24 Nov '14 08 Dec '14 22 Dec '14 05 Jan '15 19 Jan '15 02 Feb '15 16 Feb '15 02 Mar '15 16 Mar '15 30 Mar '15 13 Apr '15 27 Apr '15 11 May '15 25 May '15 08 Jun '15 22 Jun '15 06 Jul '15 20 Jul '15 03 Aug '15 17 Aug '15 31 Aug '15 14 Sep '15 28 Sep '15 12 Oct '15 26 Oct '15 09 Nov '15
F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W
1 Aerospace Building Centre Construction 235 daysMon 15/12/14 Fri 06/11/15
2 Design Stage 26 days Mon 15/12/14 Mon 19/01/15
19 Erect Steel Columns, Beams and Joist for 1st Floor 10 days Wed 18/03/15 Tue 31/03/15
20 Erect Steel Columns, Beams and Joist for 2nd Floor 10 days Wed 01/04/15 Tue 14/04/15
21 Install Stairs and Miscellaneous Iron Railing 5 days Wed 15/04/15 Tue 21/04/15
22 Erect Roof Framing 10 days Wed 15/04/15 Tue 28/04/15
23 Form and Pour Concrete - Floors 44 days Wed 01/04/15 Mon 01/06/15
24 Form 1st floor 15 days Wed 01/04/15 Tue 21/04/15
25 Install electrical underground 5 days Wed 22/04/15 Tue 28/04/15
26 Install plumbing underground 5 days Wed 22/04/15 Tue 28/04/15
27 Pour 1st floor slab 10 days Wed 29/04/15 Tue 12/05/15
28 Cure 1st floor slab 7 days Wed 13/05/15 Thu 21/05/15
29 Strip forms from 1st floor slab 2 days Fri 22/05/15 Mon 25/05/15
30 Form 2nd floor including all floor openings 15 days Wed 15/04/15 Tue 05/05/15
31 Pour 2nd floor slab 10 days Wed 06/05/15 Tue 19/05/15
32 Cure 2nd floor slab 7 days Wed 20/05/15 Thu 28/05/15
33 Strip forms from 2nd floor slab 2 days Fri 29/05/15 Mon 01/06/15
34 Roofing 15 days Wed 29/04/15 Tue 19/05/15
35 Install seamless roofing material 15 days Wed 29/04/15 Tue 19/05/15
36 Wall 60 days Tue 02/06/15 Mon 24/08/15
54 Installation of Heating, Ventilating, and Air Conditioning 10 days Tue 18/08/15 Mon 31/08/15
(HVAC)
63 Rain Water Collection System Installation 1 day Wed 22/04/15 Wed 22/04/15
64 Rain Water Tank Storage Installation 15 days Thu 23/04/15 Wed 13/05/15
65 Pump Installation 3 days Thu 14/05/15 Mon 18/05/15
66 Rain Water Supplying System installation 15 days Tue 19/05/15 Mon 08/06/15
67 Certificate of Occupancy 14 days Tue 20/10/15 Fri 06/11/15
Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Project: Construction of Aerosp
Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress