WORK SCHEDULE FOR NIGALO BOUTIQUE RESORT

ID Task Name Duration Start Finish Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
0 WORK SCHEDULE FOR NIGALO BOUTIQUE RESORT 459 days Mon 11/15/21 Thu 2/16/23
1 1 CIVIL WORK 459 days Mon 11/15/21 Thu 2/16/23
2 1.1 CIVIL WORK BLOCK C & D 162 days Mon 11/15/21 Mon 4/25/22
3 1.1.1 Site mobilization & site clearence & boring work 21 days Mon 11/15/21 Sun 12/5/21
4 1.1.2 Basement 65 days Mon 12/6/21 Tue 2/8/22
5 1.1.2.1 Foundation 37 days Mon 12/6/21 Tue 1/11/22
6 1.1.2.1.1 Earthwork in excavation 20 days Mon 12/6/21 Sat 12/25/21 12/6 12/25
7 1.1.2.1.2 Protection work for earthwork 7 days Sun 12/19/21 Sat 12/25/21 12/19 12/25
8 1.1.2.1.3 Soling work 3 days Sun 12/26/21 Tue 12/28/21 12/26 12/28
9 1.1.2.1.4 PCC work 2 days Wed 12/29/21 Thu 12/30/21 12/29 12/30
10 1.1.2.1.5 Raft Rebar work including formwork 9 days Fri 12/31/21 Sat 1/8/22 12/31 1/8
11 1.1.2.1.6 concreting work 3 days Sun 1/9/22 Tue 1/11/22 1/9 1/11
12 1.1.2.2 Shear wall & coloumn work 13 days Wed 1/12/22 Mon 1/24/22
13 1.1.2.2.1 Rebar works 4 days Wed 1/12/22 Sat 1/15/22 1/12 1/15
14 1.1.2.2.2 Formwork 6 days Sun 1/16/22 Fri 1/21/22 1/16 1/21
15 1.1.2.2.3 Concreting work 3 days Sat 1/22/22 Mon 1/24/22 1/22 1/24
16 1.1.2.3 Basement cover slab ( ground floor slab) 15 days Tue 1/25/22 Tue 2/8/22
17 1.1.2.3.1 Form work 7 days Tue 1/25/22 Mon 1/31/22 1/25 1/31
18 1.1.2.3.2 rebar 7 days Tue 2/1/22 Mon 2/7/22 2/1 2/7
19 1.1.2.3.3 concreting work 1 day Tue 2/8/22 Tue 2/8/22 2/8 2/8
20 1.1.3 Super structure work col/beam/slab 76 days Wed 2/9/22 Mon 4/25/22
21 1.1.3.1 Ground floor work 19 days Wed 2/9/22 Sun 2/27/22
22 1.1.3.1.1 Coloumn rebar work 3 days Wed 2/9/22 Fri 2/11/22 2/9 2/11
23 1.1.3.1.2 Coloumn form work 2 days Sat 2/12/22 Sun 2/13/22 2/12 2/13
24 1.1.3.1.3 Coloumn concrete work 1 day Mon 2/14/22 Mon 2/14/22 2/14 2/14
25 1.1.3.1.4 Slab form work 6 days Tue 2/15/22 Sun 2/20/22 2/15 2/20
26 1.1.3.1.5 Slab rebar work 6 days Mon 2/21/22 Sat 2/26/22 2/21 2/26
27 1.1.3.1.6 Slab concreting work 1 day Sun 2/27/22 Sun 2/27/22 2/27 2/27
28 1.1.3.2 First floor work 19 days Mon 2/28/22 Fri 3/18/22
29 1.1.3.2.1 Coloumn rebar work 3 days Mon 2/28/22 Wed 3/2/22 2/28 3/2
30 1.1.3.2.2 Coloumn form work 2 days Thu 3/3/22 Fri 3/4/22 3/3 3/4
31 1.1.3.2.3 Coloumn concrete work 1 day Sat 3/5/22 Sat 3/5/22 3/5 3/5
32 1.1.3.2.4 Slab form work 6 days Sun 3/6/22 Fri 3/11/22 3/6 3/11
33 1.1.3.2.5 Slab rebar work 6 days Sat 3/12/22 Thu 3/17/22 3/12 3/17
34 1.1.3.2.6 Slab concreting work 1 day Fri 3/18/22 Fri 3/18/22 3/18 3/18
35 1.1.3.3 Second floor work 19 days Sat 3/19/22 Wed 4/6/22
36 1.1.3.3.1 Coloumn rebar work 3 days Sat 3/19/22 Mon 3/21/22 3/19 3/21
37 1.1.3.3.2 Coloumn form work 2 days Tue 3/22/22 Wed 3/23/22 3/22 3/23
38 1.1.3.3.3 Coloumn concrete work 1 day Thu 3/24/22 Thu 3/24/22 3/24 3/24
39 1.1.3.3.4 Slab form work 6 days Fri 3/25/22 Wed 3/30/22 3/25 3/30
40 1.1.3.3.5 Slab rebar work 6 days Thu 3/31/22 Tue 4/5/22 3/31 4/5
41 1.1.3.3.6 Slab concreting work 1 day Wed 4/6/22 Wed 4/6/22 4/6 4/6
42 1.1.3.4 Third floor work 19 days Thu 4/7/22 Mon 4/25/22
43 1.1.3.4.1 Coloumn rebar work 3 days Thu 4/7/22 Sat 4/9/22 4/7 4/9
44 1.1.3.4.2 Coloumn form work 2 days Sun 4/10/22 Mon 4/11/22 4/10 4/11
45 1.1.3.4.3 Coloumn concrete work 1 day Tue 4/12/22 Tue 4/12/22 4/12 4/12
46 1.1.3.4.4 Beam form work 6 days Wed 4/13/22 Mon 4/18/22 4/13 4/18
47 1.1.3.4.5 Beam rebar work 6 days Tue 4/19/22 Sun 4/24/22 4/19 4/24
48 1.1.3.4.6 Beam concreting work 1 day Mon 4/25/22 Mon 4/25/22 4/25 4/25
49

Task Rolled Up Progress Inactive Milestone Manual Summary Progress


Milestone Split Inactive Summary Start-only Deadline
Project: RESORT BUILDING AT NAGARKOT 1
Date:OCT 20,2021 Summary External Tasks Manual Task Finish-only
Rolled Up Task Project Summary Duration-only External Tasks
Rolled Up Milestone Group By Summary Manual Summary Rollup External Milestone

Prepared by: Rakesh Lamsal for SARGA:


WORK SCHEDULE FOR NIGALO BOUTIQUE RESORT
ID Task Name Duration Start Finish Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
50
51 1.2 CIVIL WORK BLOCK B 61 days Fri 8/26/22 Tue 10/25/22
52 1.2.1 Sub-structure work 23 days Fri 8/26/22 Sat 9/17/22
53 1.2.1.1 Foundation 13 days Fri 8/26/22 Wed 9/7/22
54 1.2.1.1.1 Earthwork in excavation 5 days Fri 8/26/22 Tue 8/30/22 8/26 8/30
55 1.2.1.1.2 Soling work 2 days Wed 8/31/22 Thu 9/1/22 8/31 9/1
56 1.2.1.1.3 PCC work 1 day Fri 9/2/22 Fri 9/2/22 9/2 9/2
57 1.2.1.1.4 Raft Rebar work including formwork 3 days Sat 9/3/22 Mon 9/5/22 9/3 9/5
58 1.2.1.1.5 concreting work 2 days Tue 9/6/22 Wed 9/7/22 9/6 9/7
59 1.2.1.2 Up to PL level 10 days Thu 9/8/22 Sat 9/17/22
60 1.2.1.2.1 All complete work up to pl level 10 days Thu 9/8/22 Sat 9/17/22 9/8 9/17
61 1.2.2 Super structure work col/beam/slab 38 days Sun 9/18/22 Tue 10/25/22
62 1.2.2.1 Ground floor work 19 days Sun 9/18/22 Thu 10/6/22
63 1.2.2.1.1 Coloumn rebar work 3 days Sun 9/18/22 Tue 9/20/22 9/18 9/20
64 1.2.2.1.2 Coloumn form work 2 days Wed 9/21/22 Thu 9/22/22 9/21 9/22
65 1.2.2.1.3 Coloumn concrete work 1 day Fri 9/23/22 Fri 9/23/22 9/23 9/23
66 1.2.2.1.4 Slab form work 6 days Sat 9/24/22 Thu 9/29/22 9/24 9/29
67 1.2.2.1.5 Slab rebar work 6 days Fri 9/30/22 Wed 10/5/22 9/30 10/5
68 1.2.2.1.6 Slab concreting work 1 day Thu 10/6/22 Thu 10/6/22 10/6 10/6
69 1.2.2.2 First floor work 19 days Fri 10/7/22 Tue 10/25/22
70 1.2.2.2.1 Coloumn rebar work 3 days Fri 10/7/22 Sun 10/9/22 10/7 10/9
71 1.2.2.2.2 Coloumn form work 2 days Mon 10/10/22 Tue 10/11/22 10/10 10/11
72 1.2.2.2.3 Coloumn concrete work 1 day Wed 10/12/22 Wed 10/12/22 10/12 10/12
73 1.2.2.2.4 Slab form work 6 days Thu 10/13/22 Tue 10/18/22 10/13 10/18
74 1.2.2.2.5 Slab rebar work 6 days Wed 10/19/22 Mon 10/24/22 10/19 10/24
75 1.2.2.2.6 Slab concreting work 1 day Tue 10/25/22 Tue 10/25/22 10/25 10/25
76
77 1.3 CIVIL WORK BLOCK A 160 days Tue 4/26/22 Sun 10/2/22
78 1.3.1 Basement 65 days Tue 4/26/22 Wed 6/29/22
79 1.3.1.1 Foundation 37 days Tue 4/26/22 Wed 6/1/22
80 1.3.1.1.1 Earthwork in excavation 20 days Tue 4/26/22 Sun 5/15/22 4/26 5/15
81 1.3.1.1.2 Protection work for earthwork 7 days Mon 5/9/22 Sun 5/15/22 5/9 5/15
82 1.3.1.1.3 Soling work 3 days Mon 5/16/22 Wed 5/18/22 5/16 5/18
83 1.3.1.1.4 PCC work 2 days Thu 5/19/22 Fri 5/20/22 5/19 5/20
84 1.3.1.1.5 Raft Rebar work including formwork 9 days Sat 5/21/22 Sun 5/29/22 5/21 5/29
85 1.3.1.1.6 concreting work 3 days Mon 5/30/22 Wed 6/1/22 5/30 6/1
86 1.3.1.2 Shear wall & coloumn work 13 days Thu 6/2/22 Tue 6/14/22
87 1.3.1.2.1 Rebar works 4 days Thu 6/2/22 Sun 6/5/22 6/2 6/5
88 1.3.1.2.2 Formwork 6 days Mon 6/6/22 Sat 6/11/22 6/6 6/11
89 1.3.1.2.3 Concreting work 3 days Sun 6/12/22 Tue 6/14/22 6/12 6/14
90 1.3.1.3 Basement cover slab ( ground floor slab) 15 days Wed 6/15/22 Wed 6/29/22
91 1.3.1.3.1 Form work 7 days Wed 6/15/22 Tue 6/21/22 6/15 6/21
92 1.3.1.3.2 rebar 7 days Wed 6/22/22 Tue 6/28/22 6/22 6/28
93 1.3.1.3.3 concreting work 1 day Wed 6/29/22 Wed 6/29/22 6/29 6/29
94 1.3.2 Super structure work col/beam/slab 95 days Thu 6/30/22 Sun 10/2/22
95 1.3.2.1 Ground floor work 19 days Thu 6/30/22 Mon 7/18/22
96 1.3.2.1.1 Coloumn rebar work 3 days Thu 6/30/22 Sat 7/2/22 6/30 7/2
97 1.3.2.1.2 Coloumn form work 2 days Sun 7/3/22 Mon 7/4/22 7/3 7/4
98 1.3.2.1.3 Coloumn concrete work 1 day Tue 7/5/22 Tue 7/5/22 7/5 7/5
99 1.3.2.1.4 Slab form work 6 days Wed 7/6/22 Mon 7/11/22 7/6 7/11

Task Rolled Up Progress Inactive Milestone Manual Summary Progress


Milestone Split Inactive Summary Start-only Deadline
Project: RESORT BUILDING AT NAGARKOT 2
Date:OCT 20,2021 Summary External Tasks Manual Task Finish-only
Rolled Up Task Project Summary Duration-only External Tasks
Rolled Up Milestone Group By Summary Manual Summary Rollup External Milestone

Prepared by: Rakesh Lamsal for SARGA:


WORK SCHEDULE FOR NIGALO BOUTIQUE RESORT
ID Task Name Duration Start Finish Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
100 1.3.2.1.5 Slab rebar work 6 days Tue 7/12/22 Sun 7/17/22 7/12 7/17
101 1.3.2.1.6 Slab concreting work 1 day Mon 7/18/22 Mon 7/18/22 7/18 7/18
102 1.3.2.2 First floor work 19 days Tue 7/19/22 Sat 8/6/22
103 1.3.2.2.1 Coloumn rebar work 3 days Tue 7/19/22 Thu 7/21/22 7/19 7/21
104 1.3.2.2.2 Coloumn form work 2 days Fri 7/22/22 Sat 7/23/22 7/22 7/23
105 1.3.2.2.3 Coloumn concrete work 1 day Sun 7/24/22 Sun 7/24/22 7/24 7/24
106 1.3.2.2.4 Slab form work 6 days Mon 7/25/22 Sat 7/30/22 7/25 7/30
107 1.3.2.2.5 Slab rebar work 6 days Sun 7/31/22 Fri 8/5/22 7/31 8/5
108 1.3.2.2.6 Slab concreting work 1 day Sat 8/6/22 Sat 8/6/22 8/6 8/6
109 1.3.2.3 Second floor work 19 days Sun 8/7/22 Thu 8/25/22
110 1.3.2.3.1 Coloumn rebar work 3 days Sun 8/7/22 Tue 8/9/22 8/7 8/9
111 1.3.2.3.2 Coloumn form work 2 days Wed 8/10/22 Thu 8/11/22 8/10 8/11
112 1.3.2.3.3 Coloumn concrete work 1 day Fri 8/12/22 Fri 8/12/22 8/12 8/12
113 1.3.2.3.4 Slab form work 6 days Sat 8/13/22 Thu 8/18/22 8/13 8/18
114 1.3.2.3.5 Slab rebar work 6 days Fri 8/19/22 Wed 8/24/22 8/19 8/24
115 1.3.2.3.6 Slab concreting work 1 day Thu 8/25/22 Thu 8/25/22 8/25 8/25
116 1.3.2.4 Third floor work 19 days Fri 8/26/22 Tue 9/13/22
117 1.3.2.4.1 Coloumn rebar work 3 days Fri 8/26/22 Sun 8/28/22 8/26 8/28
118 1.3.2.4.2 Coloumn form work 2 days Mon 8/29/22 Tue 8/30/22 8/29 8/30
119 1.3.2.4.3 Coloumn concrete work 1 day Wed 8/31/22 Wed 8/31/22 8/31 8/31
120 1.3.2.4.4 Slab form work 6 days Thu 9/1/22 Tue 9/6/22 9/1 9/6
121 1.3.2.4.5 Slab rebar work 6 days Wed 9/7/22 Mon 9/12/22 9/7 9/12
122 1.3.2.4.6 Slab concreting work 1 day Tue 9/13/22 Tue 9/13/22 9/13 9/13
123 1.3.2.5 Fourth floor work 19 days Wed 9/14/22 Sun 10/2/22
124 1.3.2.5.1 Coloumn rebar work 3 days Wed 9/14/22 Fri 9/16/22 9/14 9/16
125 1.3.2.5.2 Coloumn form work 2 days Sat 9/17/22 Sun 9/18/22 9/17 9/18
126 1.3.2.5.3 Coloumn concrete work 1 day Mon 9/19/22 Mon 9/19/22 9/19 9/19
127 1.3.2.5.4 Beam form work 6 days Tue 9/20/22 Sun 9/25/22 9/20 9/25
128 1.3.2.5.5 Beam rebar work 6 days Mon 9/26/22 Sat 10/1/22 9/26 10/1
129 1.3.2.5.6 Beam concreting work 1 day Sun 10/2/22 Sun 10/2/22 10/2 10/2
130
131 1.4 General finishing work 98 days Thu 11/10/22 Wed 2/15/23
132 1.4.1 Block B 25 days Thu 11/10/22 Sun 12/4/22
133 1.4.1.1 All complete brick work for block B 20 days Tue 11/15/22 Sun 12/4/22 11/15 12/4
134 1.4.1.2 All complete plaster work for block B 7 days Thu 11/10/22 Wed 11/16/22 11/10 11/16
135 1.4.1.3 All complete IPS work for block B 3 days Thu 11/17/22 Sat 11/19/22 11/17 11/19
136 1.4.2 Block C & D 98 days Thu 11/10/22 Wed 2/15/23
137 1.4.2.1 All complete brick work for block C & D 60 days Thu 11/10/22 Sun 1/8/23 11/10 1/8
138 1.4.2.2 All complete plaster work for block C & D 26 days Mon 1/9/23 Fri 2/3/23 1/9 2/3
139 1.4.2.3 All complete IPS work for block C & D 12 days Sat 2/4/23 Wed 2/15/23 2/4 2/15
140 1.4.3 Block A 98 days Thu 11/10/22 Wed 2/15/23
141 1.4.3.1 All complete brick work for block C & D 60 days Thu 11/10/22 Sun 1/8/23 11/10 1/8
142 1.4.3.2 All complete plaster work for block C & D 26 days Mon 1/9/23 Fri 2/3/23 1/9 2/3
143 1.4.3.3 All complete IPS work for block C & D 12 days Sat 2/4/23 Wed 2/15/23 2/4 2/15
144
145 1.5 Handover 1 day Thu 2/16/23 Thu 2/16/23
146 1.5.1 Handover 1 day Thu 2/16/23 Thu 2/16/23 2/16 2/16

Task Rolled Up Progress Inactive Milestone Manual Summary Progress


Milestone Split Inactive Summary Start-only Deadline
Project: RESORT BUILDING AT NAGARKOT 3
Date:OCT 20,2021 Summary External Tasks Manual Task Finish-only
Rolled Up Task Project Summary Duration-only External Tasks
Rolled Up Milestone Group By Summary Manual Summary Rollup External Milestone

Prepared by: Rakesh Lamsal for SARGA: