ID Task Mode Task Name Duration Start Finish 09 Oct '22 16 Oct '22 23 Oct '22 30 Oct '22

9 Oct '22 16 Oct '22 23 Oct '22 30 Oct '22 06 Nov '22 13 Nov '22
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
1 RENOVASI FUEL PUMP HOUSE
2 A. PEKERJAAN PERSIAPAN
3 Setting Bowplank 1 day Mon 10/10/22 Mon 10/10/22
4 B. PEKERJAAN PLAT PONDASI
5 Galian Tanah 3 days Mon 10/10/22 Wed 12/10/22
6 Urugan Pasir Urug 1 day Wed 12/10/22 Wed 12/10/22
7 Lantai Kerja 2 days Thu 13/10/22 Fri 14/10/22
8 Pembesian 3 days Fri 14/10/22 Tue 18/10/22
9 Begisting 5 days Sat 15/10/22 Thu 20/10/22
10 Pengecoran 2 days Fri 21/10/22 Mon 24/10/22
11 C. PEKERJAAN PEDESTAL
12 Pembesian 2 days Tue 18/10/22 Wed 19/10/22
13 Begisting 3 days Mon 24/10/22 Wed 26/10/22
14 Install Anchor 2 days Wed 26/10/22 Thu 27/10/22
15 Pengecoran 2 days Fri 28/10/22 Mon 31/10/22
16 Bongkar Begisting 1 day Tue 01/11/22 Tue 01/11/22
17 D. PEKERJAAN SLOOF
18 Galian Tanah 3 days Sat 22/10/22 Tue 25/10/22
19 Urugan Pasir Urug 1 day Mon 31/10/22 Mon 31/10/22
20 Lantai Kerja 2 days Tue 01/11/22 Wed 02/11/22
21 Pembesian 2 days Thu 03/11/22 Fri 04/11/22
22 Begisting 3 days Fri 04/11/22 Tue 08/11/22
23 Pengecoran 2 days Wed 09/11/22 Thu 10/11/22
24 Bongkar Begisting 1 day Sat 12/11/22 Sat 12/11/22
25 F. PEKERJAAN URUGAN
26 Urugan Kembali 2 days Sun 13/11/22 Mon 14/11/22
27 E. PEKERJAAN LANTAI
28 Pembesian 2 days Mon 14/11/22 Tue 15/11/22
29 Begisting 1 day Tue 15/11/22 Tue 15/11/22
30 Pengecoran 2 days Tue 15/11/22 Wed 16/11/22

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: Renovasi Fuel Pump Hous Split External Tasks Inactive Summary Manual Summary Progress
Date: Mon 10/10/22 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only