You are on page 1of 10

EXPANSION OF OSMANI INTERNATIONAL

AIRPORT, SYLHET (1ST PHASE)

MEP WEEKLY REPORT

REPORT BY : AERONESS INTERNATIONAL


REPORT PERIOD : Progress Up to 18-Oct-2022
Weekly Report No : MEP-AI-WR-068

1 / 10
1. PROJECT OVERVIEW

1.1. CLIENT, CONSULTANTS & CONTRACTORS

Client : Civil Aviation Authority of Bangladesh


Designer/Consultant : Yooshin Engineering Corporation
Heerim Architects & Planners
Tarique Hasan & Associates Ltd
Main Contractor : Beijing Urban Construction Group Co., Ltd
MEP Subcontractor : Aeroness International
1.2. MEP Subcontractor’s Scope of Work

Detailed Design, Shop drawing, Execution, Testing & Commissioning, as built


Drawings and Handing over as specified in BOQ, Specifications and Drawings,
including but not limited to Furniture works, Fire Fighting System, Internal
Electrification Works, Electrical Substation works, Addressable Fire Detection &
Alarm System, Sewage Treatment Plant, Water Treatment Plant, Electro-
Mechanical Works, Communication & Security System and Fuel Hydrant Works.
1.3. Design Standards

Bangladesh National Building Code (BNBC), International Electro-technical


Commission (IEC), Institute of Electrical and Electronics Engineers (IEEE),
National Electrical Manufacturers Association (NEMA), German International
Standard (VDE), International Standard Organization (ISO), British Standard
(BS), National Fire Protection Association (NFPA), American National Standard
Institute (ASNI)

2 / 10
2. Project Personnel

No. Name Position Subject Tel: E-mail


01. Imran Karim Jony Head of Projects

02. Musfiq Chowdhury Lead of Project


Management
03. Engr. Muhammad Hossain Project Manager
04. Hasan Mahmud Amran DPM
05. Junayed Al Imran MEP Engineer
06. Mehedi Hasan Project Engineer
07. Sajib Saha AutoCAD Engineer
08. N.M.Nazmul Huda Project Engineer

3. WORK PROGRESS

Previous
Reporting Cumulative Cumulative
No Work Description Week Deviation %
week % Actual % Planned %
Cumulative%
Schematic Drawing &
1
Calculation

1.1 Air Side (AS)

1.2 Land Side (LS)

1.3 General (GE)


Passenger Terminal Building
1.4
(PTB)

1.5 Cargo Building (CAR)


Rescue and Fire Fighting
1.6
Station (FIR)
Operation Building & Control
1.7
Tower (CON)
Administrative Building
1.8
(ADM)

1.9 Maintenance Building (MAI)

1.10 AFL Station (AFL)

1.11 Utility Station (UTI)

1.12 Cargo Annex Building (ANX)


Sewage Treatment Plant (STP)
1.13 & Sewage Treatment Plant
Detailed Design/Shop
2
Drawings
3 / 10
Previous
Reporting Cumulative Cumulative
No Work Description Week Deviation %
week % Actual % Planned %
Cumulative%

2.1 Air Side (AS)

2.2 Land Side (LS)

2.3 General (GE)


Passenger Terminal Building
2.4
(PTB)

2.5 Cargo Building (CAR)

Rescue and Fire Fighting


2.6
Station (FIR)
Operation Building & Control
2.7
Tower (CON)
Administrative Building
2.8
(ADM)

2.9 Maintenance Building (MAI)

2.10 AFL Station (AFL)

2.11 Utility Station (UTI)

2.12 Cargo Annex Building (ANX)

Sewage Treatment Plant (STP)


2.13 & Sewage Treatment Plant
(WTP)

3 Procurement

3.1 Air Side (AS)

3.2 Land Side (LS)

3.3 General (GE)

Passenger Terminal Building


3.4
(PTB)

3.5 Cargo Building (CAR)

Rescue and Fire Fighting


3.6
Station (FIR)
Operation Building & Control
3.7
Tower (CON)
Administrative Building
3.8
(ADM)

4 / 10
Previous
Reporting Cumulative Cumulative
No Work Description Week Deviation %
week % Actual % Planned %
Cumulative%

3.9 Maintenance Building (MAI)

3.10 AFL Station (AFL)

3.11 Utility Station (UTI)

3.12 Cargo Annex Building (ANX)

Sewage Treatment Plant (STP)


3.13 & Sewage Treatment Plant
(WTP)

4 Installation & Commissioning

4.1 Air Side (AS)

4.2 Land Side (LS)

4.3 General (GE)

Passenger Terminal Building


4.4
(PTB)

4.5 Cargo Building (CAR)

Rescue and Fire Fighting


4.6
Station (FIR)
Operation Building & Control
4.7
Tower (CON)
Administrative Building
4.8
(ADM)

4.9 Maintenance Building (MAI)

4.10 AFL Station (AFL)

4.11 Utility Station (UTI)

4.12 Cargo Annex Building (ANX)

Sewage Treatment Plant (STP)


4.13 & Sewage Treatment Plant
(WTP)

5 / 10
4. WORK OBJECTIVE OF 4th QUARTER AND CURRENT MONTH

• To prepare shop drawings of electro-mechanical services as per submitted


SHOP DRAWING SCHEDULE with BUCG architectural drawings approved by
CAAB.
• To Prepare Method of Statements & RMC for materials as per submitted
SHOP DRAWING SCHEDULE of E&M service that needs to be installed on site
with relation to the work program.
• To carry out the construction works in line with civil works with approval from
CAAB & Consultant. For this purpose, all relevant document approval from
CAAB/Consultant and necessary activities such as material approval,
procurement, materials inspection etc. to be carried out as per the construction
timeline. At the beginning of each month, Aeroness will prepare and submit the
monthly E&M Micro Schedule with respect to the monthly civil construction
work micro schedule.
• In this quarter, the underground route for Utility tunnel, Duct bank and/or
other services is to be prepared and proposed to client to secure approval.
Otherwise, preparation of the other shop drawings will be hampered in near
future.
• Power distribution system and Utility building also need to be verified
unofficially by CAAB, with help from Ex. En. Mr. Arif. After that, we can proceed to
submit officially through consultant.
• To prepare and submit technical proposal, shop drawing, brand approval
documents for airport specialized services with respect to civil construction work
and site requirement.

6 / 10
5. WORK OF THIS WEEK
• Escalator & Elevator:
o Escalator & Elevator relevant drawings: Meeting with MOVILIFT Personal
from Italy, has been conducted on 13-Oct-2022. MOVILIFT is preparing
drawing and document as per BUCG guidance. Target Date 22-10-2022.
• Cold Storage System of CTB:
o Draft Technical proposal has been shared with BUCG by Whatsapp on 17-
Oct-2022. Actual submission Target Date 21-10-2022.
• Shop Drawing Works (Target):
o Shop drawings to be prepared and submitted as per shop drawing schedule
4.1.12.2.4.2_Shop Drawing Submission Schedule for PTB
➢ ADM Pre-embedment (submission for approval)
➢ PTB Pre-embedment (submission for approval)
➢ Utility Tunnel route (Submission for review)
➢ Control tower connection details (submission for approval)
• PTB Grounding system drawing (Submitted):
o PTB Grounding system drawings Rev 02 has been submitted on 02-Oct-
2022. Waiting for feedback.
• Pre embedment pipe layout (Draft Submitted):
o Pre embedment drawings for ADM building work has been shared for
review by Whatsapp on 16-Oct-2022.
• FHS:
o A coordination meeting has been held on 16-10-2022. Will submit the RFI
by today.
o Foreign design contractor will come here in Sylhet by 21-10-2022
• STP WTP:
o The sub-contractor has submitted the technical proposal.
o Aeroness has checked the submittal, Preparing the presentation.
o Target submission date 22-10-2022 (WTP)
o Target submission date 24-10-2022 (STP)
• Baggage Handling System: RFI regarding the meeting is shared.

• PBB: As per the information getting from CAAB, CE Sir will review the letter by this
week.

• Admin Building Grounding System Work: AERONESS Started the Grounding System
Work for Admin Building. WIR No. OIA-BU-CA-EM-ADM-001.

• PTB Grounding System Work: Grounding system work for PTB is ongoing.

7 / 10
6. WORK PLAN OF NEXT WEEK
• Revise prepared drawings: (as per requirement)
o ADM Pre embedment drawings final submission
o PTB Grounding system drawings (if consultant has any suggestion)
o To finalize technical proposal for CTB Cold Storage.
o STP Technical Submittal
o WTP Technical Submittal
o FFS (Pipe and Accessories) RMC Submittal

• Next week construction work plan:


o Pre-Embedded pipes- Material Inspection and approval
o PTB Grounding work (LPS)
o ADM Grounding work- as per site work completion.

7. PROGRESS PHOTOS
N/A.

8. PLANNED CONSTRUCTION WORK PROGRESS

Planned % for
No Work Description Planned % for ’2022
next week
1 Detailed Design/Shop Drawings
1.1 Air Side (AS)
1.2 Land Side (LS)
1.3 General (GE)
1.4 Passenger Terminal Building (PTB)
1.5 Cargo Building (CAR)
1.6 Rescue and Fire Fighting Station (FIR)
Operation Building & Control Tower
1.7
(CON)
1.8 Administrative Building (ADM)
1.9 Maintenance Building (MAI)
1.10 AFL Station (AFL)
1.11 Utility Station (UTI)
1.12 Cargo Annex Building (ANX)
Sewage Treatment Plant (STP) & Water
1.13
Treatment Plant (WTP)
2 Procurement
Air Side (AS)
Land Side (LS)
General (GE)

8 / 10
Passenger Terminal Building (PTB)
Cargo Building (CAR)
Rescue and Fire Fighting Station (FIR)
Operation Building & Control Tower
(CON)
Administrative Building (ADM)
Maintenance Building (MAI)
AFL Station (AFL)
Utility Station (UTI)
Cargo Annex Building (ANX)
Sewage Treatment Plant (STP) & Water
Treatment Plant (WTP)
3 Installation & Commissioning
3.1 Air Side (AS)
3.2 Land Side (LS)
3.3 General (GE)
3.4 Passenger Terminal Building (PTB)
3.5 Cargo Building (CAR)
3.6 Rescue and Fire Fighting Station (FIR)
Operation Building & Control Tower
3.7
(CON)
3.8 Administrative Building (ADM)
3.9 Maintenance Building (MAI)
3.10 AFL Station (AFL)
3.11 Utility Station (UTI)
3.12 Cargo Annex Building (ANX)
3.13 Sewage Treatment Plant (STP)

9. DOCUMENTS SUBMISSION OF REPORTING WEEK

Status
Document Document Ref. No Docum
No Date Description (Open or
Type ent
Close)
(RFI/TRN/MC Ref.
/LET) No

9 / 10
10. ISSUES TO BE SOLVED

a. Elevator & Escalator drawings for PTB


b. Cold storage technical proposal
c. STP & WTP
d. BHS meeting
e. Passenger boarding bridge
f. Fuel Hydrant system
g. DVOR
h. HEERIM drawings review has been shared. Need the feedback and decision of client to
speed up the shop drawing preparation stage.

11. MATERIALS DELIVERED & ORDERED

➢ N/A
12. INTERNAL ACTIVITY OF AERONESS INTERNATIONAL

Ongoing Activities:

➢ Electrical, HVAC, Special Items suppliers are to be finalized and engaged for drawings.
➢ BHS Procurement Discussion Still ongoing.
➢ Special items suppliers are being engaged to prepare the drawings/technical proposal.
➢ STP, WTP supplier Communication regarding technical parameters of the proposal.
➢ LPS grounding drawings for PTB is on progress to get approval.

<<< End of Report >>>