Tender 330-800-CN-CCC-0003 Pembangunan Belopa Facility

ID Task Task Name Duration Start Finish Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 PEMBANGUNAN BELOPA FACILITY 365 days Tue 01/11/22 Tue 31/10/23
2 CONTRAC AWARD 2 days Tue 01/11/22 Wed 02/11/22
3 Contract review dan penandatanganan kontrak 1 day Tue 01/11/22 Tue 01/11/22
4 Mobilization 1 day Wed 02/11/22 Wed 02/11/22
5 PEKERJAAN PERSIAPAN 27 days Wed 02/11/22 Mon 28/11/22
6 ADMINISTRASI, SOSIALISASI, PERIZINAN & TRAINING DAN APPROVAL 14 days Wed Tue
02/11/22 15/11/22
7 Reqruitment & Pengurusan perizinan Disnaker, BPJS TK & Kesehatan 7 days Wed Tue
02/11/22 08/11/22
8 Pengajuan pertemuan dengan Pemerintah setempat, Desa, Camat dll 3 days Wed Fri
02/11/22 04/11/22
9 Pengajuan nama2 calon pekerja, staff dan Pengawas 1 day Sat 05/11/22Sat 05/11/22
10 Sosialisasi & recruitment 1 day Sat 05/11/22Sat 05/11/22
11 Medical Check up (MCU), PM Check Kendaraan & Sticker 1 day Sun 06/11/22Sun 06/11/22
12 EHS approval untuk Training BST 3 days Mon 07/11/22 Wed 09/11/22
13 Request Badging & Approval dan General Induction/ GIP/ Badging 3 days Thu Sat
10/11/22 12/11/22
14 Permit to work ke sponsor termasuk Laydown area dan Pagar konstruksi 3 days Sun Tue
13/11/22 15/11/22
15 Pengajuan Risk Assesment (RA), JSA & SOP 6 days Thu 10/11/22 Tue 15/11/22
16 Site Set survey, Topography and Pemetaan 12 days Wed 16/11/22 Sun 27/11/22
17 Topography lokasi Facility Belopa 5 days Wed 16/11/22 Sun 20/11/22
18 Pemasangan patok dan area pagar lahan facility 5 days Wed 16/11/22 Sun 20/11/22
19 Proses gambar topo dan peta lokasi 7 days Mon 21/11/22 Sun 27/11/22
20 DED (Detail Engineering Drawing) 8 days Mon 21/11/22 Mon 28/11/22
21 Persiapan DED, Shop Drawing dan Material take off 6 days Mon 21/11/22 Sat 26/11/22
22 Pengajuan detail drawing/ fabrication drawings/ shop drawing & Material take 1 day Sun Sun
off 27/11/22 27/11/22
23 Approval by PT. MDA 1 day Mon 28/11/22 Mon 28/11/22
24 PROCUREMENT 60 days Tue 29/11/22 Fri 27/01/23
25 Quotation, Pembelian dan Transporatation material dari Vendor Lokal/Palopo/ 60 days Tue Fri
Makassar ke site/ Workshop 29/11/22 27/01/23
26 Mobilisasi Material & Alat dan Consumable – Lokal atau Luar Makassar/ Jkt / 60 days Tue Fri
Surabaya ke site 29/11/22 27/01/23
27 Report & approval by PT.MDA 60 days Tue 29/11/22 Fri 27/01/23
28 PERSIAPAN LOKASI/ LAHAN 10 days Tue 29/11/22 Thu 08/12/22
29 Persiapan lokasi Site office, Workshop & storage/ Laydown area di sekitar lokasi 10 days Tue Thu
Facility 29/11/22 08/12/22
30 Survey Topo, Pengukuran dan pemasangan patok 7 days Tue 29/11/22 Mon 05/12/22
31 Pemasangan temporary pagar konstruksi dan access masuk/ keluar material & pekerja3 serta
days lokasi
Tue 29/11/22
storage Thu 01/12/22
material dan Tools
32 Pemasangan safety sign, banner di area jalan masuk lokasi kerja 3 days Tue 29/11/22 Thu 01/12/22
33 Persiapan Flagman di jalan 10 days Tue 29/11/22 Thu 08/12/22
34 CONSTRUCTION/INSTALLATION WORK 319 days Tue 29/11/22 Fri 13/10/23
35 PEKERJAAN PEKERJAAN TANAH 24 days Fri 09/12/22Sun 01/01/23
36 Pekerjaan Clearing dan pembersihan lahan 5 days Fri 09/12/22Tue 13/12/22
37 Pengerukan top soil & hauling 14 days Wed 14/12/22 Tue 27/12/22
38 Mobilisasi tanah batuan setiap 30-50 cm menggunakan Dump Truck 14 days Wed 14/12/22 Tue 27/12/22
39 Pemadatan dengan menggunakan Compactor 14 days Wed 14/12/22 Tue 27/12/22
40 Compaction test dengan menggunakan alat CBR 3 days Wed 28/12/22 Fri 30/12/22

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline


Split External Tasks Inactive Summary Manual Summary Progress
Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only

PT. LYCON ASIA MANDIRI


Tender 330-800-CN-CCC-0003 Pembangunan Belopa Facility
ID Task Task Name Duration Start Finish Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
41 Report & Approval 24 days Fri 09/12/22Sun 01/01/23
42 FABRICATION WORK & PAINTING 66 days Tue 29/11/22Thu 02/02/23
43 Set up material dan Fabrication work 7 days Tue 29/11/22Mon 05/12/22
44 Menyiapkan WPS dan approval 14 days Tue 29/11/22Mon 12/12/22
45 Fit up dan pengelasan 60 days Tue 29/11/22Fri 27/01/23
46 Inspeksi NDT & WI 60 days Tue 29/11/22Fri 27/01/23
47 Menyiapkan pasir sand blasting, peralatan, tempat tertutup dll 7 days Tue 29/11/22Mon 05/12/22
48 Melakukan sand blasting semua steel structural 60 days Tue 29/11/22Fri 27/01/23
49 Check by QC 60 days Tue 29/11/22Fri 27/01/23
50 Spray Painting undercoat dan top coat 60 days Tue 29/11/22Fri 27/01/23
51 Check/ inspeski by QC ketebalan cat sesuai spec 60 days Tue 29/11/22Fri 27/01/23
52 Transportasi material ke lokasi lahan sesuai schedule pemasangan 60 days Tue 29/11/22Fri 27/01/23
53 Report & approval 66 days Tue 29/11/22Thu 02/02/23
54 PEKERJAAN REBAR DAN PONDASI, RING BETON/ SLOOF BETON & 40 days Wed Sun
LANTAI 28/12/22 05/02/23
55 Pengukuran dan pemasangan patok pagar beton/ bangunan 5 days Wed 28/12/22Sun 01/01/23
56 Persiapan bahan bouwplank, pengukuran dan pemasangan 4 days Wed 28/12/22Sat 31/12/22
57 Fabrikasi rebar dan bekisting/ formwork 5 days Sun 01/01/23Thu 05/01/23
58 Memastikan siku, elevasi dan kelurusan 5 days Wed 28/12/22Sun 01/01/23
59 Pemasangan bekesting/ formwork dan mengecek siku dan selimut beton 5 days Sun 01/01/23Thu 05/01/23
60 Menyiapkan campuran beton (slump test sesuai mutu beton), molen, 2 days Fri Sat
slump test dan Cylinder mould 150 dia x 300 06/01/23 07/01/23
61 Inspeksi by QC & tim project 35 days Sun 01/01/23Sat 04/02/23
62 Pengecoran & pemadatan dengan vibrator (Sample cilinder di test 7, 14 & 30 days
28 hari) Fri 06/01/23Sat 04/02/23
63 Backfilling dan pemadatan 5 days Wed 28/12/22Sun 01/01/23
64 Report & approval 40 days Wed 28/12/22Sun 05/02/23
65 PEKERJAAN KOLOM, DINDING, LANTAI & BETON DAN STEEL 78 days Sun Sun
STRUCTURAL 05/02/23 23/04/23
66 Pekerjaan Beton/ concrete & lantai (Group 1) 43 days Sun 05/02/23Sun 19/03/23
67 Pemasangan rebar vertical dan ties/ behel 5 days Sun 05/02/23Thu 09/02/23
68 Memastikan siku, elevasi dan kelurusan 5 days Sun 05/02/23Thu 09/02/23
69 Pemasangan bekesting/ formwork dan mengecek siku dan selimut beton7 days Sun 05/02/23Sat 11/02/23
70 Menyiapkan campuran beton (sesuai mutu beton), molen, slump test 2 days Sun Mon
dan Cylinder mould 12/02/23 13/02/23
71 Inspeksi by QC dan tim project 43 days Sun 05/02/23Sun 19/03/23
72 Pengecoran kolom beton (Slump test sesuai mutu beton) & pemadatan 2 days Tue Wed
dengan vibrator 14/02/23 15/02/23
73 Curing time 30 days Thu 16/02/23Fri 17/03/23
74 Report & approval 43 days Sun 05/02/23Sun 19/03/23
75 Pekerjaan pemasangan dinding batu merah/ batako (Group 2) 16 days Thu 16/02/23Fri 03/03/23
76 Pengukuran dan pemasangan laser 2 days Thu 16/02/23Fri 17/02/23
77 Pemasangan dinding bata campuran 1:3, memastikan siku, level dan 14 days Sat Fri
kelurusann 18/02/23 03/03/23
78 Plesteran dinding bata 7 days Sat 18/02/23Fri 24/02/23
79 Peng-acian 5 days Sat 18/02/23Wed 22/02/23
80 Report & approval 16 days Thu 16/02/23Fri 03/03/23
81 Pekerjaan erection steel stuctural 27 days Sat 04/03/23Thu 30/03/23
82 Menyiapakan alat, scaffolding, Crane untuk Lifting & erection dan 10 days Sat Mon
melakukan sertifikasi & approval 04/03/23 13/03/23

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline


Split External Tasks Inactive Summary Manual Summary Progress
Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only

PT. LYCON ASIA MANDIRI


Tender 330-800-CN-CCC-0003 Pembangunan Belopa Facility
ID Task Task Name Duration Start Finish Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
83 Menyiapkan sign dan barikade 5 days Sat 04/03/23Wed 08/03/23
84 Pemasangan scaffolding dan planks dan tangga 5 days Thu 09/03/23Mon 13/03/23
85 Pre-assembly, Pengangkatan, erection dan pemasangan rangka 7 days Tue Mon
structural & Tower 14/03/23 20/03/23
86 Pastikan semua alat sudah di inspeksi dan pekerja menggunakan 7 days Tue Mon
fullbody harnes 14/03/23 20/03/23
87 Fit up strutural, cleat dan plates 7 days Tue 21/03/23Mon 27/03/23
88 Pengelasan 7 days Tue 21/03/23Mon 27/03/23
89 Inspeksi QC & Tim Project 27 days Sat 04/03/23Thu 30/03/23
90 Touck up paint 3 days Tue 28/03/23Thu 30/03/23
91 Report & Approval 27 days Sat 04/03/23Thu 30/03/23
92 Pekerjaan pemasangan rangka dinding/ kosen pintu (Group 3) 24 days Fri 31/03/23Sun 23/04/23
93 Menyiapkan rangka/ kosen pintu dan jendela/ ventilasi 10 days Fri Sun
31/03/23 09/04/23
94 Siapkan stud untuk pemasangan rangka 10 days Fri 31/03/23Sun 09/04/23
95 Pemasangan sesuai level/ elevasi/ ketinggian dan siku/ kelurusan 14 days Mon 10/04/23Sun 23/04/23
96 Pemasangan stud dll dan melepas stus jika sudah selesai 14 days Mon 10/04/23Sun 23/04/23
97 Report & approval 24 days Fri 31/03/23Sun 23/04/23
98 PEKERJAAN RANGKA ATAP & ATAP 34 days Mon 24/04/23 Sat 27/05/23
99 Menyiapkan alat angkat 10 days Mon 24/04/23Wed 03/05/23
100 Menyiapkan material dan safety sign/ barikade 10 days Mon 24/04/23Wed 03/05/23
101 Pengangkatan rangka atap 7 days Thu 04/05/23
Wed 10/05/23
102 Pemasangan dan fit up serta pengelasan 5 days Thu 11/05/23Mon 15/05/23
103 Inspesksi QC & Tip Project 34 days Mon 24/04/23Sat 27/05/23
104 Touch up paint 5 days Tue 16/05/23Sat 20/05/23
105 Pemasangan atap dan bubungan/ top ridge 7 days Sun 21/05/23
Sat 27/05/23
106 Report & approval 34 days Mon 24/04/23Sat 27/05/23
107 PEKERJAAN PEMIPAAN & HYDROTEST 187 days Wed 01/03/23Sun 03/09/23
108 Menyiapkan peralatan, material pipa, fitting, connector dll termasuk bracket30pipe
days Wed 01/03/23Thu 30/03/23
109 30 days
Menentukan titik pemasangan, jalur pipa, penggalian underground dan overhead Fri 31/03/23Sat 29/04/23
110 Penggalian jalur pipa & pemasangan lengkap marking pipe 90 days Sun 30/04/23Fri 28/07/23
111 Pemasangan dan pengelasan pipe bracket untuk overhead pipe 120 days Sun 30/04/23Sun 27/08/23
112 Pemasangan pipa, lengkap konektor, valve dan marking 120 days Sun 30/04/23Sun 27/08/23
113 Pemasangan fiting2 pipa 120 days Sun 30/04/23Sun 27/08/23
114 Melakukan hydrotest/ Test kebocoran 5 days Mon 28/08/23Fri 01/09/23
115 Witnes dan Inspeksi by QC dan Inspector MDA 187 days Wed 01/03/23Sun 03/09/23
116 Tie-in 2 days Sat 02/09/23Sun 03/09/23
117 Report & approval 187 days Wed 01/03/23Sun 03/09/23
118 PEKERJAAN ELEKTRIKAL, LAN, AC, CCTV KONEKSI & TIE-IN 200 days Wed 01/03/23Sat 16/09/23
119 Marking dan penentuan jalur kabel dan titik fitting 30 days Wed 01/03/23Thu 30/03/23
120 Penarikan kabel (Underground cable di beri marking pada jalurnya) 90 days Fri 31/03/23Wed 28/06/23
121 Pemasangan stop kontak dan saklar 40 days Fri 31/03/23Tue 09/05/23
122 Pemasangan kabel LAN, Telp, CCTV, listrik/ lampu dll 40 days Fri 31/03/23Tue 09/05/23
123 Pemasangan U/G Cable dan Lampu taman 40 days Fri 31/03/23Tue 09/05/23
124 Connection/ tie-in ke PLN 10 days Wed 10/05/23Fri 19/05/23
125 Test & commissioning; Lampu, AC, dll 14 days Sat 20/05/23Fri 02/06/23
126 Report & approval 200 days Wed 01/03/23Sat 16/09/23
127 PEKERJAAN FINISHING/ PENGECATAN DINDING 161 days Sat 04/03/23Fri 11/08/23
128 Melakukan persiapan dan pembersihan area pengecatan 90 days Sat 04/03/23Thu 01/06/23
Task Project Summary Inactive Milestone Manual Summary Rollup Deadline
Split External Tasks Inactive Summary Manual Summary Progress
Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only

PT. LYCON ASIA MANDIRI


Tender 330-800-CN-CCC-0003 Pembangunan Belopa Facility
ID Task Task Name Duration Start Finish Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
129 Pemasangan Scaffolding & tangga 90 days Mon 03/04/23Sat 01/07/23
130 Melakukan pengecatan dasar/ undercoat dan inspeksi 30 days Mon 19/06/23Tue 18/07/23
131 Melakukan pengecatan top coat 25 days Mon 03/07/23Thu 27/07/23
132 Finishing dan pembersiahan 40 days Mon 03/07/23Fri 11/08/23
133 PEMASANGAN PINTU DAN JENDELA (MATERIAL PAPAN/ BAJA 65 days Mon Tue
RINGAN & UVPC) 24/04/23 27/06/23
134 Persiapan material dan pengukuran ulang 30 days Mon 24/04/23Tue 23/05/23
135 Pemasangan daun pintu, jendela dan engsel dll 60 days Mon 24/04/23Thu 22/06/23
136 Test & inspeksi QC dan Inspector MDA 65 days Mon 24/04/23
Tue 27/06/23
137 Report & Approval 65 days Mon 24/04/23Tue 27/06/23
138 PEKERJAAN PEDESTRIAN, WALKWAY & PAVING BLOCK 285 days Mon 02/01/23 Fri 13/10/23
139 Persiapan dan pemasangan subgrade, Grading & compaction 250 days Mon 02/01/23 Fri 08/09/23
140 Compaction test 250 days Mon 09/01/23
Fri 15/09/23
141 Pengukuran & Pemasangan patok dan benang, elevasi dan siku/ bouwplank250
dlldays Wed 11/01/23Sun 17/09/23
142 Pemasangan sharing/ formwork atau batas walkway atau jalan 250 days Mon 16/01/23 Fri 22/09/23
143 Hampar kerikil, chipseal dan Aspal dan sealing jalan 250 days Mon 23/01/23 Fri 29/09/23
144 Pemasangan paving block untuk walkway 250 days Mon 30/01/23 Fri 06/10/23
145 Pengecekan & inspeksi kepadatan paving 250 days Mon 06/02/23 Fri 13/10/23
146 Penaburan pasir 250 days Mon 06/02/23 Fri 13/10/23
147 Report & approval 285 days Mon 02/01/23 Fri 13/10/23
148 PEKERJAAN FINISHING/ SELESAI 322 days Wed 14/12/22 Tue 31/10/23
149 Pembersihan seluruh area kerja 310 days Wed 14/12/22 Thu 19/10/23
150 Pengecekan seluruh pekerjaan 310 days Wed 21/12/22 Thu 26/10/23
151 Commissioning 30 days Fri 29/09/23Sat 28/10/23
152 Handover 3 days Sun 29/10/23Tue 31/10/23
153 Demobilization 320 days Wed 14/12/22 Sun 29/10/23

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline


Split External Tasks Inactive Summary Manual Summary Progress
Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only

PT. LYCON ASIA MANDIRI