15/11//2021
Page 2 of 13
I. PROJECT OVERVIEW
1. Project Description
Name of project Sai Gon Binh An Urban Area
Address An Phu Ward, Thu Duc City, HCM City
Type Townhouses and villas
Project Owner Sai Gon Development and Investment Joint Stock Company
Nos of Townhouses Phase 1: 915, phase 2: 487, phase 3: 426 and 22 villas
Area
- Land area ≈ 170 ha
- Floor area 75-120 m2/FL
Page 3 of 13
No. Content % Completion Status
Preliminary works
Phase 1
Phase 2
2 Leveling works 10
Main works
Page 4 of 13
NEXT WEEK PLAN
In No. of
No Description Title Machinery Target Zone 15-Nov 16-Nov 17-Nov 18-Nov 19-Nov 20-Nov 21-Nov Remark
charge worker
A. Contruction activities plan
Crane, pile drivers,
1 Test pile driven works Mr.An D.SM 20 50 Piles Phase 1
welder,…
2 Static load test works Mr. An D. SM Crane, pile drivers 20 15 Piles Phase1
Bulldozer,Excavator,
4 Leveling works Mr.Khoa Supervisor 10 30% Phase 2
Trucks
Page 5 of 9
IV.PROJECT MANPOWER
1. Manpower of Contractor
Mon Tue Wed Thu Fri Sat Sun
Position 08-Nov-21 09-Nov-21 10-Nov-21 11-Nov-21 12-Nov-21 13-Nov-21 14-Nov-21
Day shift Night shift Day shift Night shift Day shift Night shift Day shift Night shift Day shift Night shift Day shift Night shift Day shift Night shift
Project Manager 1 0 1 0 1 0 1 0 1 0 1 0 1 0
Site Manager 1 0 1 0 1 0 1 0 1 0 1 0 1 0
Deputy Site Manager 2 0 2 0 2 0 2 0 2 0 2 0 2 0
Engineer 15 2 15 2 15 2 15 2 15 2 15 2 15 2
Safety Officer 1 0 1 0 1 0 1 0 1 0 1 0 1 0
Worker 19 0 23 0 31 0 30 0 27 0 38 0 31 0
Security 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Total 40 3 44 3 52 3 51 3 48 3 59 3 52 3
Page 6 of 13
3. Security
Access Gate checking: The security still check carefully person passing through main Gate.
Prevention plan for Covid-19: All people must be measure temperature, wash their hands and
complete declaration form at gate in before get in.
PROJECT OVERVIEW
Page 7 of 9
FINISHING LEVELING WORKS AT PHASE 1
Page 8 of 13
SETTING OUT GATE No.02
Page 9 of 13
IMPORT PRETENSION PILE TO THE SITE
Page 10 of 13
CHECK ON PILE’S STRAINGHTNESS
Page 11 of 13
PILE DONE DRIVING
Page 12 of 13
VII. WEATHER IN WEEK
VIII. APPENDICE
1. Appendix 1 – REGISTER OF DOCUMENTS
2. Appendix 2– TEST PILE PROGRESS
Page 13 of 13
CHỦ ĐẦU TƯ/ PROJECT INVESTOR TỔNG THẦU THI CÔNG/ GENERAL CONTRACTOR TỔNG THẦU THI CÔNG/ GENERAL CONTRACTOR
SGBA Project
DỰ ÁN/
KHU ĐÔ THỊ SÀI GÒN BÌNH AN
PROJECT: SAI GON BINH AN URBAN AREA
ĐỊA CHỈ/ Đường Đỗ Xuân Hợp, Phường An Phú, Thành Phố Thủ Đức, Thành Phố Hồ Chí Minh
LOCATION:
Do Xuan Hop Street, An Phu Ward, Thu Duc City, Ho Chi Minh City
MATERIALS
1 SAP.CEN.RFA.MA.001. ITP forms and drawings title frame Submitted by Email 25-Oct-21 29-Oct-21 D
2 SAP.CEN.RFA.MA.002. Pile Suppliers Capacity Profiles and Pile Quality Profiles Submitted by Email 27-Oct-21 D
11 SAP.CEN.RFA.MA.011 Concrete suppliers capacity profiles_ Viet Duc Submit by email 02-Nov-21 D
17 SAP.CEN.RFA.MA.017 Quality profile in conformity with material regulations Hong Ha Submit by email 03-Nov-21 D
Concrete quality profile in conformity with material regulations for general works, pile works
19 SAP.CEN.RFA.MA.019 Submit by email 05-Nov-21 D
and structure works_ Viet Han
20 SAP.CEN.RFA.MA.020 Company profile of design consultancy - verification unit_ Lien Viet Submit by email 05-Nov-21 D
7 SAP_CEN_RFA_ME-007 Profile of truck crane Hitachi - KH 100 -180-638 and machine operator profile. Submitted by Email 12-Nov-21 00-Jan-00 D
8 SAP_CEN_RFA_ME-008 Profile of pile driver machine ZYJ420BS00196 and machine operator Profile-HoangNgoc Submitted by Email 15-Nov-21 00-Jan-00 D
9 SAP_CEN_RFA_ME-009 Profile of pile driver machine ZYC700B-B1 and machine operator profile-HoangNgoc Submitted by Email 15-Nov-21 00-Jan-00 D
30/10 Code: C
1 SAP-CEN-RFA-MS-001 Power station Arrangement Plan Submitted by Email 22-Oct-21 26-Oct-21 3-Nov-21 12-Nov-21 D - Not detail enough for review
- To contact with local EVN first
2 SAP.CEN.RFA.MS.002 Temporary Office and logistic plan for phase 1 Submitted by Email 25-Oct-21 D
6 SAP.CEN.RFA.MS.006 Temporary electrical water drawing for phase 1. Submitted by Email 10-Nov-21 D
SHOPDRAWING
SYSTEM DOCUMENTARY
TÌNH TRẠNG PHÊ DUYỆT/ STATUS OF
NGÀY ĐỆ TRÌNH/ SUBMISSION DATE STATUS OF DOC
APPROVAL
MÃ HỒ SƠ/ CODE OF DOC TÌNH TRẠNG & CÁCH THỨC ĐỆ TRÌNH/ NGÀY
STT/ No. NỘI DUNG ĐỆ TRÌNH/ CONTENT OF SUBMISSION GHI CHÚ/ NOTE Kế hoạch xử lý
(DỰ ÁN/ PROJECT) STATUS & TYPE OF SUBMISSION LẦN 1/ LẦN LẦN 3/ LẦN 4/ PHẢN HỒI/ DESIGN BẢN MỀM/ BẢN CỨNG/
CLIENT
REV00 2/REV01 REV02 REV03 RESPOND CONSULTANT SOFT COPY HARD COPY
DATE
Báo cáo kết quả đo đạc kiểm tra mốc khống chế tọa độ bằng công nghệ GPS và đo dẫn độ cao
Đã đệ trình lại ngày 20/10/2021/
1 SAP_CEN_RFA_OTS-001 thủy chuẩn Submitted by Email 20-Oct-21 D
Resubmitted on 20/10/2021
Report for checking coordinate control points using GPS and leveling
22/10 Code C
2 SAP_CEN_RFA_OTS-002 Setting out fence drawings/ Bản vẽ triển khai hàng rào Submitted by Email 21-Oct-21 25-Oct-21 D - find comment in following papes
- to revise and resubmit
4 SAP_CEN_RFA_OTS-004 Response and prevention plan of covid-19 Submitted by Email 30-Oct-21 D
6 SAP_CEN_RFA_OTS-006 Sercurity control procedure. Submitted by Email 22-Oct-21 8-Nov-21 D Code C: Bổ sung hồ sơ đơn vị bảo vệ Lâm Giang
7 SAP_CEN_RFA_OTS-007 Profile of Construction Machinery and Equipment for Excavation Works Submitted by Email 27-Oct-21 D
8 SAP_CEN_RFA_OTS-008 Profile of Construction Machinery and Equipment for Pile Works Submitted by Email 27-Oct-21 D
10
SGSU RFI
4 RFI-005 (Phase 2, 3) Rearrange the pilecap, tie beam or use the current design option (for phase 1) Submitted by Email 22/10/2021 22-Oct-21 D Considering
DESIGN DRAWING
2 STRUCTURAL DESIGN Design drawings of LK1 to LK6 (for review) Submitted by Email 15-Oct-21 D
5 STRUCTURAL DESIGN Design drawings of LV2-1.1 (for review) Submitted by Email 28-Oct-21 D