ID Task Task Name Duration Start Finish Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023
Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 PEMBANGUNAN BELOPA FACILITY 365 days Tue 01/11/22 Tue 31/10/23
2 CONTRAC AWARD 2 days Tue 01/11/22 Wed 02/11/22
3 Contract review dan penandatanganan kontrak 1 day Tue 01/11/22 Tue 01/11/22
4 Mobilization 1 day Wed 02/11/22 Wed 02/11/22
5 PEKERJAAN PERSIAPAN 27 days Wed 02/11/22 Mon 28/11/22
6 ADMINISTRASI, SOSIALISASI, PERIZINAN & TRAINING DAN APPROVAL 14 days Wed Tue
02/11/22 15/11/22
7 Reqruitment & Pengurusan perizinan Disnaker, BPJS TK & Kesehatan 7 days Wed Tue
02/11/22 08/11/22
8 Pengajuan pertemuan dengan Pemerintah setempat, Desa, Camat dll 3 days Wed Fri
02/11/22 04/11/22
9 Pengajuan nama2 calon pekerja, staff dan Pengawas 1 day Sat 05/11/22Sat 05/11/22
10 Sosialisasi & recruitment 1 day Sat 05/11/22Sat 05/11/22
11 Medical Check up (MCU), PM Check Kendaraan & Sticker 1 day Sun 06/11/22Sun 06/11/22
12 EHS approval untuk Training BST 3 days Mon 07/11/22 Wed 09/11/22
13 Request Badging & Approval dan General Induction/ GIP/ Badging 3 days Thu Sat
10/11/22 12/11/22
14 Permit to work ke sponsor termasuk Laydown area dan Pagar konstruksi 3 days Sun Tue
13/11/22 15/11/22
15 Pengajuan Risk Assesment (RA), JSA & SOP 6 days Thu 10/11/22 Tue 15/11/22
16 Site Set survey, Topography and Pemetaan 12 days Wed 16/11/22 Sun 27/11/22
17 Topography lokasi Facility Belopa 5 days Wed 16/11/22 Sun 20/11/22
18 Pemasangan patok dan area pagar lahan facility 5 days Wed 16/11/22 Sun 20/11/22
19 Proses gambar topo dan peta lokasi 7 days Mon 21/11/22 Sun 27/11/22
20 DED (Detail Engineering Drawing) 8 days Mon 21/11/22 Mon 28/11/22
21 Persiapan DED, Shop Drawing dan Material take off 6 days Mon 21/11/22 Sat 26/11/22
22 Pengajuan detail drawing/ fabrication drawings/ shop drawing & Material take 1 day Sun Sun
off 27/11/22 27/11/22
23 Approval by PT. MDA 1 day Mon 28/11/22 Mon 28/11/22
24 PROCUREMENT 60 days Tue 29/11/22 Fri 27/01/23
25 Quotation, Pembelian dan Transporatation material dari Vendor Lokal/Palopo/ 60 days Tue Fri
Makassar ke site/ Workshop 29/11/22 27/01/23
26 Mobilisasi Material & Alat dan Consumable – Lokal atau Luar Makassar/ Jkt / 60 days Tue Fri
Surabaya ke site 29/11/22 27/01/23
27 Report & approval by PT.MDA 60 days Tue 29/11/22 Fri 27/01/23
28 PERSIAPAN LOKASI/ LAHAN 10 days Tue 29/11/22 Thu 08/12/22
29 Persiapan lokasi Site office, Workshop & storage/ Laydown area di sekitar lokasi 10 days Tue Thu
Facility 29/11/22 08/12/22
30 Survey Topo, Pengukuran dan pemasangan patok 7 days Tue 29/11/22 Mon 05/12/22
31 Pemasangan temporary pagar konstruksi dan access masuk/ keluar material & pekerja3 serta
days lokasi
Tue 29/11/22
storage Thu 01/12/22
material dan Tools
32 Pemasangan safety sign, banner di area jalan masuk lokasi kerja 3 days Tue 29/11/22 Thu 01/12/22
33 Persiapan Flagman di jalan 10 days Tue 29/11/22 Thu 08/12/22
34 CONSTRUCTION/INSTALLATION WORK 319 days Tue 29/11/22 Fri 13/10/23
35 PEKERJAAN PEKERJAAN TANAH 24 days Fri 09/12/22Sun 01/01/23
36 Pekerjaan Clearing dan pembersihan lahan 5 days Fri 09/12/22Tue 13/12/22
37 Pengerukan top soil & hauling 14 days Wed 14/12/22 Tue 27/12/22
38 Mobilisasi tanah batuan setiap 30-50 cm menggunakan Dump Truck 14 days Wed 14/12/22 Tue 27/12/22
39 Pemadatan dengan menggunakan Compactor 14 days Wed 14/12/22 Tue 27/12/22
40 Compaction test dengan menggunakan alat CBR 3 days Wed 28/12/22 Fri 30/12/22