004A- Insulation resistance test report for LV and MV cable
Attachment #6 – SKD-ITP-054-004B- IR Test Report for Control and Signal cable
Attachment #7 – SKD-ITP-054-005- Backfilling of Cable trench.
Attachment #8 – SKD-ITP-054-006A-Cable Termination Checklist
Attachment #9 – SKD-ITP-054-006B-Cable termination Inspection report
Attachment #10 – SKD-ITP-054-007-Cable splicing Checklist
Attachment #11 – SKD-ITP-054-008-Fiber optic cable OTDR test report
Attachment #12 – SKD-ITP-054-009-Fiber optic cable Termination Checklist

5
SKD-DEC-QAC-ITP-054

Test Plan (ITP) For Cable pulling & Termination work

Inspection Verifying Inspection, Test Points


Responsible Person
S/N Description of Activity Reference Document and Test Acceptance Criteria and Control SUBCON DEC PMC Remark
Requirements Data, Forms
A Prior to Start Activity
Authority Approved As per Project Approval from the
Approved
A.1 Drawings Available on Project Manager Approved Drawings Specified PMCs Engineer DT DA DR
Requirements Drawings
Site
Check Availability of Construction Technical As per Project Compliance with
Approved
A.2 Foundation steel Works Manager Specification, Shop Specified Project Specified DT DA DR
Drawing Requirements Requirements Submittal
A.3 Check Availability Inspection Construction As per Project Compliance with
Technical Approved
& Testing Plan for Cable Manager QA/QC Specified Project Specified DT DA DR
Specification Submittal
Pulling &Termination Work Engineer Requirements Requirements
A.4 Availability of Risk As per Project Compliance with HSE
Assessment for MSRA for CM, HSE Officer Specified Requirements Approved
Project HSE Plan DT DA DR
Cable Pulling &Termination Requirements Submittal
Work
B Preparation Works
Back-filling soil sampling Surveyor, CM, Civil Check approved Verify Setting Compliance with Report
and Rolling test Engineer inspection report out as Shown in Drawings and Project
B.1 the Drawing Specified Requirements H W DR

Lean concrete cushion Construction Check approved As per Project Compliance with
Approved
B.2 Manager, QA/QC inspection report Specified Drawings and Project DT DR DR
Engineer Requirements Specified Requirements Submittal
Compliance with
Material Inspection has CM, Civil Engineer, Physical
B.3 QMP Drawings and Project Report W W H
been done and approved QA/QC Engineer Inspection
Specified Requirements
C During Cable Pulling and Termination work

Compliance with Refer to form:


Excavation of Cable Surveyor, CM, Approved Drawings, Physical SKD-ITP-054-
C.1 Drawings and Project H H H
trench with bedding QA/QC Engineer Method Statement Inspection Report 001
Specified Requirements
Cable drum insulation Refer to form:
resistance test report Compliance with
QA/QC Engineer, Physical SKD-ITP-054-
C.2 Approved Drawings Drawings and Project Report H H H
(IR Test) Electrical Manager Inspection 002
Specified Requirements
C.3 Cable Laying check list QA/QC Engineer, Approved Material, Physical Compliance with Report H H W Refer to form:
Electrical Manager as per drawing Inspection Drawings and Project SKD-ITP-054-

6
SKD-DEC-QAC-ITP-054

Test Plan (ITP) For Cable pulling & Termination work

, Method Statement Specific Requirements 003A


QA/QC Engineer, Approved Material, Compliance with Refer to form:
C.4 Cable laying Inspection Physical
Electrical Manager as per drawing Drawings and Project Report H H W SKD-ITP-054-
report Inspection 003B
, Method Statement Specified Requirements
IR Test Report for LV and Approved Material, Compliance with Refer to form:
QA/QC Engineer, Physical
C.5 as per drawing Drawings and Project Report H H W SKD-ITP-054-
Medium cable Electrical Manager Inspection 004A
, Method Statement Specified Requirements
Approved Material, Compliance with Refer to form:
IR Test Report for Control QA/QC Engineer, Physical
C.6 as per drawing Drawings and Project Report H H W SKD-ITP-054-
and Signal cable Electrical Manager Inspection 004B
, Method Statement Specified Requirements
Construction Compliance with Refer to form:
Backfilling of Cable Approved Drawings, Physical
C.7 Manager, QA/QC Drawings and Project H H H SKD-ITP-054-
trench Method Statement Inspection Report 005
Engineer Specified Requirements
Approved Material, Compliance with Refer to form:
C.8 Cable Termination QA/QC Engineer, Physical
as per drawing Drawings and Project Report H H DR SKD-ITP-054-
Checklist Electrical Manager Inspection 006A
, Method Statement Specified Requirements
Approved Material, Compliance with Refer to form:
Cable termination QA/QC Engineer, Physical
C.9 as per drawing Drawings and Project Report H H H SKD-ITP-054-
Inspection report Electrical Manager Inspection 006B
, Method Statement Specified Requirements
Approved Material, Compliance with Refer to form:
C.10 QA/QC Engineer, Physical
Cable splicing Checklist as per drawing Drawings and Project Report H H H SKD-ITP-054-
Electrical Manager Inspection 007
, Method Statement Specified Requirements
Fiber optic cable OTDR Approved Material, Compliance with Refer to form:
QA/QC Engineer,
C.11 as per drawing Test report Drawings and Project Report H H H SKD-ITP-054-
test report Electrical Manager 008
, Method Statement Specified Requirements
Fiber optic cable Approved Material, Compliance with Refer to form:
QA/QC Engineer, Physical
C.12 as per drawing Drawings and Project Report H H H SKD-ITP-054-
Termination Checklist Electrical Manager Inspection 009
, Method Statement Specified Requirements

7
SKD-DEC-QAC-ITP-054
Test Plan (ITP) For Cable pulling &
Termination work

Legend: DEC= Dongfang Electric international Corporation DA= Document Approval H= Hold Point- RFI Required; Signature Required to Proceed

PMC = Project management company DR= Document Review W= Witness Point- RFI Not Required, Witnessing Required
Subcon. = Sub Contractor DT= Document Transmittal

Sign by PC/PMC: Sign by EPC Contractor: Sign by Subcontractor:

Name: Name: Name:

Position: Position: Position:

:Signature Signature: Signature:

8
SKD-DEC-QAC-ITP-054
Test Plan (ITP) For Cable pulling &
Termination work

INSPECTION REPORT No: SKD-ITP-054-001


Date:
Sub-Contractor: ZECCA Start Time:
Work Title: Cable pulling and Termination work Finish Time:
Inspected work: Excavation of Cable trench with bedding
Structure/Location: PV area, Block 05
Basic documents for acceptance:
1.Approved drawings: SKD-DEC-PV-ELE-DRA-0303 Section drawing of cable trench in PV field
2.Method statement and risk assessment: SKD-DEC-QAC-INP-046
3.Inspection and test plan: SKD-DEC-QAC-ITP-054
3.Measurement and test report, as attached (if any):
4.Request for inspection:
5.Other relative documents (if any):

Method of Inspection
□Visual □Laboratory test □Measurement □Survey □Others
Assessment
NO Inspection content
Subcontractor EPC Remarks
The length and width of the cable trench are
1.
suitable according to the drawing
2. Inspection for Excavation for the cable trench

3. Ground surface check, no solid and sharp things

Check the thickness of the sand inside the trench


4.
available to the drawing

5. Trench is ready for cable pulling

Note:
Conclusion: Accepted the above inspected work and agreed to carry out the next civil works. □ yes □ No
Sub-contractor EPC Contractor PC / PMC
HI-TECH CC5 DEC Masdar / Gopa JURU
Name
Signature
Date

9
SKD-DEC-QAC-ITP-054
Test Plan (ITP) For Cable pulling &
Termination work

INSPECTION REPORT No: SKD-ITP-054-002


Date:
Sub-Contractor: ZECCA&CC5 Start Time:
Work Title: Cable pulling and Termination work Finish Time:
Inspected work: Cable drum insulation resistance test report (IR Test )
Structure/Location: Substation area, Building: From Control building to Unit -01 .
Basic documents for acceptance:
1.Approved drawings: SKD-DEC-SS-ELE-DRA
2.Method statement and risk assessment: SKD-DEC-QAC1-INP-046
3.Inspection and test plan: SKD-DEC-QAC-ITP-054
3.Measurement and test report, as attached (if any):
4.Request for inspection:
5.Other relative documents (if any):
Method of Inspection
□Visual □Laboratory test □Measurement □Survey □Others

Insulation resistance (Mega-ohm) Remarks


NO. Cable Drum No. Phase to Phase to Duration Continuity
Phase Earth time test
1

Note:

Conclusion: Accepted the above inspected work and agreed to carry out the next works. □ yes □ No
Sub-contractor EPC Contractor PC / PMC
ZECCA DEC Masdar / Gopa JURU
Position

Signature

Full Name

10
SKD-DEC-QAC-ITP-054
Test Plan (ITP) For Cable pulling &
Termination work

INSPECTION REPORT No: SKD-ITP-054-003A


Date:
Sub-Contractor: ZECCA&CC5 Start Time:
Work Title: Cable pulling and Termination work Finish Time:
Inspected work: Cable Laying check list
Structure/Location: Substation area, Building: From Control building to Unit -01 .
Basic documents for acceptance:
1.Approved drawings: SKD-DEC-SS-ELE-DRA
2.Method statement and risk assessment: SKD-DEC-QAC1-INP-046
3.Inspection and test plan: SKD-DEC-QAC-ITP-054
3.Measurement and test report, as attached (if any):
4.Request for inspection:
5.Other relative documents (if any):

Method of Inspection
□Visual □Laboratory test □Measurement □Survey □Others
Assessment
NO. Inspection content
Subcontractor EPC Remarks
1. Check cable type and size
2. Check cable dressing and fixing
3. Check cable Idenfication tag
4. Check no jacket damage and twist
5. Check cable route and schedule
Check civil inspection report for backfilling soft
7.
sand (Thickness) if required
8. Check that the tape is installed
Check cable tray dressing and cable ties or clamps
9.
as per the cable size.

Note:
Conclusion: Accepted the above inspected work and agreed to carry out the next civil works. □ yes □ No
Sub-contractor EPC Contractor PC / PMC
ZECCA DEC Masdar / Gopa JURU
Position
Signature
Full Name

INSPECTION REPORT No: SKD-ITP-054-003B


Date:
Sub-Contractor: ZECCA&CC5 Start Time:
Work Title: Cable pulling and Termination work Finish Time:

11
SKD-DEC-QAC-ITP-054
Test Plan (ITP) For Cable pulling &
Termination work

Inspected work: Cable laying Inspection report


Structure/Location: Substation area, Building: From Control building to Unit -01 .
Basic documents for acceptance:
1.Approved drawings: SKD-DEC-SS-ELE-DRA
2.Method statement and risk assessment: SKD-DEC-QAC-INP-046
3.Inspection and test plan: SKD-DEC-QAC-ITP-054
3.Measurement and test report, as attached (if any):
4.Request for inspection:
5.Other relative documents (if any):

Method of Inspection
□Visual □Laboratory test □Measurement □Survey □Others
Cable Route
NO. Cable No. Type Size Remarks
From To
1.
2.
3.
4.
5.
6.
7.
Comments from Subcontractor:
Comments from EPC:
Comments from PC/PMC:
Conclusion: Accepted the above inspected work and agreed to carry out the next civil works. □ yes □ No
Sub-contractor EPC Contractor PC / PMC
ZECCA DEC Masdar / Gopa JURU
Position
Signature
Full Name

INSPECTION REPORT No: SKD-ITP-054-004A


Date:
Sub-Contractor: ZECCA&CC5 Start Time:
Work Title Cable pulling and Termination work Finish Time:
Inspected work: INSULATION RESISTANCE TEST REPORT FOR LV AND MV CABLE
Structure/Location: Substation area, Building: From Control building to Unit -01 .

12
SKD-DEC-QAC-ITP-054
Test Plan (ITP) For Cable pulling &
Termination work

Basic documents for acceptance:


1.Approved drawings: SKD-DEC-SS-ELE-DRA-
2.Method statement and risk assessment: SKD-DEC-QAC-INP-046
3.Inspection and test plan: SKD-DEC-QAC-ITP-054
3.Measurement and test report, as attached (if any):
4.Request for inspection:
5.Other relative documents (if any):

Method of Inspection
□Visual □Laboratory test □Measurement □Survey □Others
Insulation Resistance ( Ohms )
NO. Cable No. Continuity Remarks
L1 to L2 L2 to L3 L3 to L1 L1/L2/L3 to E

1
2
3
4
5
6
7

Note :
Conclusion: Accepted the above inspected work and agreed to carry out the next civil works. □ yes □ No
Sub-contractor EPC Contractor PC / PMC
ZECCA DEC Masdar / Gopa JURU
Position
Signature
Full Name

INSPECTION REPORT No: SKD-ITP-054-004B


Date:
Sub-Contractor: ZECCA&CC5 Start Time:
Work Title Cable pulling and Termination work Finish Time:
Inspected work: IR Test Report for Control and Signal cable
Structure/Location: Substation area, Building: From Control building to Unit -01 .

13
SKD-DEC-QAC-ITP-054
Test Plan (ITP) For Cable pulling &
Termination work

Basic documents for acceptance:


1.Approved drawings: SKD-DEC-SS-ELE-DRA-
2.Method statement and risk assessment: SKD-DEC-QAC-INP-046
3.Inspection and test plan: SKD-DEC-QAC-ITP-054
3.Measurement and test report, as attached (if any):
4.Request for inspection:
5.Other relative documents (if any):

Method of Inspection
□Visual □Laboratory test □Measurement □Survey □Others
Insulation Resistance ( Ohms )
NO. Cable No. Continuity Core to Core to Remarks
Core to Earthing
Core Shield
1.
2.
3.
4.
5.
6.
7.

Note:
Conclusion: Accepted the above inspected work and agreed to carry out the next civil works. □ yes □ No
Sub-contractor EPC Contractor PC / PMC
ZECCA DEC Masdar / Gopa JURU
Position
Signature
Full Name

INSPECTION REPORT No: SKD-ITP-054-005


Date:
Sub-Contractor: ZECCA Start Time:
Work Title: Cable pulling and Termination work Finish Time:
Inspected work: Backfilling of Cable trench.
Structure/Location: PV area, Block 05

14
SKD-DEC-QAC-ITP-054
Test Plan (ITP) For Cable pulling &
Termination work

Basic documents for acceptance:


1.Approved drawings: SKD-DEC-PV-ELE-DRA-0303-06 Section drawing of cable trench in PV field
2.Method statement and risk assessment: SKD-DEC-QAC-INP-046
3.Inspection and test plan: SKD-DEC-QAC-ITP-054
3.Measurement and test report, as attached (if any):
4.Request for inspection: SKD-DEC-PMC-CC-ELE-RFI-00-0001
5.Other relative documents (if any):

Method of Inspection
□Visual □Laboratory test □Measurement □Survey □Others
NO Assessment
Inspection content
. Subcontractor EPC Remarks
Have Warning tape/ covers been provide for
1.
services lines etc
2. Are underground services suitably protected

3. Level as per drawing

Check that the materials are in accordance with the


4.
approval material submit

5. Check work completed backfilling

Note:
Conclusion: Accepted the above inspected work and agreed to carry out the next civil works. □ yes □ No
Sub-contractor EPC Contractor PC / PMC
HI-TECH CC5 DEC Masdar / Gopa JURU
Name
Signature
Date

INSPECTION REPORT No: SKD-ITP-054-006A


Date:
Sub-Contractor: ZECCA&CC5 Start Time:
Work Title: Cable pulling and Termination work Finish Time:
Inspected work: Cable Termination Checklist
Structure/Location: Substation area, Building: From Control building to Unit -01 .

15
SKD-DEC-QAC-ITP-054
Test Plan (ITP) For Cable pulling &
Termination work

Basic documents for acceptance:


1.Approved drawings: SKD-DEC-SS-ELE-DRA-
2.Method statement and risk assessment: SKD-DEC-QAC-INP-046
3.Inspection and test plan: SKD-DEC-QAC-ITP-054
3.Measurement and test report, as attached (if any):
4.Request for inspection:
5.Other relative documents (if any):

Method of Inspection
□Visual □Laboratory test □Measurement □Survey □Others
Assessment
NO. Inspection content
Subcontractor EPC Remarks
1. Check terminal lug is the correct type and size
2. Confirm correct supported without steer
3. Check installation of cable gland and earthing
4. Check permanent identification tag is correct
5. Check cable length is adequate and bending radius
6. Check installation of kick plate if required
7. Cable Termination and connection
Check gland plate material to be checked and
8.
future space.
Comments from Subcontractor:
Comments from EPC:
Comments from PC/PMC:
Conclusion: Accepted the above inspected work and agreed to carry out the next civil works. □ yes □ No
Sub-contractor EPC Contractor PC / PMC
ZECCA DEC Masdar / Gopa JURU
Position
Signature
Full Name

INSPECTION REPORT No: SKD-ITP-054-006B


Date:
Sub-Contractor: ZECCA&CC5 Start Time:
Work Title Cable pulling and Termination work Finish Time:
Inspected work: Cable termination Inspection report
Structure/Location: Substation area, Building: From Control building to Unit -01 .

16
SKD-DEC-QAC-ITP-054
Test Plan (ITP) For Cable pulling &
Termination work

Basic documents for acceptance:


1.Approved drawings: SKD-DEC-SS-ELE-DRA-
2.Method statement and risk assessment: SKD-DEC-QAC-INP-046
3.Inspection and test plan: SKD-DEC-QAC-ITP-054
3.Measurement and test report, as attached (if any):
4.Request for inspection:
5.Other relative documents (if any):

Method of Inspection
□Visual □Laboratory test □Measurement □Survey □Others
Insulation Resistance ( Ohms )
NO. Cable No. Remarks
Type Size From To

1.
2.
3.
4.
5.
6.

Note:
Conclusion: Accepted the above inspected work and agreed to carry out the next civil works. □ yes □ No
Sub-contractor EPC Contractor PC / PMC
ZECCA DEC Masdar / Gopa JURU
Position
Signature
Full Name

INSPECTION REPORT No: SKD-ITP-054-007


Date:
Sub-Contractor: ZECCA&CC5 Start Time:
Work Title: Cable pulling and Termination work Finish Time:
Inspected work: Cable splicing Checklist
Structure/Location: Substation area, Building: From Control building to Unit -01 .

17
SKD-DEC-QAC-ITP-054
Test Plan (ITP) For Cable pulling &
Termination work

Basic documents for acceptance:


1.Approved drawings: SKD-DEC-SS-ELE-DRA-
2.Method statement and risk assessment: SKD-DEC-QAC-INP-046
3.Inspection and test plan: SKD-DEC-QAC-ITP-054
3.Measurement and test report, as attached (if any):
4.Request for inspection:
5.Other relative documents (if any):

Method of Inspection
□Visual □Laboratory test □Measurement □Survey □Others
Assessment
NO. Inspection content
Subcontractor EPC Remarks
1. Both cables (tags)for splice for correct
2. All conductor checked for the correct phases
3. Check crimping done properly
4. All part are clean and degreased before tubing
5. Installation above splice is correct
6. Weather proof tubing provided properly
7. Cable splicing completed satisfactory
Check if splicing kit is approved type and suitable
8.
for the location.

Note:
Conclusion: Accepted the above inspected work and agreed to carry out the next civil works. □ yes □ No
Sub-contractor EPC Contractor PC / PMC
ZECCA DEC Masdar / Gopa JURU
Position
Signature
Full Name

INSPECTION REPORT No: SKD-ITP-054-008


Date:
Sub-Contractor: ZECCA&CC5 Start Time:
Work Title: Cable pulling and Termination work Finish Time:
Inspected work: Fiber optic cable OTDR test report
Structure/Location: Substation area, Building and PV area :
Basic documents for acceptance:
1.Approved drawings: SKD-DEC-SS-ELE-DRA -
2.Method statement and risk assessment: SKD-DEC-QAC-INP-046
3.Inspection and test plan: SKD-DEC-QAC-ITP-007
3.Measurement and test report, as attached (if any):

18
SKD-DEC-QAC-ITP-054
Test Plan (ITP) For Cable pulling &
Termination work

4.Request for inspection:


5.Other relative documents (if any):
Method of Inspection
□Visual □Laboratory test □Measurement □Survey □Others
Assessment
NO. Inspection content
Subcontractor EPC
Wave Length: nm Pass Criteria : db.
P-Acceptable fiber loss: db./KM L-Length Measured by OTDR: KM
S-Acceptable Splice Loss: db. N-NO,of splices
C-Number of connectors: X-Acceptable Connector Loss: db.
Power Transmitted at A: db. Power transmitted at B: db.
A-B B-A Average
Fiber Color or (IL)
Tube No
No: Power Receved at B IL (A-B) Power Receved at B IL (A-B) Insertion
Loss

IL(A-B): (Power transmited at A)-(Power Recaved at AB) IL(A-B): (Power transmited at B)-(Power Receved at A)
Maker : Model No:
Test Equipment :
Calibration Date : Serial No:
Note:
Conclusion: Accepted the above inspected work and agreed to carry out the next works. □ yes □ No
Sub-contractor EPC Contractor PC / PMC
ZECCA DEC Masdar / Gopa JURU
Position
Signature
Full Name

No: SKD-ITP-054-009
INSPECTION REPORT Date:
Sub-Contractor: ZECCA&CC5 Start Time:
Work Title: Cable pulling and Termination work Finish Time:
Inspected work: Fiber optic cable Termination Checklist
Structure/Location: Substation area, Building: From Control building to Unit -01 .
Basic documents for acceptance:
1.Approved drawings: SKD-DEC-SS-ELE-DRA-
2.Method statement and risk assessment: SKD-DEC-QAC-INP-046
3.Inspection and test plan: SKD-DEC-QAC-ITP-054
3.Measurement and test report, as attached (if any):
4.Request for inspection:
5.Other relative documents (if any):

19
SKD-DEC-QAC-ITP-054
Test Plan (ITP) For Cable pulling &
Termination work

Method of Inspection
□Visual □Laboratory test □Measurement □Survey □Others
Assessment
NO. Inspection content
Subcontractor EPC Remarks
1. Check cable code and size correct
2. Cable identity and tag number correct
3. Check installation of cable gland
4. Fibers terminated correctly at device
5. Fibers terminated correctly at patch panel
6. Fiber identification correct
Fibers cores terminated correctly at patch panel
7.
/control panel
8. Point to point continuity test after the termination

Note:
Conclusion: Accepted the above inspected work and agreed to carry out the next civil works. □ yes □ No
Sub-contractor EPC Contractor PC / PMC
ZECCA DEC Masdar / Gopa JURU
Position
Signature
Full Name

20