Professional Documents
Culture Documents
ID Task Name Duration Start Finish Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
0 WORK SCHEDULE FOR NIGALO BOUTIQUE RESORT 459 days Mon 11/15/21 Thu 2/16/23
1 1 CIVIL WORK 459 days Mon 11/15/21 Thu 2/16/23
2 1.1 CIVIL WORK BLOCK C & D 162 days Mon 11/15/21 Mon 4/25/22
3 1.1.1 Site mobilization & site clearence & boring work 21 days Mon 11/15/21 Sun 12/5/21
4 1.1.2 Basement 65 days Mon 12/6/21 Tue 2/8/22
5 1.1.2.1 Foundation 37 days Mon 12/6/21 Tue 1/11/22
6 1.1.2.1.1 Earthwork in excavation 20 days Mon 12/6/21 Sat 12/25/21 12/6 12/25
7 1.1.2.1.2 Protection work for earthwork 7 days Sun 12/19/21 Sat 12/25/21 12/19 12/25
8 1.1.2.1.3 Soling work 3 days Sun 12/26/21 Tue 12/28/21 12/26 12/28
9 1.1.2.1.4 PCC work 2 days Wed 12/29/21 Thu 12/30/21 12/29 12/30
10 1.1.2.1.5 Raft Rebar work including formwork 9 days Fri 12/31/21 Sat 1/8/22 12/31 1/8
11 1.1.2.1.6 concreting work 3 days Sun 1/9/22 Tue 1/11/22 1/9 1/11
12 1.1.2.2 Shear wall & coloumn work 13 days Wed 1/12/22 Mon 1/24/22
13 1.1.2.2.1 Rebar works 4 days Wed 1/12/22 Sat 1/15/22 1/12 1/15
14 1.1.2.2.2 Formwork 6 days Sun 1/16/22 Fri 1/21/22 1/16 1/21
15 1.1.2.2.3 Concreting work 3 days Sat 1/22/22 Mon 1/24/22 1/22 1/24
16 1.1.2.3 Basement cover slab ( ground floor slab) 15 days Tue 1/25/22 Tue 2/8/22
17 1.1.2.3.1 Form work 7 days Tue 1/25/22 Mon 1/31/22 1/25 1/31
18 1.1.2.3.2 rebar 7 days Tue 2/1/22 Mon 2/7/22 2/1 2/7
19 1.1.2.3.3 concreting work 1 day Tue 2/8/22 Tue 2/8/22 2/8 2/8
20 1.1.3 Super structure work col/beam/slab 76 days Wed 2/9/22 Mon 4/25/22
21 1.1.3.1 Ground floor work 19 days Wed 2/9/22 Sun 2/27/22
22 1.1.3.1.1 Coloumn rebar work 3 days Wed 2/9/22 Fri 2/11/22 2/9 2/11
23 1.1.3.1.2 Coloumn form work 2 days Sat 2/12/22 Sun 2/13/22 2/12 2/13
24 1.1.3.1.3 Coloumn concrete work 1 day Mon 2/14/22 Mon 2/14/22 2/14 2/14
25 1.1.3.1.4 Slab form work 6 days Tue 2/15/22 Sun 2/20/22 2/15 2/20
26 1.1.3.1.5 Slab rebar work 6 days Mon 2/21/22 Sat 2/26/22 2/21 2/26
27 1.1.3.1.6 Slab concreting work 1 day Sun 2/27/22 Sun 2/27/22 2/27 2/27
28 1.1.3.2 First floor work 19 days Mon 2/28/22 Fri 3/18/22
29 1.1.3.2.1 Coloumn rebar work 3 days Mon 2/28/22 Wed 3/2/22 2/28 3/2
30 1.1.3.2.2 Coloumn form work 2 days Thu 3/3/22 Fri 3/4/22 3/3 3/4
31 1.1.3.2.3 Coloumn concrete work 1 day Sat 3/5/22 Sat 3/5/22 3/5 3/5
32 1.1.3.2.4 Slab form work 6 days Sun 3/6/22 Fri 3/11/22 3/6 3/11
33 1.1.3.2.5 Slab rebar work 6 days Sat 3/12/22 Thu 3/17/22 3/12 3/17
34 1.1.3.2.6 Slab concreting work 1 day Fri 3/18/22 Fri 3/18/22 3/18 3/18
35 1.1.3.3 Second floor work 19 days Sat 3/19/22 Wed 4/6/22
36 1.1.3.3.1 Coloumn rebar work 3 days Sat 3/19/22 Mon 3/21/22 3/19 3/21
37 1.1.3.3.2 Coloumn form work 2 days Tue 3/22/22 Wed 3/23/22 3/22 3/23
38 1.1.3.3.3 Coloumn concrete work 1 day Thu 3/24/22 Thu 3/24/22 3/24 3/24
39 1.1.3.3.4 Slab form work 6 days Fri 3/25/22 Wed 3/30/22 3/25 3/30
40 1.1.3.3.5 Slab rebar work 6 days Thu 3/31/22 Tue 4/5/22 3/31 4/5
41 1.1.3.3.6 Slab concreting work 1 day Wed 4/6/22 Wed 4/6/22 4/6 4/6
42 1.1.3.4 Third floor work 19 days Thu 4/7/22 Mon 4/25/22
43 1.1.3.4.1 Coloumn rebar work 3 days Thu 4/7/22 Sat 4/9/22 4/7 4/9
44 1.1.3.4.2 Coloumn form work 2 days Sun 4/10/22 Mon 4/11/22 4/10 4/11
45 1.1.3.4.3 Coloumn concrete work 1 day Tue 4/12/22 Tue 4/12/22 4/12 4/12
46 1.1.3.4.4 Beam form work 6 days Wed 4/13/22 Mon 4/18/22 4/13 4/18
47 1.1.3.4.5 Beam rebar work 6 days Tue 4/19/22 Sun 4/24/22 4/19 4/24
48 1.1.3.4.6 Beam concreting work 1 day Mon 4/25/22 Mon 4/25/22 4/25 4/25
49