1. Hydrogeology
2. Pumping unit including solar system
3. Elevated steel platforms
7 Allow 2% provisional sum for supervision fee by the project management team 741,150.00
3.9 Supply and insert filter gravel pack material Bags 30 2,000 60,000.00
4.0 Borehole development of the borehole Hrs 3 5,500 16,500.00
4.1 Prepare well head, well cap serial number and cement slab around the LS 1 24,500 24,500.00
well head with dimensions of 1mx1mx1m (this should be reinforced
mass concrete round the borehole with a concrete cover and all be
submerged below the river bed to allow smooth floor of the river with
zero interuptions). This
should be done as designed and instructions from the P.E
4.2 Supply of water for drillling operations and field camp LS 1 35,000 35,000.00
4.3 Test pumping of boreholes including inserting and removal of Hrs 24 4,500 108,000.00
pump
4.4 Physical, Chemical and bacterialogical analysis of the water LS 1 30,000 30,000.00
obtained
Sub Totals for borehole drilling, development & test pumping 3,029,000.00
Sub Total for 1no. Borehole 3,029,000.00
Total for 2no. Borehole 6,058,000.00
Notes: Items in Bill No. 3.2-3.5 are provisional rates which shall only be sunctioned by the client or his
1 representative Items in Bill No. 3 are provisional rates dependant on the amount of water obtained after
2 drilling & test
A B C D E F
Item Description Unit Qty(a) Rate(b)
Amount(a*b)
3 2,500,000 2,500,000.00
Provide and install a 150m pressed mild steel panels of 6mm
thick, internal bracings, brackets and roof cover of minimum
1.5mm thick MS sheets, calibrated water-level indicator,
external and internal ladder and lockable manhole cover.Provide
A No. 1
all bolts and sealant as necessary. Inside of tank to be painted
with two coats of non-toxic bituminous black paint and outside
to be painted with two coats of silver aluminous paint.
Provide and erect (concrete pad foundation included) 15 m high 700,000 700,000.00
steel tower comprising of universal columns, angle bracings, cat-
ladders and platform comprising of UB beams, 3mm thick
chequered plate on 600mm wide walkway with 900mm high
B No. 1
guard rail. Provide all bolts necessary for erection. The steel
tower to be painted with one coat grey oxide zinc chromate
primer, two coats silver aluminium paint. Tower should include
provide cat ladder.
Supply and install the pipes to the ground level of the tanks all 182,000.00
C pipes and fittings to be 4" GI (rising as inlet and down No. 4 45,500
distribution pipe)
Sub Totals for elevated steel tank 3,382,000.00
Pipes and pipe Fittings: Meters, valves and Chambers
D 90mm Ø gate valve (peglur) complete with fittings No. 2 48,500 97,000
Junction chambers -
E Supply materials, transport to site and construct 1m x 1m x 1m No. 2
35,000
Junction/control chambers with locked steel cover 70,000
Sub totals for pipe and pipe fittings 167,000
Sub Totals for Pipes
Sub totals for elevated steel tank 3,382,000.00
Sub totals for pipes and pipe fittings 167,000
TOTAL FOR ELEVATED STEEL TANK 3,549,000.00
A B C D E F
Item Description Unit Qty(a) Rate(b)
Amount(a*b
Bill No 6 ELEVATED STEEL TANK (2No.)
Construction of 100m3 steel tank on 15m tower (5m x 5m x
4m P.S.ST)
3 2,100,000 2,100,000
Provide and install a 100m pressed mild steel panels of 6mm
thick, internal bracings, brackets and roof cover of minimum
1.5mm thick MS sheets, calibrated water-level indicator, external
A and internal ladder and lockable manhole cover. No. 1
Provide all bolts and sealant as necessary. Inside of tank to be
painted with two coats of non-toxic bituminous black paint and
outside to be painted with two coats of silver aluminous paint.
Provide and erect (concrete pad foundation included) 15 m high 655,000 655,000
steel tower comprising of universal columns, angle bracings, cat-
ladders and platform comprising of UB beams, 3mm thick
chequered plate on 600mm wide walkway with 900mm high
B No. 1
guard rail. Provide all bolts necessary for erection. The steel
tower to be painted with one coat grey oxide zinc chromate
primer, two coats silver aluminium paint. Tower
should include provide cat ladder.
Supply and install the pipes to the ground level of the tanks all 182,000
C pipes and fittings to be 4" GI (rising as inlet and down No. 4 45,500
distribution pipe)
Sub Totals for elevated steel tank 2,937,000
Pipes and pipe Fittings: Meters, valves and Chambers -
D 90mm Ø gate valve (peglur) complete with fittings No. 2 48,500 97,000
Junction chambers -
E Supply materials, transport to site and construct 1m x 1m x 1m No. 2 70,000
35,000
Junction/control chambers with locked steel cover
Sub totals for pipe and pipe fittings 167,000
Sub totals for elevated steel tank 2,937,000
Sub totals for pipes and pipe fittings 167,000
TOTAL FOR 1NO. ELEVATED STEEL TANK 3,104,000
TOTAL FOR 1NO. ELEVATED STEEL TANK 3,104,000
A B C D E F