The document provides a cost summary and status update for the Bike Water Supply and Sanitation Project. The total contract amount is $49,992,524 and so far $45,118,983 has been spent, which is 90.3% of the total. Pipe works are 92.4% complete financially and 95.5% complete physically. Civil works are 88.7% complete financially and 82% complete physically. Several individual items like generators and guard houses are near 98% complete physically.
The document provides a cost summary and status update for the Bike Water Supply and Sanitation Project. The total contract amount is $49,992,524 and so far $45,118,983 has been spent, which is 90.3% of the total. Pipe works are 92.4% complete financially and 95.5% complete physically. Civil works are 88.7% complete financially and 82% complete physically. Several individual items like generators and guard houses are near 98% complete physically.
The document provides a cost summary and status update for the Bike Water Supply and Sanitation Project. The total contract amount is $49,992,524 and so far $45,118,983 has been spent, which is 90.3% of the total. Pipe works are 92.4% complete financially and 95.5% complete physically. Civil works are 88.7% complete financially and 82% complete physically. Several individual items like generators and guard houses are near 98% complete physically.
Project:- Bike Water Supply and Sanitation Project
Cost Summary all Works
Contract Financial Item No Item Description Total Amount Amount Status % A-1 General Items 2,294,000 2,950,000 77.8% A-2 Pipe works 27,819,605 30,123,261 92.4% A-3 Civil works 15,005,378 16,919,263 88.7% TOTAL 45,118,983 49,992,524 90.3% Physical Status % 100.0% 95.5% 82.0% 92.5% Total Executed S.No Description of Item No Amount C-1 Ground Reservior of 1000m3 1 3,363,214.5 C-2 Ground Reservior of 500m3 1 2,259,752.8 C-3 Construction of 200m3 underground at cooling basin 1 2,129,506.3 C-7 Generator and Guard house at BH and 500m3 2 1,747,364.5 construction of toilet at 1000m3, 500m^3 booster station C-9 3 671,130.4 and borehole Artificail well at Boster Station 500m3 and at 200m3 C-10 1 343,579.2 Underground RCC C-12 Solid Waste Disposal pit 1 987,750.0 C-15 Rectangular water cooling tank 1 3,503,080.7 Sub Total 15,005,378.4 Financial Physical Total Amount Status % Status % 4,869,082.2 69.1% 75.0% 3,019,106.7 74.8% 80.0% 2,657,289.6 80.1% 90.0% 1,704,664.0 102.5% 97.0%
1,063,195.7 63.1% 85.0%
1,073,294.9 32.0% 35.0%
1,193,350.0 82.8% 95.0%
1,339,280.3 261.6% 99.0% 16,919,263.4 88.7% 82.0% Financial Physical Item No Item Description Status Status 1 Construction of Cooling tank 98% 2 Construction of Underground rectangular tank 90%
3 Construction of Generator and Guard House @BH&BS2 98%
4 Construction of Toilet @BH&1000M3 98%
5 Construction of 500m3 Booster Reservoir 80% 6 Construction of 1000m3 Service Reservoir 75% 7 Construction of Toilet @500M3 20% 8 Construction of wet well 35% 9 Trench Excavation 100% 10 Pipe welding and laying 98% 11 Construction of Solid Waste Disposal 80% 13 Pipe Supply 100% 98% 81% S.No Description of Item No Total Executed Total Amount
Supply of HDPE - Raising main and Fitting :- From
B-1 Borhole To 500m3 Booster Station and from booster 1 20,355,000 20,355,000 1 to Service Reservior B-2 Mainline welding,laying & fitting 1 1,453,520 1,414,000 Main Line Trench excavation from BH to Service B-3 1 4,620,634 5,725,424.0 Reservoir B-4 Mainline pipe Civil Works 1 1,390,450 2,628,836.8 Sub Total 27,819,604.5 30,123,260.8 Financial Physical Status % Status %