PROGRAMME OF WORKS FOR PROPOSED DESIGN,CONSTRUCTION & EQUIPPING OF EASTERN REGIONAL HOSPITAL-PHASE 1,KOFORIDUA,EASTERN REGION

ID Task Name Duration Start Finish ust 2021 September 2021 October 2021 November 2021 December 2021 January 2022 February 2022 March 2022 April 2022 May 2022 June 2022 July 2022
4 9 14 19 24 29 3 8 13 18 23 28 3 8 13 18 23 28 2 7 12 17 22 27 2 7 12 17 22 27 1 6 11 16 21 26 31 5 10 15 20 25 2 7 12 17 22 27 1 6 11 16 21 26 1 6 11 16 21 26 31 5 10 15 20 25 30 5 10
1 PROGRAMME OF WORKS FOR PROPOSED DESIGN,CONSTRUCTION & 333 days Mon 8/9/21 Thu 7/7/22
EQUIPPING OF THE EASTERN REGIONAL HOSPITAL PROJECT- PHASE
2 CONSTRUCTION PREPARATION 25 days Mon 8/9/21 Thu 9/2/21
3 Preparation for manpower and machinery to site 5 days Mon 8/9/21 Fri 8/13/21
4 Temporary Site Buildings 20 days Sat 8/14/21 Thu 9/2/21
5 ZONE A 231 days Sat 8/14/21 Fri 4/1/22
6 Earthworks 58 days Sat 8/14/21 Sun 10/10/21
7 Setting-out 3 days Sat 8/14/21 Mon 8/16/21
8 Earthworks Excavation 15 days Tue 8/17/21 Tue 8/31/21
9 Foundation Excavation 10 days Wed 9/1/21 Fri 9/10/21
10 Backfill 10 days Fri 10/1/21 Sun 10/10/21
11 Concrete Works 177 days Sat 9/11/21 Sun 3/6/22
12 Foundation Concrete 45 days Sat 9/11/21 Mon 10/25/21
13 Blinding 5 days Sat 9/11/21 Wed 9/15/21
14 RC footing & Columns 15 days Thu 9/16/21 Thu 9/30/21
15 RC Beams & Slab 15 days Mon 10/11/21 Mon 10/25/21
16 BASEMENT 35 days Tue 10/26/21 Mon 11/29/21
17 Reinforcement 15 days Tue 10/26/21 Tue 11/9/21
18 Formwork 15 days Wed 11/10/21 Wed 11/24/21
19 Concrete Works 5 days Thu 11/25/21 Mon 11/29/21
20 GROUND FLOOR 25 days Tue 11/30/21 Fri 12/24/21
21 Reinforcement 13 days Tue 11/30/21 Sun 12/12/21
22 Formwork 7 days Mon 12/13/21 Sun 12/19/21
23 Concrete Works 5 days Mon 12/20/21 Fri 12/24/21
24 1st FLOOR 25 days Sat 12/25/21 Tue 1/18/22
25 Reinforcement 13 days Sat 12/25/21 Thu 1/6/22
26 Formwork 7 days Fri 1/7/22 Thu 1/13/22
27 Concrete Works 5 days Fri 1/14/22 Tue 1/18/22
28 2nd FLOOR 25 days Wed 1/19/22 Sat 2/12/22
29 Reinforcement 13 days Wed 1/19/22 Mon 1/31/22
30 Formwork 7 days Tue 2/1/22 Mon 2/7/22
31 Concrete Works 5 days Tue 2/8/22 Sat 2/12/22
32 3rd FLOOR 22 days Sun 2/13/22 Sun 3/6/22
33 Reinforcement 10 days Sun 2/13/22 Tue 2/22/22
34 Formwork 7 days Wed 2/23/22 Tue 3/1/22
35 Concrete Works 5 days Wed 3/2/22 Sun 3/6/22
36 MASONRY WALLS 48 days Sun 2/13/22 Fri 4/1/22
37 Basement walls 8 days Sun 2/13/22 Sun 2/20/22
38 Ground floor walls 10 days Mon 2/21/22 Wed 3/2/22
39 1st floor walls 10 days Thu 3/3/22 Sat 3/12/22
40 2nd floor walls 10 days Sun 3/13/22 Tue 3/22/22
41 3rd floor walls 10 days Wed 3/23/22 Fri 4/1/22
42 ZONE B 243 days Sat 9/11/21 Wed 5/11/22
43 Earthworks 88 days Sat 9/11/21 Tue 12/7/21
44 Setting-out 3 days Mon 10/11/21 Wed 10/13/21
45 Earthworks Excavation 25 days Thu 10/14/21 Sun 11/7/21
46 Foundation Excavation 20 days Mon 11/8/21 Sat 11/27/21
47 Backfill 10 days Sun 11/28/21 Tue 12/7/21
48 Concrete Works 148 days Fri 10/29/21 Fri 3/25/22
49 Foundation 55 days Fri 10/29/21 Wed 12/22/21
50 Blinding concrete 10 days Fri 10/29/21 Sun 11/7/21
51 RC footing & Columns 20 days Mon 11/8/21 Sat 11/27/21
52 RC Beams & Slab 15 days Sun 11/28/21 Sun 12/12/21
53 GROUND FLOOR 23 days Thu 12/23/21 Fri 1/14/22
54 Reinforcement 12 days Thu 12/23/21 Mon 1/3/22
55 Formwork 8 days Tue 1/4/22 Tue 1/11/22
56 Concrete Works 3 days Wed 1/12/22 Fri 1/14/22
57 1st FLOOR 23 days Sat 1/15/22 Sun 2/6/22
58 Reinforcement 12 days Sat 1/15/22 Wed 1/26/22
59 Formwork 8 days Thu 1/27/22 Thu 2/3/22
60 Concrete Works 3 days Fri 2/4/22 Sun 2/6/22
61 2nd FLOOR 20 days Mon 2/7/22 Sat 2/26/22
62 Reinforcement 10 days Mon 2/7/22 Wed 2/16/22
63 Formwork 7 days Thu 2/17/22 Wed 2/23/22
64 Concrete Works 3 days Thu 2/24/22 Sat 2/26/22
65 3rd FLOOR 27 days Sun 2/27/22 Fri 3/25/22
66 Reinforcement 12 days Sun 2/27/22 Thu 3/10/22
67 Formwork 10 days Fri 3/11/22 Sun 3/20/22
68 Concrete Works 5 days Mon 3/21/22 Fri 3/25/22
69 MASONRY WALLS 40 days Sat 4/2/22 Wed 5/11/22
70 Ground floor walls 10 days Sat 4/2/22 Mon 4/11/22
71 1st floor walls 10 days Tue 4/12/22 Thu 4/21/22
72 2nd floor walls 10 days Fri 4/22/22 Sun 5/1/22
73 3rd floor walls 10 days Mon 5/2/22 Wed 5/11/22
74 ZONE C 240 days Tue 10/26/21 Wed 6/22/22
75 Earthworks 70 days Tue 10/26/21 Mon 1/3/22
76 Setting-out 3 days Tue 10/26/21 Thu 10/28/21
77 Earthworks Excavation 20 days Fri 10/29/21 Wed 11/17/21
78 Foundation Excavation 15 days Thu 11/18/21 Thu 12/2/21
79 Backfill 10 days Sat 12/25/21 Mon 1/3/22
80 Concrete Works 145 days Fri 12/3/21 Tue 4/26/22
81 Foundation 46 days Fri 12/3/21 Mon 1/17/22
82 Blinding concrete 7 days Fri 12/3/21 Thu 12/9/21
83 RC footing & Columns 15 days Fri 12/10/21 Fri 12/24/21
84 RC Beams & Slab 14 days Tue 1/4/22 Mon 1/17/22
85 GROUND FLOOR 24 days Tue 1/18/22 Thu 2/10/22
86 Reinforcement 12 days Tue 1/18/22 Sat 1/29/22
87 Formwork 7 days Sun 1/30/22 Sat 2/5/22
88 Concrete Works 5 days Sun 2/6/22 Thu 2/10/22
89 1st FLOOR 24 days Fri 2/11/22 Sun 3/6/22
90 Reinforcement 12 days Fri 2/11/22 Tue 2/22/22
91 Formwork 7 days Wed 2/23/22 Tue 3/1/22
92 Concrete Works 5 days Wed 3/2/22 Sun 3/6/22
93 2nd FLOOR 27 days Mon 3/7/22 Sat 4/2/22
94 Reinforcement 15 days Mon 3/7/22 Mon 3/21/22
95 Formwork 7 days Tue 3/22/22 Mon 3/28/22
96 Concrete Works 5 days Tue 3/29/22 Sat 4/2/22
97 3rd FLOOR 24 days Sun 4/3/22 Tue 4/26/22
98 Reinforcement 12 days Sun 4/3/22 Thu 4/14/22
99 Formwork 7 days Fri 4/15/22 Thu 4/21/22
100 Concrete Works 5 days Fri 4/22/22 Tue 4/26/22
101 MASONRY WALLS 42 days Thu 5/12/22 Wed 6/22/22
102 Ground floor walls 10 days Thu 5/12/22 Sat 5/21/22
103 1st floor walls 10 days Sun 5/22/22 Tue 5/31/22
104 2nd floor walls 10 days Wed 6/1/22 Fri 6/10/22
105 3rd floor walls 12 days Sat 6/11/22 Wed 6/22/22
106 ZONE D 90 days Mon 3/7/22 Sat 6/4/22
107 External and Ancillary works 90 days Mon 3/7/22 Sat 6/4/22
108 ASSOCIATED MEP WORKS 225 days Tue 10/26/21 Tue 6/7/22
109 Associated MEP works 225 days Tue 10/26/21 Tue 6/7/22
110 HAND OVER AND ACCEPTANCE 15 days Thu 6/23/22 Thu 7/7/22
111 Handover and acceptance 15 days Thu 6/23/22 Thu 7/7/22

Page 1