ID Task Name Duration Start Finish

24 Nov '14 08 Dec '14 22 Dec '14 05 Jan '15 19 Jan '15 02 Feb '15 16 Feb '15 02 Mar '15 16 Mar '15 30 Mar '15 13 Apr '15 27 Apr '15 11 May '15 25 May '15 08 Jun '15 22 Jun '15 06 Jul '15 20 Jul '15 03 Aug '15 17 Aug '15 31 Aug '15 14 Sep '15 28 Sep '15 12 Oct '15 26 Oct '15 09 Nov '15
F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W
1 Aerospace Building Centre Construction 235 daysMon 15/12/14 Fri 06/11/15
2 Design Stage 26 days Mon 15/12/14 Mon 19/01/15

3 Site Survey 1 day Mon 15/12/14 Mon 15/12/14


4 Overall Building Design 20 days Tue 16/12/14 Mon 12/01/15
5 Foundation Design 20 days Tue 16/12/14 Mon 12/01/15
6 Framing and Wall Design 20 days Tue 16/12/14 Mon 12/01/15
7 Sustainable Building Design 20 days Tue 16/12/14 Mon 12/01/15
8 Finalise design 5 days Tue 13/01/15 Mon 19/01/15
9 Foundation 41 days Tue 20/01/15 Tue 17/03/15

10 Excavation for foundation 3 days Tue 20/01/15 Thu 22/01/15


11 Foundation Drainage System 5 days Fri 23/01/15 Thu 29/01/15
12 Form Basement Walls 15 days Fri 23/01/15 Thu 12/02/15
13 Pour Concrete for Foundations and Basement Walls 10 days Fri 13/02/15 Thu 26/02/15
14 Cure Foundations and Basement Walls 7 days Fri 27/02/15 Mon 09/03/15
15 Strip Basement Wall Forms 2 days Tue 10/03/15 Wed 11/03/15
16 Water Proofing and Insulation Basement Walls 2 days Thu 12/03/15 Fri 13/03/15
17 Backfill Soil 2 days Mon 16/03/15 Tue 17/03/15
18 Steel Framing 30 days Wed 18/03/15 Tue 28/04/15

19 Erect Steel Columns, Beams and Joist for 1st Floor 10 days Wed 18/03/15 Tue 31/03/15
20 Erect Steel Columns, Beams and Joist for 2nd Floor 10 days Wed 01/04/15 Tue 14/04/15
21 Install Stairs and Miscellaneous Iron Railing 5 days Wed 15/04/15 Tue 21/04/15
22 Erect Roof Framing 10 days Wed 15/04/15 Tue 28/04/15
23 Form and Pour Concrete - Floors 44 days Wed 01/04/15 Mon 01/06/15
24 Form 1st floor 15 days Wed 01/04/15 Tue 21/04/15
25 Install electrical underground 5 days Wed 22/04/15 Tue 28/04/15
26 Install plumbing underground 5 days Wed 22/04/15 Tue 28/04/15
27 Pour 1st floor slab 10 days Wed 29/04/15 Tue 12/05/15
28 Cure 1st floor slab 7 days Wed 13/05/15 Thu 21/05/15
29 Strip forms from 1st floor slab 2 days Fri 22/05/15 Mon 25/05/15
30 Form 2nd floor including all floor openings 15 days Wed 15/04/15 Tue 05/05/15
31 Pour 2nd floor slab 10 days Wed 06/05/15 Tue 19/05/15
32 Cure 2nd floor slab 7 days Wed 20/05/15 Thu 28/05/15
33 Strip forms from 2nd floor slab 2 days Fri 29/05/15 Mon 01/06/15
34 Roofing 15 days Wed 29/04/15 Tue 19/05/15
35 Install seamless roofing material 15 days Wed 29/04/15 Tue 19/05/15
36 Wall 60 days Tue 02/06/15 Mon 24/08/15

37 Wall Sheathing Installation 15 days Tue 02/06/15 Mon 22/06/15


38 Dry Wall Installation 15 days Tue 23/06/15 Mon 13/07/15
39 Wall Siding Installation 15 days Tue 14/07/15 Mon 03/08/15
40 Wall Insulation Installation 10 days Tue 04/08/15 Mon 17/08/15
41 Glass installation 10 days Tue 02/06/15 Mon 15/06/15
42 Door Installation 5 days Tue 18/08/15 Mon 24/08/15
43 Window Installation 5 days Tue 18/08/15 Mon 24/08/15
44 Finishing 40 days Tue 25/08/15 Mon 19/10/15

45 Flooring 20 days Tue 25/08/15 Mon 21/09/15


46 Tiling 20 days Tue 22/09/15 Mon 19/10/15
47 Painting 15 days Tue 25/08/15 Mon 14/09/15
48 Utilities (Sewer, Electrical, Water, Gas) 30 days Wed 29/04/15 Tue 09/06/15

49 Sewer Plumbing Works 30 days Wed 29/04/15 Tue 09/06/15


50 Lighting and Electrical Works 30 days Wed 29/04/15 Tue 09/06/15
51 Domestic Water Plumbing Works 30 days Wed 29/04/15 Tue 09/06/15
52 Gas Plumbing Works 30 days Wed 29/04/15 Tue 09/06/15
53 Mechanical Sytems 10 days Tue 18/08/15 Mon 31/08/15

54 Installation of Heating, Ventilating, and Air Conditioning 10 days Tue 18/08/15 Mon 31/08/15
(HVAC)

55 PV Solar System 65 days Wed 20/05/15 Tue 18/08/15

56 Structure Installation 20 days Wed 20/05/15 Tue 16/06/15


57 PV Modules Installation 20 days Wed 17/06/15 Tue 14/07/15
58 Cabling Works 10 days Wed 15/07/15 Tue 28/07/15
59 Combiner Box Installation 5 days Wed 29/07/15 Tue 04/08/15
60 Inverter Installation 5 days Wed 05/08/15 Tue 11/08/15
61 Connection to Grid 5 days Wed 12/08/15 Tue 18/08/15
62 Rain Water Harvesting 34 days Wed 22/04/15 Mon 08/06/15

63 Rain Water Collection System Installation 1 day Wed 22/04/15 Wed 22/04/15
64 Rain Water Tank Storage Installation 15 days Thu 23/04/15 Wed 13/05/15
65 Pump Installation 3 days Thu 14/05/15 Mon 18/05/15
66 Rain Water Supplying System installation 15 days Tue 19/05/15 Mon 08/06/15
67 Certificate of Occupancy 14 days Tue 20/10/15 Fri 06/11/15

Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Project: Construction of Aerosp
Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress

Page 1