May 2024 Jun 2024 Jul 2024 Aug 2024

Name Duration Start Finish


31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25
1 CA Estate Access Road... 114 days? 4/5/24 8:00 AM 7/29/24 5:00 PM
2 Start Project 0 days? 4/5/24 8:00 AM 4/5/24 8:00 AM
3 Prelmiinaries 19 days 4/5/24 8:00 AM 4/23/24 5:00 PM
4 Permits 5 days 4/5/24 8:00 AM 4/9/24 5:00 PM Project Manager;Surveyor[0%]
5 Site Office Set Up 14 days 4/10/24 8:00 AM 4/23/24 5:00 PM Project Manager;Foreman;Mason;Carpentor;Helpers
6 Road Works 61 days 4/24/24 8:00 AM 6/25/24 5:00 PM
7 Site Survey 14 days 4/24/24 8:00 AM 5/7/24 5:00 PM Project Manager;Surveyor;Foreman[50%]
8 Site Clearance 12 days 5/8/24 8:00 AM 5/19/24 5:00 PM Project Manager[50%];Civil Engineer;Foreman;Plant Operator;Helpers
9 Excavations 21 days 5/15/24 8:00 AM 6/6/24 5:00 PM Project Manager;Civil Engineer;Surveyor[50%];Foreman;Plant Operator;Hel
10 Grading /Gravelling 25 days 5/30/24 8:00 AM 6/25/24 5:00 PM Project Manager;Civil Engineer;Foreman;Mason;Plant Oper
11 Pedestrian Pavement 29 days 6/26/24 8:00 AM 7/24/24 5:00 PM
12 EarthWorks 10 days 6/26/24 8:00 AM 7/5/24 5:00 PM Project Manager;Civil Engineer;Foreman;Plant Op
13 Road Kerbs 7 days 7/6/24 8:00 AM 7/12/24 5:00 PM Project Manager;Foreman;Mason;Helpers
14 Paving Slabs 12 days 7/13/24 8:00 AM 7/24/24 5:00 PM Project Manager[50%];Foreman;M
15 Road Furniture 5 days 7/25/24 8:00 AM 7/29/24 5:00 PM Project Manager;Foreman;M
16 Finish Project 0 days 7/29/24 5:00 PM 7/29/24 5:00 PM 7/29
CA Estate Access Roads at AFRALTI