You are on page 1of 3

NATIONAL GRID

Title: Index Number:


CL-NG-6460-002-048
Check list of AC Distribution Panels Commissioning Page Number:
1 of 3

1.0 Equipment General Data and Information

Substation
Bay/Panel
Equipment Serial No
2.0 Mechanical check and Visual Inspection

Item Description Done Remarks


Inspect for physical damage or defects including quality of paint
1.
work
Inspect and verify ACDB Rating Plate, check bus-bar rating,
2.
short circuit withstand current & main MCCBs rating at 55 oC.
3. Verify correct rating of each circuit breaker per design drawings
4. Check tightness of all bolted connections
Verify that all front panel mounted devices (meters, selector
5. switches, push buttons, timers, indication lamps, etc.) are
installed per layout drawing and are correctly labeled
6. Check for proper grounding connection (torque wrench method)
Check that all wiring within the panel are rated 1000/600V and
7.
not smaller than 2.5mm2
Check that wiring made without splices. The control wires have
8. solderless insulating ring type terminals, tin plated copper crimp
type.
9. Check color coding as per specifications.
Check no more than two conductors terminated together at one
10.
terminal point.
11. Check all ferruling as per specification.
12. Check CT circuits terminal blocks are as per specification.
Check terminal blocks are grouped according to function, i.e.
13. (AC or DC power supply), CT, DC CONTROLS,
ANNUNCATION, SOE, SCADA etc. and are labeled accordingly.
Check not less than 20% spare terminals are provided on each
14.
terminal block.
Check all spare contacts of relays, conductors, switches etc. are
15.
wired up to terminal blocks for future use.
16. Check the grounding as per specification.
17. Check nameplates as per specification and schematic drawings.
18. Check indications, alarms.

Archiving System Website: http://AMAS


NATIONAL GRID

Title: Index Number:


CL-NG-6460-002-048
Check list of AC Distribution Panels Commissioning Page Number:
2 of 3

3.0 Electrical Test

Item Description Done Remarks


1. Insulation test of all buses and wiring.
2. Phasing check
3. Check all MCBs for their ratings and alarms.
Apply trip test for all MCCBs by pole- pole current injection
4.
method
Test all voltmeters, ammeters, watt-meters, MCBs, Auxiliary
5.
relays, protection relays and control devices.
6. Functional check of main power supply circuit breaker.
7. Functional check of each branch circuit breaker
8. Functional check phase selector switches
9. Schem check for all panels and control circuits.
10. Check Automatic Transfer Switching scheme (ATS)

CSD Contractor T&C Contractor


Name
Sign.

Archiving System Website: http://AMAS


NATIONAL GRID

Title: Index Number:


CL-NG-6460-002-048
Check list of AC Distribution Panels Commissioning Page Number:
3 of 3

Archiving System Website: http://AMAS

You might also like