Niketan Hotel Project

Master Schedule Ver 2 (3 May 2014)


ID Task Name Duration Start Finish 2013
Jun Jul Aug Sep Oct Nov Dec Jan Feb
1 Niketan Hotel 1531 days 01/06/13 08:00 25/09/17 17:00 1
2 Regulatory Approvals 376 days 01/06/13 08:00 30/06/14 17:00
3 CDA Special Committee Approval for LUC 1 day 11/11/13 08:00 11/11/13 17:00 11/11
4 CDA Hotel Construction Approval 1 day 01/06/13 08:00 01/06/13 17:00 01/06
5 Environment Department Approval 1 day 30/06/14 08:00 30/06/14 17:00
6 Fire Department Approval 1 day 15/12/13 08:00 15/12/13 17:00 15/12
7 Design Phase 496 days 01/06/13 08:00 25/11/14 17:00 4
8 Architectural Concept Design 176 days 01/06/13 08:00 12/12/13 17:00
9 Architectural Design ( 1st Draft ) 19 days 13/04/14 08:00 01/05/14 17:00
10 Approval of Architectural Design (1st Draft ) 7 days 02/05/14 08:00 08/05/14 17:00
11 Preliminary Architectural drawing ( GFC ) 19 days 04/05/14 08:00 22/05/14 17:00
12 Architectural Detailed Design for Structural 170 days 13/12/13 08:00 31/05/14 17:00
13 Foundation Design 32 days 03/05/14 08:00 03/06/14 17:00
14 Shore Piling Drawings 3 days 09/05/14 08:00 11/05/14 17:00
15 Shore piling working Drawings ( GFC ) 5 days 12/05/14 08:00 16/05/14 17:00
16 Complete Revised Architectural plan 20 days 09/05/14 08:00 28/05/14 17:00
17 Complete Revised Architectural Sections & Elevations 10 days 29/05/14 08:00 07/06/14 17:00
18 Complete Architectural Working Drawing ( GFC ) 30 days 24/05/14 08:00 22/06/14 17:00
19 Complete Structural Design (GFC) 21 days 01/06/14 08:00 21/06/14 17:00
20 MEP Design Drawings 30 days 01/06/14 08:00 30/06/14 17:00
21 MEP ( DBR ) 15 days 17/05/14 08:00 31/05/14 17:00
22 Approval of MEP Design (1st Draft ) 8 days 01/06/14 08:00 08/06/14 17:00
23 MEP Design Drawings ( GFC ) 31 days 09/06/14 08:00 09/07/14 17:00
24 Architectural coordination drawings based on services & 20 days 10/07/14 08:00 08/08/14 17:00
Structural drawings
25 Detailed drawings for doors and windows 15 days 09/08/14 08:00 23/08/14 17:00
26 Final Schedule of finishes and specifications. 20 days 24/08/14 08:00 12/09/14 17:00
27 Detailed Fit-out Drawings 150 days 23/05/14 08:00 16/11/14 17:00
28 Detailed Fit-out Specification Schedules 69 days 31/08/14 08:00 25/11/14 17:00
29 Mobilization Work 92 days 06/04/14 08:00 06/07/14 17:00
30 Site mobilization 49 days 06/04/14 08:00 24/05/14 17:00
31 Layout works 5 days 02/06/14 08:00 06/06/14 17:00
32 Fence & Sign Board 20 days 17/06/14 08:00 06/07/14 17:00

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Prepared by: Kaymonto & Partner Milestone Inactive Milestone Start-only


Summary Inactive Summary Finish-only
Project Summary Manual Task Progress
External Tasks Duration-only Deadline

Page 1 of 15
Niketan Hotel Project
Master Schedule Ver 2 (3 May 2014)
ID Task Name Duration Start Finish 2013
Jun Jul Aug Sep Oct Nov Dec Jan Feb
33 Shore Protection Work 114 days 07/07/14 08:00 25/11/14 17:00
34 Shore Piling 90 days 07/07/14 08:00 01/11/14 17:00
35 Tie Beam 24 days 02/11/14 08:00 25/11/14 17:00
36 Earth Excavation 80 days 26/11/14 08:00 13/02/15 17:00
37 1st Phase Excavation 30 days 26/11/14 08:00 25/12/14 17:00
38 1st Phase Earth Cutting & Bracing(upto -10' 0'' Level) 30 days 26/11/14 08:00 25/12/14 17:00

39 2nd phase Excavation 50 days 26/12/14 08:00 13/02/15 17:00


40 2nd Phase Earth Cutting & Bracing 50 days 26/12/14 08:00 13/02/15 17:00
41 Structural Work 505 days 30/01/15 08:00 17/06/16 17:00
42 Sub Structure 130 days 30/01/15 08:00 08/06/15 17:00
43 Mat casting & R/W 60 days 30/01/15 08:00 30/03/15 17:00
44 Basement-2 & RW 35 days 31/03/15 08:00 04/05/15 17:00
45 Column Casting & RW 15 days 31/03/15 08:00 14/04/15 17:00
46 B-2 Roof Slab Casting 20 days 15/04/15 08:00 04/05/15 17:00
47 Basement-1 & RW 35 days 05/05/15 08:00 08/06/15 17:00
48 Column Casting & RW 15 days 05/05/15 08:00 19/05/15 17:00
49 B-1 Roof Slab Casting 20 days 20/05/15 08:00 08/06/15 17:00
50 Super Structure 375 days 09/06/15 08:00 17/06/16 17:00
51 Ground Floor 45 days 09/06/15 08:00 23/07/15 17:00
52 Column & Shear Wall Casting 15 days 09/06/15 08:00 23/06/15 17:00
53 Roof Slab Casting 30 days 24/06/15 08:00 23/07/15 17:00
54 1st Floor 30 days 24/07/15 08:00 22/08/15 17:00
57 2nd Floor 30 days 23/08/15 08:00 21/09/15 17:00
58 Column & Shear Wall Casting 15 days 23/08/15 08:00 06/09/15 17:00
59 Roof Slab Casting 15 days 07/09/15 08:00 21/09/15 17:00
60 3rd Floor 30 days 22/09/15 08:00 21/10/15 17:00
61 Column & Shear Wall Casting 15 days 22/09/15 08:00 06/10/15 17:00
62 Roof Slab Casting 15 days 07/10/15 08:00 21/10/15 17:00
63 4th Floor 30 days 22/10/15 08:00 20/11/15 17:00
64 Column & Shear Wall Casting 15 days 22/10/15 08:00 05/11/15 17:00
65 Roof Slab Casting 15 days 06/11/15 08:00 20/11/15 17:00
66 5th Floor 30 days 21/11/15 08:00 20/12/15 17:00

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Prepared by: Kaymonto & Partner Milestone Inactive Milestone Start-only


Summary Inactive Summary Finish-only
Project Summary Manual Task Progress
External Tasks Duration-only Deadline

Page 2 of 15
Niketan Hotel Project
Master Schedule Ver 2 (3 May 2014)
ID Task Name Duration Start Finish 2013
Jun Jul Aug Sep Oct Nov Dec Jan Feb
67 Column & Shear Wall Casting 15 days 21/11/15 08:00 05/12/15 17:00
68 Roof Slab Casting 15 days 06/12/15 08:00 20/12/15 17:00
69 6th Floor 30 days 21/12/15 08:00 19/01/16 17:00
70 Column & Shear Wall Casting 15 days 21/12/15 08:00 04/01/16 17:00
71 Roof Slab Casting 15 days 05/01/16 08:00 19/01/16 17:00
72 7th Floor 30 days 20/01/16 08:00 18/02/16 17:00
73 Column & Shear Wall Casting 15 days 20/01/16 08:00 03/02/16 17:00
74 Roof Slab Casting 15 days 04/02/16 08:00 18/02/16 17:00
75 8th Floor 30 days 19/02/16 08:00 19/03/16 17:00
76 Column & Shear Wall Casting 15 days 19/02/16 08:00 04/03/16 17:00
77 Roof Slab Casting 15 days 05/03/16 08:00 19/03/16 17:00
78 9th Floor 30 days 20/03/16 08:00 18/04/16 17:00
79 Column & Shear Wall Casting 15 days 20/03/16 08:00 03/04/16 17:00
80 Roof Slab Casting 15 days 04/04/16 08:00 18/04/16 17:00
81 10th Floor 30 days 19/04/16 08:00 18/05/16 17:00
82 Column & Shear Wall Casting 15 days 19/04/16 08:00 03/05/16 17:00
83 Roof Slab Casting 15 days 04/05/16 08:00 18/05/16 17:00
84 OHWT + Machine Room+Others 30 days 19/05/16 08:00 17/06/16 17:00
85 Finishing Work 720 days 07/10/15 08:00 25/09/17 17:00
86 Brick work 370 days 07/10/15 08:00 10/10/16 17:00
87 Electrical work (concealed) 370 days 06/11/15 08:00 09/11/16 17:00
88 Plumbing Concealed Work 370 days 06/11/15 08:00 09/11/16 17:00
89 Door frame fitting 370 days 21/12/15 08:00 24/12/16 17:00
90 Metal Work(Grill, railing) 370 days 20/01/16 08:00 23/01/17 17:00
91 Inside Plaster Work 370 days 04/02/16 08:00 07/02/17 17:00
92 Out side work 130 days 08/02/17 08:00 17/06/17 17:00
93 Electrical Wiring & SDB 320 days 05/03/16 08:00 18/01/17 17:00
94 Tiles & Marble Works 565 days 20/01/16 08:00 06/08/17 17:00
95 Sample Collection & Approval 30 days 20/01/16 08:00 18/02/16 17:00
96 Procurement 120 days 19/02/16 08:00 17/06/16 17:00
97 Execution 120 days 09/04/17 08:00 06/08/17 17:00
98 Wood work(Door Shutter) 120 days 09/05/17 08:00 05/09/17 17:00
99 Aluminum work 530 days 04/02/16 08:00 17/07/17 17:00

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Prepared by: Kaymonto & Partner Milestone Inactive Milestone Start-only


Summary Inactive Summary Finish-only
Project Summary Manual Task Progress
External Tasks Duration-only Deadline

Page 3 of 15
Niketan Hotel Project
Master Schedule Ver 2 (3 May 2014)
ID Task Name Duration Start Finish 2013
Jun Jul Aug Sep Oct Nov Dec Jan Feb
100 Sample Collection & Approval 45 days 04/02/16 08:00 19/03/16 17:00
101 Procurement 90 days 20/03/16 08:00 17/06/16 17:00
102 Execution 130 days 10/03/17 08:00 17/07/17 17:00
103 Fixture Fittings 320 days 19/04/16 08:00 04/03/17 17:00
104 Sample Collection & Approval 40 days 19/04/16 08:00 28/05/16 17:00
105 Procurement 100 days 29/05/16 08:00 05/09/16 17:00
106 Execution 180 days 06/09/16 08:00 04/03/17 17:00
107 Switch & Socket Fitting 120 days 29/05/17 08:00 25/09/17 17:00
108 Painting 120 days 09/04/17 08:00 06/08/17 17:00
109 Polishing and Pointing Work 60 days 08/07/17 08:00 05/09/17 17:00
110 Sub station Installation 240 days 04/04/16 08:00 29/11/16 17:00
111 Quotation Collection 30 days 04/04/16 08:00 03/05/16 17:00
112 Contractor Selection 30 days 04/05/16 08:00 02/06/16 17:00
113 L/c Opening & Site Delivery 120 days 03/06/16 08:00 30/09/16 17:00
114 Installation 30 days 01/10/16 08:00 30/10/16 17:00
115 Commissioning 30 days 31/10/16 08:00 29/11/16 17:00
116 Generator Installation 200 days 04/05/16 08:00 19/11/16 17:00
117 Quotation Collection 30 days 04/05/16 08:00 02/06/16 17:00
118 Contractor Selection 30 days 03/06/16 08:00 02/07/16 17:00
119 L/c Opening 90 days 03/07/16 08:00 30/09/16 17:00
120 Installation 30 days 01/10/16 08:00 30/10/16 17:00
121 Commissioning 20 days 31/10/16 08:00 19/11/16 17:00
122 Lift Installation 270 days 04/04/16 08:00 29/12/16 17:00
123 Quotation Collection 30 days 04/04/16 08:00 03/05/16 17:00
124 Contractor Selection 30 days 04/05/16 08:00 02/06/16 17:00
125 L/c Opening & Lift at Site 120 days 03/06/16 08:00 30/09/16 17:00
126 Lift installation 60 days 01/10/16 08:00 29/11/16 17:00
127 Commissioning 30 days 30/11/16 08:00 29/12/16 17:00
128 Air Condition 270 days 04/04/16 08:00 29/12/16 17:00
129 Quotation Collection 30 days 04/04/16 08:00 03/05/16 17:00
130 Contractor Selection 30 days 04/05/16 08:00 02/06/16 17:00
131 L/c Opening 90 days 03/06/16 08:00 31/08/16 17:00
132 Installation 90 days 01/09/16 08:00 29/11/16 17:00

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Prepared by: Kaymonto & Partner Milestone Inactive Milestone Start-only


Summary Inactive Summary Finish-only
Project Summary Manual Task Progress
External Tasks Duration-only Deadline

Page 4 of 15
Niketan Hotel Project
Master Schedule Ver 2 (3 May 2014)
ID Task Name Duration Start Finish 2013
Jun Jul Aug Sep Oct Nov Dec Jan Feb
133 Commissioning 30 days 30/11/16 08:00 29/12/16 17:00
134 Others 385 days 01/09/16 08:00 20/09/17 17:00
135 Fire Protection 160 days 01/09/16 08:00 07/02/17 17:00
136 Utility connections 160 days 01/10/16 08:00 09/03/17 17:00
137 Water Purification System 120 days 10/11/16 08:00 09/03/17 17:00
138 PABX 120 days 10/11/16 08:00 09/03/17 17:00
139 CCTV 120 days 10/11/16 08:00 09/03/17 17:00
140 Boundary wall (Structural) 70 days 30/03/17 08:00 07/06/17 17:00
141 Main gate fitting 15 days 08/06/17 08:00 22/06/17 17:00
142 Ground floor finishing 90 days 30/11/16 08:00 27/02/17 17:00
143 Land scaping 90 days 30/11/16 08:00 27/02/17 17:00
144 Interior decoration 100 days 29/05/17 08:00 05/09/17 17:00
145 Decoration at common area 90 days 30/11/16 08:00 27/02/17 17:00
146 CDA inspection for Occupancy certificate 60 days 23/06/17 08:00 21/08/17 17:00
147 Hand over 30 days 22/08/17 08:00 20/09/17 17:00

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Prepared by: Kaymonto & Partner Milestone Inactive Milestone Start-only


Summary Inactive Summary Finish-only
Project Summary Manual Task Progress
External Tasks Duration-only Deadline

Page 5 of 15
Niketan Hotel Project
Master Schedule Ver 2 (3 May 2014)
2014 2015
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

30/06

496 days

11/05

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Prepared by: Kaymonto & Partner Milestone Inactive Milestone Start-only


Summary Inactive Summary Finish-only
Project Summary Manual Task Progress
External Tasks Duration-only Deadline

Page 6 of 15
Niketan Hotel Project
Master Schedule Ver 2 (3 May 2014)
2014 2015
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Prepared by: Kaymonto & Partner Milestone Inactive Milestone Start-only


Summary Inactive Summary Finish-only
Project Summary Manual Task Progress
External Tasks Duration-only Deadline

Page 7 of 15
Niketan Hotel Project
Master Schedule Ver 2 (3 May 2014)
2014 2015
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Prepared by: Kaymonto & Partner Milestone Inactive Milestone Start-only


Summary Inactive Summary Finish-only
Project Summary Manual Task Progress
External Tasks Duration-only Deadline

Page 8 of 15
Niketan Hotel Project
Master Schedule Ver 2 (3 May 2014)
2014 2015
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Prepared by: Kaymonto & Partner Milestone Inactive Milestone Start-only


Summary Inactive Summary Finish-only
Project Summary Manual Task Progress
External Tasks Duration-only Deadline

Page 9 of 15
Niketan Hotel Project
Master Schedule Ver 2 (3 May 2014)
2014 2015
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Prepared by: Kaymonto & Partner Milestone Inactive Milestone Start-only


Summary Inactive Summary Finish-only
Project Summary Manual Task Progress
External Tasks Duration-only Deadline

Page 10 of 15
Niketan Hotel Project
Master Schedule Ver 2 (3 May 2014)
2016 2017
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
1531 d

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Prepared by: Kaymonto & Partner Milestone Inactive Milestone Start-only


Summary Inactive Summary Finish-only
Project Summary Manual Task Progress
External Tasks Duration-only Deadline

Page 11 of 15
Niketan Hotel Project
Master Schedule Ver 2 (3 May 2014)
2016 2017
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct

505 days

375 days

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Prepared by: Kaymonto & Partner Milestone Inactive Milestone Start-only


Summary Inactive Summary Finish-only
Project Summary Manual Task Progress
External Tasks Duration-only Deadline

Page 12 of 15
Niketan Hotel Project
Master Schedule Ver 2 (3 May 2014)
2016 2017
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct

720 da

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Prepared by: Kaymonto & Partner Milestone Inactive Milestone Start-only


Summary Inactive Summary Finish-only
Project Summary Manual Task Progress
External Tasks Duration-only Deadline

Page 13 of 15
Niketan Hotel Project
Master Schedule Ver 2 (3 May 2014)
2016 2017
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct

240 days

200 days

270 days

270 days

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Prepared by: Kaymonto & Partner Milestone Inactive Milestone Start-only


Summary Inactive Summary Finish-only
Project Summary Manual Task Progress
External Tasks Duration-only Deadline

Page 14 of 15
Niketan Hotel Project
Master Schedule Ver 2 (3 May 2014)
2016 2017
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct

385 day

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Prepared by: Kaymonto & Partner Milestone Inactive Milestone Start-only


Summary Inactive Summary Finish-only
Project Summary Manual Task Progress
External Tasks Duration-only Deadline

Page 15 of 15

You might also like