The document shows a list of 16 items for a construction project with details on the item description, quantity, contracted cost, executed cost, and physical and financial completion percentages. The total contracted cost for all items was over 284 million with over 151 million executed so far, resulting in an overall financial completion of 53.14% and physical completion of 56.27%.
The document shows a list of 16 items for a construction project with details on the item description, quantity, contracted cost, executed cost, and physical and financial completion percentages. The total contracted cost for all items was over 284 million with over 151 million executed so far, resulting in an overall financial completion of 53.14% and physical completion of 56.27%.
The document shows a list of 16 items for a construction project with details on the item description, quantity, contracted cost, executed cost, and physical and financial completion percentages. The total contracted cost for all items was over 284 million with over 151 million executed so far, resulting in an overall financial completion of 53.14% and physical completion of 56.27%.
Bill No Item Description Unit Qty Cont Executed Fin Stat %
1 General Item LS 1 12,403,000 8,178,500 65.9%
2 Supply of HDPE Pipes For Transmission Main KM 56.7 139,771,240 61,637,030 44.1% 3 Pipe Civil Work KM 53.0 88,567,088 45,544,673 51.4% 4 100m3 Booster Reservoir No 1 2,108,594 1,894,980 89.9% 5 1000m3 Reservoir No 1 13,953,985 12,605,901 90.3% 6 Generator House No 2 1,480,563 774,214 52.3% 7 Pump House No 1 2,196,231 1,628,290 74.1% 8 Guard House at 1000m3 Reservoir & Booster St. No 2 1,666,358 1,131,485 67.9% 9 Construction of Water Points No 25 6,116,235 1,450,407 23.7% 10 Construction of Cattle Troughs No 15 5,352,828 1,807,032 33.8% 11 Fencing Works No 5 3,999,159 6,402,827 160.1% 12 Rehabilitation of Existing 100m3 Reservoirs No 1 425,840 0 0.0% 13 Construction of Operator Dwelling No 1 2,589,992 2,954,321 114.1% 15 Access Road To 1000m3 Reservoir LS 1 3,377,250 5,385,984 159.5% 16 Construction of Toilet LS 1 968,363 27,760 2.9% Total 284,976,726 151,423,404 53.14% Phy Stat % 75% 39% 40% 95% 90% 48% 92% 55% 52% 20% 33% 0% 95% 100% 10% 56.27%