Mar 2024 Apr 2024 May 2024 Jun 2024 Jul 2024 Aug 2024

Name Duration Start Finish


04 11 18 25 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11
1 ANS HQ FENCE 110 days 2/8/24 8:00 AM 7/15/24 5:00 PM
2 Project start 0 days 2/12/24 8:00 AM 2/12/24 8:00 AM 2/12
3 Site Handover/Kick Off 1 day 2/8/24 8:00 AM 2/8/24 5:00 PM
4 Preliminaries 10 days 2/12/24 8:00 AM 2/23/24 5:00 PM
5 Construction Permits 10 days 2/12/24 8:00 AM 2/23/24 5:00 PM
6 Sub-Structures 73 days 2/15/24 8:00 AM 5/29/24 5:00 PM
7 Site Clearance/Demolitions 18 days 2/15/24 8:00 AM 3/11/24 5:00 PM
8 Excavations 21 days 3/4/24 8:00 AM 4/3/24 5:00 PM
9 Foundation Concrete Works 21 days 3/25/24 8:00 AM 4/24/24 5:00 PM
10 Foundation wall 21 days 4/16/24 8:00 AM 5/14/24 5:00 PM
11 Backfil 21 days 5/1/24 8:00 AM 5/29/24 5:00 PM
12 Super Structures 42 days 5/6/24 8:00 AM 7/3/24 5:00 PM
13 Columns 21 days 5/6/24 8:00 AM 6/4/24 5:00 PM
14 Masonry Wall 21 days 5/8/24 8:00 AM 6/6/24 5:00 PM
15 Coping/Piers 11 days 5/23/24 8:00 AM 6/7/24 5:00 PM
16 Finishes 24 days 5/30/24 8:00 AM 7/3/24 5:00 PM
17 Site Snagging 8 days 7/4/24 8:00 AM 7/15/24 5:00 PM
18 Hand Over 0 days 7/15/24 5:00 PM 7/15/24 5:00 PM 7/15
ANS HQ FENCE MLOLONGO