You are on page 1of 2

WIRA GERED WATER SUPPLY PROJECT SCHEDULE

ID Task Name Duration Start Finish Nov '22 Dec '22 Jan '22 Feb '22 Mar '22 Apr '22 May '22 Jun '22 Jul '22
25 1 8 152229 6 132027 3 10172431 7 142128 7 142128 4 1118 25 2 9 162330 6 132027 4 111825
1 Water Point 120 days Wed 11/24/21 Thu 4/28/22
2 100m3 RCC reservoir 141 days Tue 11/2/21 Wed 5/4/22
3 Excavation 7 days Tue 11/2/21 Wed 11/10/21
4 Select fill 3 days Wed 11/10/21 Mon 11/15/21
5 Hard core fill 5 days Mon 11/15/21 Sat 11/20/21
6 Lean concrete 1 day Sat 11/20/21 Mon 11/22/21
7 Water curing 15 days Mon 11/22/21 Sat 12/11/21
8 Placing of Geo membrene 1 day Sat 12/11/21 Mon 12/13/21
9 Floor Slab Concrete Work 17 days Mon 12/13/21 Tue 1/4/22
10 Wall concrete work 25 days Tue 1/4/22 Sat 2/5/22
11 Water Curing 15 days Sat 2/5/22 Thu 2/24/22
12 Cheseling for plastering 7 days Fri 2/25/22 Mon 3/7/22
13 Plastering 9 days Mon 3/7/22 Thu 3/17/22
14 Roof Slab 21 days Thu 3/17/22 Thu 4/14/22
15 Water curing 7 days Thu 4/14/22 Fri 4/22/22
16 Roof slab scread 3 days Sat 4/23/22 Wed 4/27/22
17 Messilineous work 5 days Wed 4/27/22 Wed 5/4/22
18 V. Chamber for 100m3 service reservoir 22 days Fri 3/18/22 Fri 4/15/22
19 Spring Capping one 88 days Fri 1/21/22 Mon 5/16/22
20 Site Clearing 1 day Fri 1/21/22 Fri 1/21/22
21 Excavation & Spring spot collection 40 days Sat 1/22/22 Tue 3/15/22
22 Masonory work 14 days Wed 3/16/22 Sat 4/2/22
23 Spring box construction 3 days Mon 4/4/22 Thu 4/7/22
24 Gravel material collection and filling 7 days Mon 4/4/22 Tue 4/12/22
25 Roof slab concrete work 12 days Sat 4/23/22 Mon 5/9/22
26 Finishing work 5 days Tue 5/10/22 Mon 5/16/22
27 Pipe work only pressure line 36 days Wed 2/2/22 Tue 3/22/22
28 Excavation 11 days Wed 2/2/22 Wed 2/16/22
29 Pipe installation 25 days Thu 2/17/22 Tue 3/22/22
30 Back fill 22 days Fri 2/18/22 Fri 3/18/22
31 Pipe work for Distribution 51 days Thu 3/17/22 Mon 5/23/22
32 Excavation 11 days Thu 3/17/22 Thu 3/31/22
33 Pipe installation 18 days Thu 3/31/22 Sat 4/23/22
34 Back fill 22 days Sat 4/23/22 Mon 5/23/22
35 Valve chamber for distribution 24 days Tue 5/24/22 Thu 6/23/22
36 Anchore block 18 days Mon 4/25/22 Tue 5/17/22
37 Trust Block 14 days Wed 5/25/22 Sat 6/11/22
38 Generator and Guared House 57.31 days Mon 2/28/22 Thu 5/12/22
39 Site Clearing 1 day Mon 2/28/22 Tue 3/1/22

Task Milestone External Tasks


Project: Wira Gered work Schedule
Split Summary External Milestone
Date: Tue 2/22/22
Progress Project Summary Deadline

Page 1
WIRA GERED WATER SUPPLY PROJECT SCHEDULE
ID Task Name Duration Start Finish Nov '22 Dec '22 Jan '22 Feb '22 Mar '22 Apr '22 May '22 Jun '22 Jul '22
25 1 8 152229 6 132027 3 10172431 7 142128 7 142128 4 1118 25 2 9 162330 6 132027 4 111825
40 Excavation 7 days Tue 3/1/22 Wed 3/9/22
41 Masonory work 7 days Wed 3/9/22 Fri 3/18/22
42 Block work 8 days Sat 3/19/22 Wed 3/30/22
43 Concrete work 14 days Thu 3/31/22 Mon 4/18/22
44 Roof work 5 days Tue 4/19/22 Mon 4/25/22
45 Plastering 4 days Tue 4/26/22 Fri 4/29/22
46 Door and window fixing 2 days Sat 4/30/22 Tue 5/3/22
47 painting 1 day Wed 5/4/22 Wed 5/4/22
48 Pavment and fence work 6 days Thu 5/5/22 Thu 5/12/22
49 100m3 Concrete Reservoir for wet well 117 days Tue 2/22/22 Sat 7/23/22
50 Excavation 20 days Tue 2/22/22 Fri 3/18/22
51 Select fill 3 days Fri 3/18/22 Wed 3/23/22
52 Hard core fill 5 days Wed 3/23/22 Wed 3/30/22
53 Lean concrete 1 day Wed 3/30/22 Thu 3/31/22
54 Water curing 7 days Thu 3/31/22 Fri 4/8/22
55 Placing of Geo membrene 1 day Fri 4/8/22 Mon 4/11/22
56 Floor Slab Concrete Work 14 days Mon 4/11/22 Thu 4/28/22
57 Wall concrete work 21 days Thu 4/28/22 Thu 5/26/22
58 Water Curing 7 days Thu 5/26/22 Fri 6/3/22
59 Cheseling for plastering 7 days Fri 6/3/22 Mon 6/13/22
60 Plastering 9 days Tue 6/14/22 Fri 6/24/22
61 Roof Slab 7 days Fri 6/24/22 Mon 7/4/22
62 Water curing 7 days Mon 7/4/22 Wed 7/13/22
63 Roof slab scread 3 days Wed 7/13/22 Mon 7/18/22
64 Messilineous work 5 days Mon 7/18/22 Sat 7/23/22
65 V. Chamber for 100m3 wet well 22 days Thu 5/26/22 Thu 6/23/22
66 Electro Mechanical Work 30 days Thu 5/19/22 Mon 6/27/22

Task Milestone External Tasks


Project: Wira Gered work Schedule
Split Summary External Milestone
Date: Tue 2/22/22
Progress Project Summary Deadline

Page 2

You might also like