PROCEDURE FOR OVERHAULING MOTOR


Following preparation to be done before start doing
job for motor change / overhauling
BEFORE MOTOR REPLACEMENT
SPARE MOTOR TO BE ARRANGE
Insure arranged motor Frame,
mounting and RPM should be
same as installed motor.

Do not start work before


confirm motor data is
shoutable for replacement
motor
SHUTDOWN TO BE TAKEN FROM
CONCERN DEPARTMENT

SHUTDOWN IS BASIC PROTOCOL


FOR WORKING ANY ELECTRICAL
SYSTEM.

While it's understandable


that an interruption is not
ideal for facility operations,
safety is of utmost
importance
ISOLATE THE POWER AND PLACE DANGER BOARD ON
FEEDER FOR AVOID ACCIDENT
NOTE PHASE SEQUENCE &
DISCONNECT ALL CONNECTION
DISCONNECT ALL CABLE AND EARTH
MOTOR REPLACEMENT
CHECK IR AND WR OF MOTOR
CHECK STAR / DELTA LINK OF MOTOR
CHECK ALIGNMENT OF
COUPLING
CONNECTION AND
COVER TO BE PROVIDE
PROPERLY
DURING TRIAL OF
MOTOR