KO-C1-PMA-CSH-SH-004_Schedule Recovery for Outstanding Works_2022.01.

01
ID WBS Task Task Name Duration Start Finish Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022
Mode Dec Jan Feb Mar Apr May Jun Jul
1 1 EASTERN REGIONAL HOSPITAL KOFORIDUA 194.25 days Tue 12/7/21 Mon 7/4/22
2 1.1 PROJECT MILESTONES 194.25 days Tue 12/7/21 Mon 7/4/22
3 1.1.1 Commencement Date_Outstanding Works 0 days Tue 12/7/21 Tue 12/7/21 12/7
4 1.1.2 Completion of casting of 1st suspended slab 15 days Fri 3/11/22 Sun 3/27/22
5 1.1.3 Start of masonry works on walls 15.5 days Fri 4/15/22 Sun 5/1/22
6 1.1.4 Last structural concrete pour on roof slab 8.5 days Thu 6/2/22 Sat 6/11/22
7 1.1.5 Completion of works, inspection and issue of  1.5 days Sat 7/2/22 Mon 7/4/22
Provisional acceptance certificate, and completion 
of the removal/dismantling of all site installation 
works
8 1.2 ZONE A 172.75 days Wed 12/29/21 Sun 7/3/22
9 1.2.1 ZONE A ‐1 172.5 days Wed 12/29/21 Sun 7/3/22
10 1.2.1.1 BASEMENT WORKS 139.75 days Wed 12/29/21 Sat 5/28/22
11 1.2.1.1.1 Backfilling around foundation/ column & wall  16 days Wed 12/29/21 Sat 1/15/22
necks
12 1.2.1.1.2 Structual Backfilling works 9 days Sun 1/23/22 Tue 2/1/22
13 1.2.1.1.3 Backfilling at back of retaining walls 33 days Wed 4/20/22 Wed 5/25/22
14 1.2.1.1.4 Neck columns works 15 days Wed 12/29/21 Fri 1/14/22
15 1.2.1.1.5 Tie Beams works 13 days Tue 1/11/22 Tue 1/25/22
16 1.2.1.1.6 Slab on grade works 15 days Tue 1/25/22 Thu 2/10/22
17 1.2.1.1.7 Expansion joints works 1 day Tue 2/22/22 Wed 2/23/22
18 1.2.1.1.8 Columns & Wall works_ Superstructure 14 days Fri 2/11/22 Sat 2/26/22
19 1.2.1.1.9 Drop panels & Slab works 12 days Thu 3/31/22 Tue 4/12/22
20 1.2.1.1.10 First fix (MEP) 30 days Fri 2/25/22 Tue 3/29/22
21 1.2.1.1.11 Infill blockworks 19 days Sun 5/8/22 Sat 5/28/22
22 1.2.1.2 GROUND FLOOR WORKS 62 days Fri 4/15/22 Mon 6/20/22
23 1.2.1.2.1 Columns & Wall work 7 days Fri 4/15/22 Fri 4/22/22
24 1.2.1.2.2 Beams & Slab works 16 days Sat 4/23/22 Tue 5/10/22
25 1.2.1.2.3 Neoprene Pads installation works 1 day Wed 5/18/22 Thu 5/19/22
26 1.2.1.2.4 First fix (MEP) 4 days Tue 5/3/22 Sat 5/7/22
27 1.2.1.2.5 Infill blockworks 20 days Mon 5/30/22 Mon 6/20/22
28 1.2.1.3 FIRST FLOOR WORKS 47.5 days Fri 5/13/22 Sun 7/3/22
29 1.2.1.3.1 Columns work 10 days Fri 5/13/22 Mon 5/23/22
30 1.2.1.3.2 Beams works & Slabs works 10 days Mon 5/23/22 Thu 6/2/22
31 1.2.1.3.3 Neoprene Pads installation works 1 day Tue 6/7/22 Wed 6/8/22
32 1.2.1.3.4 First fix (MEP) 2 days Thu 5/26/22 Sat 5/28/22
33 1.2.1.3.5 Infill blockworks 9 days Thu 6/23/22 Sun 7/3/22
34 1.2.2 ZONE A‐2 170.75 days Fri 12/31/21 Sun 7/3/22
35 1.2.2.1 BASEMENT WORKS 139.5 days Fri 12/31/21 Mon 5/30/22
36 1.2.2.1.1 Backfilling around foundation/ column & wall  20 days Fri 12/31/21 Fri 1/21/22
necks

Page 1
KO-C1-PMA-CSH-SH-004_Schedule Recovery for Outstanding Works_2022.01.01
ID WBS Task Task Name Duration Start Finish Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022
Mode Dec Jan Feb Mar Apr May Jun Jul
37 1.2.2.1.2 Structual Backfilling works 20 days Mon 1/24/22 Mon 2/14/22
38 1.2.2.1.3 Backfilling at back of retaining walls 34 days Sat 4/23/22 Sun 5/29/22
39 1.2.2.1.4 Neck columns works 22 days Fri 12/31/21 Mon 1/24/22
40 1.2.2.1.5 Tie Beams works 13 days Thu 1/13/22 Thu 1/27/22
41 1.2.2.1.6 Slab on grade works 14 days Fri 1/28/22 Sat 2/12/22
42 1.2.2.1.7 Expansion joints works 1 day Mon 3/21/22 Mon 3/21/22
43 1.2.2.1.8 Columns & Wall works_ Superstructure 10 days Tue 3/22/22 Fri 4/1/22
44 1.2.2.1.9 Drop panels & Slab works 16 days Fri 4/1/22 Mon 4/18/22
45 1.2.2.1.10 First fix (MEP) 20 days Sat 4/2/22 Sat 4/23/22
46 1.2.2.1.11 Infill blockworks 19 days Tue 5/10/22 Mon 5/30/22
47 1.2.2.2 GROUND FLOOR WORKS 68 days Fri 4/8/22 Mon 6/20/22
48 1.2.2.2.1 Columns & Wall work 12 days Fri 4/8/22 Wed 4/20/22
49 1.2.2.2.2 Beams & Slab works 16 days Thu 4/21/22 Sun 5/8/22
50 1.2.2.2.3 Neoprene Pads installation works 1 day Mon 5/16/22 Mon 5/16/22
51 1.2.2.2.4 First fix (MEP) 4 days Thu 4/28/22 Mon 5/2/22
52 1.2.2.2.5 Infill blockworks 21 days Sat 5/28/22 Mon 6/20/22
53 1.2.2.3 FIRST FLOOR WORKS 50.25 days Tue 5/10/22 Sun 7/3/22
54 1.2.2.3.1 Columns & Wall work 10 days Tue 5/10/22 Fri 5/20/22
55 1.2.2.3.2 Beams works & Slabs works 6 days Sun 5/15/22 Sat 5/21/22
56 1.2.2.3.3 Neoprene Pads installation works 1 day Sun 5/29/22 Mon 5/30/22
57 1.2.2.3.4 First fix (MEP) 4 days Thu 5/12/22 Mon 5/16/22
58 1.2.2.3.5 Infill blockworks 16.5 days Wed 6/15/22 Sun 7/3/22
59 1.2.2.4 SECOND FLOOR WORKS 38.5 days Mon 5/23/22 Sun 7/3/22
60 1.2.2.4.1 Columns work 9 days Mon 5/23/22 Wed 6/1/22
61 1.2.2.4.2 Beams works & Slabs works 8 days Thu 6/2/22 Sat 6/11/22
62 1.2.2.4.3 Neoprene Pads installation works 1 day Sun 6/19/22 Mon 6/20/22
63 1.2.2.4.4 First fix (MEP) 2 days Fri 6/3/22 Mon 6/6/22
64 1.2.2.4.5 Infill blockworks 7.5 days Sat 6/25/22 Sun 7/3/22
65 1.2.3 ZONE A‐3 160.5 days Wed 12/29/21 Mon 6/20/22
66 1.2.3.1 BASEMENT WORKS 115.5 days Wed 12/29/21 Mon 5/2/22
67 1.2.3.1.1 Backfilling around foundation/ column & wall n20 days Wed 12/29/21 Wed 1/19/22
68 1.2.3.1.2 Structual Backfilling works 21 days Thu 2/3/22 Fri 2/25/22
69 1.2.3.1.3 Backfilling at back of retaining walls 34 days Sun 3/27/22 Mon 5/2/22
70 1.2.3.1.4 Neck columns works 23 days Wed 12/29/21 Sun 1/23/22
71 1.2.3.1.5 Tie Beams works 23 days Tue 1/11/22 Fri 2/4/22
72 1.2.3.1.6 Slab on grade works 14 days Sun 2/6/22 Mon 2/21/22
73 1.2.3.1.7 Expansion joints works 1 day Mon 2/21/22 Tue 2/22/22
74 1.2.3.1.8 Columns & Wall works_ Superstructure 14 days Tue 2/22/22 Wed 3/9/22
75 1.2.3.1.9 Drop panels & Slab works 6.5 days Tue 3/15/22 Mon 3/21/22
76 1.2.3.1.10 First fix (MEP) 15 days Tue 3/22/22 Wed 4/6/22

Page 2
KO-C1-PMA-CSH-SH-004_Schedule Recovery for Outstanding Works_2022.01.01
ID WBS Task Task Name Duration Start Finish Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022
Mode Dec Jan Feb Mar Apr May Jun Jul
77 1.2.3.1.11 Infill blockworks 11 days Sun 4/10/22 Thu 4/21/22
78 1.2.3.2 GROUND FLOOR WORKS 61 days Wed 3/23/22 Fri 5/27/22
79 1.2.3.2.1 Columns & Wall work 10 days Wed 3/23/22 Sat 4/2/22
80 1.2.3.2.2 Beams & Slab works 10 days Sun 3/27/22 Wed 4/6/22
81 1.2.3.2.3 Neoprene Pads installation works 2 days Thu 4/7/22 Fri 4/8/22
82 1.2.3.2.4 First fix (MEP) 4 days Wed 3/30/22 Sun 4/3/22
83 1.2.3.2.5 Infill blockworks 22 days Wed 5/4/22 Fri 5/27/22
84 1.2.3.3 FIRST FLOOR WORKS 68 days Fri 4/8/22 Mon 6/20/22
85 1.2.3.3.1 Columns work 11 days Fri 4/8/22 Tue 4/19/22
86 1.2.3.3.2 Beams works & Slabs works 8 days Tue 5/3/22 Wed 5/11/22
87 1.2.3.3.3 Neoprene Pads installation works 2 days Wed 5/11/22 Fri 5/13/22
88 1.2.3.3.4 First fix (MEP) 4 days Wed 5/4/22 Sun 5/8/22
89 1.2.3.3.5 Infill blockworks 18 days Wed 6/1/22 Mon 6/20/22
90 1.2.4 ZONE A‐4 159 days Fri 12/31/21 Mon 6/20/22
91 1.2.4.1 BASEMENT WORKS 122 days Fri 12/31/21 Wed 5/11/22
92 1.2.4.1.1 Backfilling around foundation/ column & wall n20 days Fri 12/31/21 Fri 1/21/22
93 1.2.4.1.2 Structual Backfilling works 21 days Fri 2/4/22 Sat 2/26/22
94 1.2.4.1.3 Backfilling at back of retaining walls 36 days Sun 4/3/22 Wed 5/11/22
95 1.2.4.1.4 Neck columns works 22 days Fri 12/31/21 Mon 1/24/22
96 1.2.4.1.5 Tie Beams works 23 days Thu 1/13/22 Mon 2/7/22
97 1.2.4.1.6 Slab on grade works 16 days Tue 2/8/22 Fri 2/25/22
98 1.2.4.1.7 Expansion joints works 1 day Sat 2/26/22 Sun 2/27/22
99 1.2.4.1.8 Columns & Wall works_ Superstructure 23 days Sun 2/20/22 Wed 3/16/22
100 1.2.4.1.9 Drop panels & Slab works 12 days Thu 3/17/22 Tue 3/29/22
101 1.2.4.1.10 First fix (MEP) 25 days Mon 3/21/22 Sat 4/16/22
102 1.2.4.1.11 Infill blockworks 15 days Fri 4/15/22 Sun 5/1/22
103 1.2.4.2 GROUND FLOOR WORKS 56 days Thu 3/31/22 Mon 5/30/22
104 1.2.4.2.1 Columns & Wall work 10 days Thu 3/31/22 Sun 4/10/22
105 1.2.4.2.2 Beams & Slab works 9 days Tue 4/12/22 Thu 4/21/22
106 1.2.4.2.3 Neoprene Pads installation works 2 days Fri 4/29/22 Sun 5/1/22
107 1.2.4.2.4 First fix (MEP) 4 days Thu 4/28/22 Mon 5/2/22
108 1.2.4.2.5 Infill blockworks 19 days Tue 5/10/22 Mon 5/30/22
109 1.2.4.3 FIRST FLOOR WORKS 55 days Fri 4/22/22 Mon 6/20/22
110 1.2.4.3.1 Columns work 13 days Fri 4/22/22 Fri 5/6/22
111 1.2.4.3.2 Beams works & Slabs works 13 days Sat 5/7/22 Sat 5/21/22
112 1.2.4.3.3 Neoprene Pads installation works 2 days Sun 5/29/22 Tue 5/31/22
113 1.2.4.3.4 First fix (MEP) 4 days Thu 5/12/22 Mon 5/16/22
114 1.2.4.3.5 Infill blockworks 10 days Fri 6/10/22 Mon 6/20/22
115 1.3 ZONE B 191.5 days Tue 12/7/21 Thu 6/30/22
116 1.3.1 ZONE B ‐ 1 161 days Tue 12/7/21 Sun 5/29/22

Page 3
KO-C1-PMA-CSH-SH-004_Schedule Recovery for Outstanding Works_2022.01.01
ID WBS Task Task Name Duration Start Finish Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022
Mode Dec Jan Feb Mar Apr May Jun Jul
117 1.3.1.1 SUB‐STRUCTURE WORKS 53 days Tue 12/7/21 Tue 2/1/22
118 1.3.1.1.1 Neck columns works 40 days Tue 12/7/21 Tue 1/18/22
119 1.3.1.1.2 Backfilling around foundation/ column & wall n32 days Tue 12/21/21 Mon 1/24/22
120 1.3.1.1.3 Structual Backfilling works 13 days Sat 1/15/22 Sat 1/29/22
121 1.3.1.1.4 First fix (MEP) 20 days Tue 1/4/22 Tue 1/25/22
122 1.3.1.1.5 Tie beams works 42 days Wed 12/8/21 Fri 1/21/22
123 1.3.1.1.6 Slab on Grade works including Expansion joint f10 days Sat 1/22/22 Tue 2/1/22
124 1.3.1.2 GROUND FLOOR WORKS 56 days Mon 2/28/22 Thu 4/28/22
125 1.3.1.2.1 Columns work 15 days Mon 2/28/22 Tue 3/15/22
126 1.3.1.2.2 Beams & Slabs works 14 days Fri 3/18/22 Fri 4/1/22
127 1.3.1.2.3 Neoprene Pads installation works 1 day Sun 4/3/22 Mon 4/4/22
128 1.3.1.2.4 First fix (MEP) 4 days Wed 3/23/22 Sun 3/27/22
129 1.3.1.2.5 Infill blockworks 10 days Mon 4/18/22 Thu 4/28/22
130 1.3.1.3 FIRST FLOOR WORKS 52 days Sun 4/3/22 Sun 5/29/22
131 1.3.1.3.1 Columns work 8 days Sun 4/3/22 Mon 4/11/22
132 1.3.1.3.2 Beams & Slabs works 12 days Wed 4/13/22 Mon 4/25/22
133 1.3.1.3.3 Neoprene Pads installation works 1 day Wed 4/27/22 Wed 4/27/22
134 1.3.1.3.4 First fix (MEP) 4 days Mon 4/18/22 Fri 4/22/22
135 1.3.1.3.5 Infill blockworks 15 days Fri 5/13/22 Sun 5/29/22
136 1.3.2 ZONE B ‐ 2 146 days Wed 1/5/22 Fri 6/10/22
137 1.3.2.1 SUB‐STRUCTURE WORKS 82 days Wed 1/5/22 Sun 4/3/22
138 1.3.2.1.1 Excavation ( including stabilization works) 23 days Wed 1/5/22 Sat 1/29/22
139 1.3.2.1.2 Blinding works 20 days Fri 1/14/22 Sat 2/5/22
140 1.3.2.1.3 Formwork to foundation bases 19 days Wed 1/19/22 Tue 2/8/22
141 1.3.2.1.4 Steel reinforcement 20 days Sat 1/22/22 Sun 2/13/22
142 1.3.2.1.5 Foundation concrete 11 days Mon 3/14/22 Fri 3/25/22
143 1.3.2.1.6 Neck columns works 12 days Fri 3/11/22 Thu 3/24/22
144 1.3.2.1.7 Backfilling around foundation/ column & wall n10 days Tue 3/8/22 Fri 3/18/22
145 1.3.2.1.8 Structual Backfilling works 4 days Wed 3/23/22 Sun 3/27/22
146 1.3.2.1.9 First fix (MEP) 20 days Fri 3/11/22 Fri 4/1/22
147 1.3.2.1.10 Tie beams works 10 days Wed 3/23/22 Sun 4/3/22
148 1.3.2.1.11 Slab on Grade works including Expansion joint f5 days Tue 3/29/22 Sun 4/3/22
149 1.3.2.2 GROUND FLOOR WORKS 63 days Mon 4/4/22 Fri 6/10/22
150 1.3.2.2.1 Columns & Wall works 14 days Mon 4/4/22 Tue 4/19/22
151 1.3.2.2.2 Beams & Slabs works 18 days Wed 4/20/22 Mon 5/9/22
152 1.3.2.2.3 First fix (MEP) 4 days Thu 4/28/22 Mon 5/2/22
153 1.3.2.2.4 Infill blockworks 14 days Fri 5/27/22 Fri 6/10/22
154 1.3.2.3 FIRST FLOOR WORKS 29 days Wed 5/11/22 Fri 6/10/22
155 1.3.2.3.1 Columns work 11 days Wed 5/11/22 Sun 5/22/22
156 1.3.2.3.2 Beams & Slabs works 15 days Sat 5/14/22 Mon 5/30/22

Page 4
KO-C1-PMA-CSH-SH-004_Schedule Recovery for Outstanding Works_2022.01.01
ID WBS Task Task Name Duration Start Finish Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022
Mode Dec Jan Feb Mar Apr May Jun Jul
157 1.3.2.3.3 First fix (MEP) 4 days Mon 5/16/22 Fri 5/20/22
158 1.3.2.3.4 Infill blockworks 10 days Tue 5/31/22 Fri 6/10/22
159 1.3.3 ZONE B ‐ 3 170.5 days Wed 12/29/21 Thu 6/30/22
160 1.3.3.1 BASEMENT WORKS 142.5 days Wed 12/29/21 Tue 5/31/22
161 1.3.3.1.1 Backfilling around foundation/ column & wall n22 days Wed 12/29/21 Fri 1/21/22
162 1.3.3.1.2 Structual Backfilling works 22 days Sat 1/22/22 Mon 2/14/22
163 1.3.3.1.3 Backfilling at back of retaining walls 34 days Mon 4/25/22 Tue 5/31/22
164 1.3.3.1.4 Neck columns works 24 days Wed 12/29/21 Mon 1/24/22
165 1.3.3.1.5 Tie Beams works 15 days Tue 1/11/22 Thu 1/27/22
166 1.3.3.1.6 Slab on grade works 15 days Wed 1/26/22 Fri 2/11/22
167 1.3.3.1.7 Columns & Wall works_ Superstructure 12 days Thu 3/24/22 Tue 4/5/22
168 1.3.3.1.8 Drop panels & Slab works 14 days Wed 4/6/22 Wed 4/20/22
169 1.3.3.1.9 First fix (MEP) 30 days Fri 4/1/22 Tue 5/3/22
170 1.3.3.2 GROUND FLOOR WORKS 47 days Sat 4/23/22 Sun 6/12/22
171 1.3.3.2.1 Columns work 8 days Sat 4/23/22 Sun 5/1/22
172 1.3.3.2.2 Beams & Slabs works 7 days Wed 5/4/22 Wed 5/11/22
173 1.3.3.2.3 First fix (MEP) 7 days Sat 4/30/22 Sun 5/8/22
174 1.3.3.2.4 Infill blockworks 15 days Fri 5/27/22 Sun 6/12/22
175 1.3.3.3 FIRST FLOOR WORKS 45 days Fri 5/13/22 Thu 6/30/22
176 1.3.3.3.1 Columns work 8 days Fri 5/13/22 Sun 5/22/22
177 1.3.3.3.2 Beams & Slabs works 8 days Tue 5/24/22 Wed 6/1/22
178 1.3.3.3.3 First fix (MEP) 7 days Sun 5/22/22 Sun 5/29/22
179 1.3.3.3.4 Infill blockworks 12 days Sat 6/18/22 Thu 6/30/22
180 1.4 ZONE C 190 days Thu 12/9/21 Fri 7/1/22
181 1.4.1 ZONE C ‐ 1 151 days Tue 1/18/22 Wed 6/29/22
182 1.4.1.1 SUB‐STRUCTURE WORKS 68 days Tue 1/18/22 Thu 3/31/22
183 1.4.1.1.1 Excavation ( including stabilization works) 20 days Tue 1/18/22 Tue 2/8/22
184 1.4.1.1.2 Blinding works 11 days Fri 1/28/22 Wed 2/9/22
185 1.4.1.1.3 Formwork to foundation bases 10 days Wed 2/2/22 Sat 2/12/22
186 1.4.1.1.4 Steel reinforcement 11 days Sat 2/5/22 Wed 2/16/22
187 1.4.1.1.5 Foundation concrete 10 days Sat 2/12/22 Wed 2/23/22
188 1.4.1.1.6 Neck columns works 9 days Sat 2/19/22 Mon 2/28/22
189 1.4.1.1.7 Backfilling around foundation/ column & wall  6 days Fri 3/11/22 Thu 3/17/22
necks
190 1.4.1.1.8 Structual Backfilling works 9 days Fri 3/18/22 Sun 3/27/22
191 1.4.1.1.9 First fix (MEP) 27 days Sat 2/19/22 Sun 3/20/22
192 1.4.1.1.10 Tie beams works 6 days Thu 3/24/22 Wed 3/30/22
193 1.4.1.1.11 Slab on Grade works including Expansion joint  9 days Tue 3/22/22 Thu 3/31/22
fixing
194 1.4.1.2 GROUND FLOOR WORKS 48 days Sat 4/2/22 Mon 5/23/22

Page 5
KO-C1-PMA-CSH-SH-004_Schedule Recovery for Outstanding Works_2022.01.01
ID WBS Task Task Name Duration Start Finish Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022
Mode Dec Jan Feb Mar Apr May Jun Jul
195 1.4.1.2.1 Columns & Wall works 8 days Sat 4/2/22 Sun 4/10/22
196 1.4.1.2.2 Beams & Slabs works 8 days Tue 4/12/22 Wed 4/20/22
197 1.4.1.2.3 First fix (MEP) 4 days Wed 4/13/22 Sun 4/17/22
198 1.4.1.2.4 Infill blockworks 15 days Sat 5/7/22 Mon 5/23/22
199 1.4.1.3 FIRST FLOOR WORKS 52 days Mon 4/25/22 Sun 6/19/22
200 1.4.1.3.1 Columns work 9 days Mon 4/25/22 Wed 5/4/22
201 1.4.1.3.2 Beams & Slabs works 11 days Wed 5/11/22 Sun 5/22/22
202 1.4.1.3.3 First fix (MEP) 4 days Wed 5/18/22 Sun 5/22/22
203 1.4.1.3.4 Infill blockworks 10 days Thu 6/9/22 Sun 6/19/22
204 1.4.1.4 SECOND FLOOR WORKS 34 days Tue 5/24/22 Wed 6/29/22
205 1.4.1.4.1 Columns work 10 days Tue 5/24/22 Fri 6/3/22
206 1.4.1.4.2 Beams & Slabs works 11 days Mon 5/30/22 Fri 6/10/22
207 1.4.1.4.3 First fix (MEP) 4 days Tue 6/7/22 Fri 6/10/22
208 1.4.1.4.4 Infill blockworks 9 days Mon 6/20/22 Wed 6/29/22
209 1.4.2 ZONE C ‐ 2 172 days Tue 12/21/21 Thu 6/23/22
210 1.4.2.1 SUB‐STRUCTURE WORKS 100 days Tue 12/21/21 Thu 4/7/22
211 1.4.2.1.1 Excavation ( including stabilization works) 7 days Tue 12/21/21 Tue 12/28/21
212 1.4.2.1.2 Blinding works 8 days Fri 1/7/22 Sat 1/15/22
213 1.4.2.1.3 Formwork to foundation bases 8 days Thu 1/13/22 Fri 1/21/22
214 1.4.2.1.4 Steel reinforcement 11 days Sat 1/22/22 Wed 2/2/22
215 1.4.2.1.5 Foundation concrete 8 days Wed 3/2/22 Thu 3/10/22
216 1.4.2.1.6 Neck columns works 9 days Sat 3/5/22 Mon 3/14/22
217 1.4.2.1.7 Backfilling around foundation/ column & wall  6 days Fri 3/11/22 Thu 3/17/22
necks
218 1.4.2.1.8 Structual Backfilling works 5 days Thu 3/31/22 Tue 4/5/22
219 1.4.2.1.9 First fix (MEP) 20 days Sat 3/5/22 Sat 3/26/22
220 1.4.2.1.10 Tie beams works 7 days Mon 3/21/22 Mon 3/28/22
221 1.4.2.1.11 Slab on Grade works including Expansion joint  8 days Wed 3/30/22 Thu 4/7/22
fixing
222 1.4.2.2 GROUND FLOOR WORKS 20 days Sat 4/9/22 Sun 5/1/22
223 1.4.2.2.1 Columns & Wall works 8 days Sat 4/9/22 Mon 4/18/22
224 1.4.2.2.2 Beams & Slabs works 8 days Tue 4/12/22 Wed 4/20/22
225 1.4.2.2.3 Neoprene Pads Installation works 4 days Sun 4/17/22 Thu 4/21/22
226 1.4.2.2.4 First fix (MEP) 4 days Wed 4/13/22 Sun 4/17/22
227 1.4.2.2.5 Infill blockworks 8 days Fri 4/22/22 Sun 5/1/22
228 1.4.2.3 FIRST FLOOR WORKS 53 days Thu 4/21/22 Fri 6/17/22
229 1.4.2.3.1 Columns work 10 days Thu 4/21/22 Mon 5/2/22
230 1.4.2.3.2 Beams & Slabs works 13 days Sun 5/1/22 Sun 5/15/22
231 1.4.2.3.3 Neoprene Pads Installation works 1 day Mon 5/16/22 Tue 5/17/22
232 1.4.2.3.4 First fix (MEP) 4 days Mon 5/9/22 Thu 5/12/22

Page 6
KO-C1-PMA-CSH-SH-004_Schedule Recovery for Outstanding Works_2022.01.01
ID WBS Task Task Name Duration Start Finish Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022
Mode Dec Jan Feb Mar Apr May Jun Jul
233 1.4.2.3.5 Infill blockworks 14 days Thu 6/2/22 Fri 6/17/22
234 1.4.2.4 SECOND FLOOR WORKS 35 days Tue 5/17/22 Thu 6/23/22
235 1.4.2.4.1 Columns work 10 days Tue 5/17/22 Fri 5/27/22
236 1.4.2.4.2 Beams & Slabs works 10 days Tue 5/31/22 Fri 6/10/22
237 1.4.2.4.3 Neoprene Pads Installation works 2 days Fri 6/10/22 Sun 6/12/22
238 1.4.2.4.4 First fix (MEP) 4 days Thu 6/2/22 Mon 6/6/22
239 1.4.2.4.5 Infill blockworks 10 days Mon 6/13/22 Thu 6/23/22
240 1.4.3 ZONE C ‐ 3 149 days Thu 12/9/21 Wed 5/18/22
241 1.4.3.1 SUB‐STRUCTURE WORKS 73 days Thu 12/9/21 Fri 2/25/22
242 1.4.3.1.1 Excavation ( including stabilization works) 19 days Thu 12/9/21 Wed 12/29/21
243 1.4.3.1.2 Blinding works 11 days Mon 12/20/21 Fri 12/31/21
244 1.4.3.1.3 Formwork to foundation bases 10 days Mon 1/3/22 Thu 1/13/22
245 1.4.3.1.4 Steel reinforcement 8 days Sat 1/15/22 Mon 1/24/22
246 1.4.3.1.5 Foundation concrete 8 days Sat 1/22/22 Sun 1/30/22
247 1.4.3.1.6 Neck columns works 4 days Tue 2/1/22 Fri 2/4/22
248 1.4.3.1.7 Backfilling around foundation/ column & wall  4 days Thu 2/3/22 Mon 2/7/22
necks
249 1.4.3.1.8 Structual Backfilling works 10 days Thu 2/10/22 Mon 2/21/22
250 1.4.3.1.9 First fix (MEP) 24 days Fri 1/28/22 Wed 2/23/22
251 1.4.3.1.10 Tie beams works 4 days Wed 2/9/22 Sun 2/13/22
252 1.4.3.1.11 Slab on Grade works including Expansion joint  10 days Tue 2/15/22 Fri 2/25/22
fixing
253 1.4.3.2 GROUND FLOOR WORKS 67 days Mon 2/28/22 Tue 5/10/22
254 1.4.3.2.1 Columns & Wall works 10 days Mon 2/28/22 Thu 3/10/22
255 1.4.3.2.2 Beams & Slabs works 11 days Sat 3/12/22 Thu 3/24/22
256 1.4.3.2.3 First fix (MEP) 4 days Thu 3/17/22 Mon 3/21/22
257 1.4.3.2.4 Infill blockworks 19 days Wed 4/20/22 Tue 5/10/22
258 1.4.3.3 FIRST FLOOR WORKS 50 days Fri 3/25/22 Wed 5/18/22
259 1.4.3.3.1 Columns work 8 days Fri 3/25/22 Sun 4/3/22
260 1.4.3.3.2 Beams & Slabs works 8 days Mon 4/4/22 Tue 4/12/22
261 1.4.3.3.3 First fix (MEP) 4 days Tue 4/12/22 Fri 4/15/22
262 1.4.3.3.4 Infill blockworks 16 days Sun 5/1/22 Wed 5/18/22
263 1.4.4 EXTERNAL WORKS 89 days Mon 3/28/22 Fri 7/1/22
264 1.4.4.1 STAFF ACCOMODATION BUILDING 60.5 days Wed 4/20/22 Thu 6/23/22
265 1.4.4.1.1 Earthworks 2 days Wed 4/20/22 Thu 4/21/22
266 1.4.4.1.2 Setting out & Excavation works 4 days Thu 4/21/22 Mon 4/25/22
267 1.4.4.1.3 Substructure works 16 days Thu 4/21/22 Sun 5/8/22
268 1.4.4.1.3 Ground stabilization & Blinding works 2 days Sun 4/24/22 Tue 4/26/22
269 1.4.4.1.3 Foundation concrete works 10 days Thu 4/21/22 Sun 5/1/22
270 1.4.4.1.3 Sleeper walls works 6 days Tue 4/26/22 Mon 5/2/22

Page 7
KO-C1-PMA-CSH-SH-004_Schedule Recovery for Outstanding Works_2022.01.01
ID WBS Task Task Name Duration Start Finish Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022
Mode Dec Jan Feb Mar Apr May Jun Jul
271 1.4.4.1.3 Damp proof works 1 day Thu 5/5/22 Thu 5/5/22
272 1.4.4.1.3 Backfill & compaction works 1 day Sat 5/7/22 Sun 5/8/22
273 1.4.4.1.4 Superstructure 60.5 days Wed 4/20/22 Thu 6/23/22
274 1.4.4.1.4. GROUND FLOOR WORKS 35 days Mon 5/9/22 Wed 6/15/22
275 1.4.4.1.4 Ground beams works 8 days Mon 5/9/22 Tue 5/17/22
276 1.4.4.1.4 Oversite Concrete Slab works 8 days Fri 5/20/22 Sat 5/28/22
277 1.4.4.1.4 Columns works 8 days Wed 6/1/22 Thu 6/9/22
278 1.4.4.1.4 Beams & slabs works 10 days Sun 6/5/22 Wed 6/15/22
279 1.4.4.1.4 First fix works(MEP) 8 days Thu 5/5/22 Fri 5/13/22
280 1.4.4.1.4 Infill blockworks 12 days Mon 5/30/22 Sat 6/11/22
281 1.4.4.1.4.8 FIRST FLOOR WORKS 14 days Thu 6/9/22 Thu 6/23/22
282 1.4.4.1.4 Columns works 8 days Thu 6/9/22 Fri 6/17/22
283 1.4.4.1.4 Roof beams works 8 days Mon 6/13/22 Tue 6/21/22
284 1.4.4.1.4 Roofing works 12 days Fri 6/10/22 Thu 6/23/22
285 1.4.4.1.4 First fix works(MEP) 3 days Mon 6/13/22 Wed 6/15/22
286 1.4.4.1.4 Infill blockworks 10 days Tue 6/7/22 Fri 6/17/22
287 1.4.4.2 TECHNICAL BUILDINGS WORKS 89 days Mon 3/28/22 Fri 7/1/22
288 1.4.4.2.1 Earthworks(General) 2 days Mon 3/28/22 Tue 3/29/22
289 1.4.4.2.2 Setting out & Excavation works(General) 2 days Thu 3/31/22 Fri 4/1/22
290 1.4.4.2.3 ELECTRICAL PLANT ROOM WORKS 84 days Sat 4/2/22 Fri 7/1/22
291 1.4.4.2.3. Substructure works 30 days Sat 4/2/22 Wed 5/4/22
292 1.4.4.2.3 Ground stabilization & Blinding works 7 days Sat 4/2/22 Sat 4/9/22
293 1.4.4.2.3 Foundation concrete works 10 days Tue 4/12/22 Fri 4/22/22
294 1.4.4.2.3 Neck Columns & walls works 5 days Sat 4/23/22 Thu 4/28/22
295 1.4.4.2.3 Damp proof works 1 day Sun 5/1/22 Mon 5/2/22
296 1.4.4.2.3 Backfill & compaction works 1 day Tue 5/3/22 Wed 5/4/22
297 1.4.4.2.3. Superstructure 53 days Thu 5/5/22 Fri 7/1/22
298 1.4.4.2.3 Ground beams works 8 days Thu 5/5/22 Fri 5/13/22
299 1.4.4.2.3 First fix works(MEP) 4 days Thu 5/12/22 Mon 5/16/22
300 1.4.4.2.3 Oversite Concrete Slab works 10 days Thu 5/19/22 Mon 5/30/22
301 1.4.4.2.3 Columns & Walls works 9 days Tue 5/31/22 Thu 6/9/22
302 1.4.4.2.3 Damp proof works 1 day Sun 5/15/22 Mon 5/16/22
303 1.4.4.2.3 Roofing works 10 days Tue 6/14/22 Fri 6/24/22
304 1.4.4.2.3.2 Masonry works 10 days Tue 6/21/22 Fri 7/1/22
305 1.4.4.2.3. MEDICAL GAS PLANT WORKS 46 days Thu 5/5/22 Thu 6/23/22
306 1.4.4.2.3 Substructure works 21 days Thu 5/5/22 Fri 5/27/22
307 1.4.4.2.3 Ground stabilization & Blinding works 4 days Thu 5/5/22 Mon 5/9/22
308 1.4.4.2.3 Foundation concrete works 8 days Thu 5/12/22 Fri 5/20/22
309 1.4.4.2.3 Neck Columns & walls works 3 days Sat 5/21/22 Tue 5/24/22
310 1.4.4.2.3 Damp proof works 1 day Fri 5/27/22 Fri 5/27/22

Page 8
KO-C1-PMA-CSH-SH-004_Schedule Recovery for Outstanding Works_2022.01.01
ID WBS Task Task Name Duration Start Finish Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022
Mode Dec Jan Feb Mar Apr May Jun Jul
311 1.4.4.2.3 Backfill & compaction works 1 day Fri 5/27/22 Fri 5/27/22
312 1.4.4.2.3 Superstructure 43 days Mon 5/9/22 Thu 6/23/22
313 1.4.4.2.3 Ground beams works 5 days Mon 5/9/22 Fri 5/13/22
314 1.4.4.2.3 First fix works(MEP) 3 days Wed 5/11/22 Fri 5/13/22
315 1.4.4.2.3 Oversite Concrete Slab works 5 days Sun 5/15/22 Fri 5/20/22
316 1.4.4.2.3 Columns & Walls works 4 days Mon 5/23/22 Thu 5/26/22
317 1.4.4.2.3 Damp proof works 1 day Mon 5/23/22 Mon 5/23/22
318 1.4.4.2.3 Roofing works 10 days Mon 5/30/22 Thu 6/9/22
319 1.4.4.2.3 Masonry works 12 days Sat 6/11/22 Thu 6/23/22
320 1.4.4.2.3.4 WATER TANK AREA WORKS 52 days Fri 5/6/22 Fri 7/1/22
321 1.4.4.2.3 Substructure works 21 days Fri 5/6/22 Sun 5/29/22
322 1.4.4.2.3 Ground stabilization & Blinding works 3 days Fri 5/6/22 Mon 5/9/22
323 1.4.4.2.3 Foundation concrete works 8 days Thu 5/12/22 Fri 5/20/22
324 1.4.4.2.3 Neck Columns & walls works 3 days Sat 5/21/22 Tue 5/24/22
325 1.4.4.2.3 Damp proof works 1 day Sat 5/28/22 Sun 5/29/22
326 1.4.4.2.3 Backfill & compaction works 1 day Fri 5/27/22 Fri 5/27/22
327 1.4.4.2.3 Superstructure 34 days Thu 5/26/22 Fri 7/1/22
328 1.4.4.2.3 Ground beams works 7 days Thu 5/26/22 Thu 6/2/22
329 1.4.4.2.3 First fix works(MEP) 3 days Fri 6/3/22 Mon 6/6/22
330 1.4.4.2.3 Oversite Concrete Slab works 5 days Sat 6/4/22 Thu 6/9/22
331 1.4.4.2.3 Columns & Walls works 5 days Sat 6/11/22 Thu 6/16/22
332 1.4.4.2.3 Roofing works 9 days Fri 6/17/22 Mon 6/27/22
333 1.4.4.2.3 Damp proof works 1 day Wed 6/29/22 Thu 6/30/22
334 1.4.4.2.3 Masonry works 8 days Thu 6/23/22 Fri 7/1/22
335 1.4.4.2.3. SECURITY ROOMS WORKS 52 days Thu 5/5/22 Thu 6/30/22
336 1.4.4.2.3 Substructure works 25 days Thu 5/5/22 Wed 6/1/22
337 1.4.4.2.3 Ground stabilization & Blinding works 3 days Thu 5/5/22 Sun 5/8/22
338 1.4.4.2.3 Foundation concrete works 9 days Tue 5/10/22 Thu 5/19/22
339 1.4.4.2.3 Neck Columns & walls works 6 days Fri 5/20/22 Thu 5/26/22
340 1.4.4.2.3 Damp proof works 1 day Sun 5/29/22 Mon 5/30/22
341 1.4.4.2.3 Backfill & compaction works 1 day Tue 5/31/22 Wed 6/1/22
342 1.4.4.2.3 Superstructure 25 days Fri 6/3/22 Thu 6/30/22
343 1.4.4.2.3 Ground beams works 6 days Fri 6/3/22 Thu 6/9/22
344 1.4.4.2.3 First fix works(MEP) 3 days Sun 6/12/22 Wed 6/15/22
345 1.4.4.2.3 Oversite Concrete Slab works 8 days Mon 6/13/22 Tue 6/21/22
346 1.4.4.2.3 Columns  works 9 days Mon 6/20/22 Wed 6/29/22
347 1.4.4.2.3 Roofing works 9 days Tue 6/21/22 Thu 6/30/22
348 1.4.4.2.3 Masonry works 9 days Mon 6/20/22 Wed 6/29/22
349 1.4.4.2.3 OUTDOOR KITCHEN WORKS 53 days Thu 5/5/22 Fri 7/1/22
350 1.4.4.2.3 Substructure works 26 days Thu 5/5/22 Thu 6/2/22

Page 9
KO-C1-PMA-CSH-SH-004_Schedule Recovery for Outstanding Works_2022.01.01
ID WBS Task Task Name Duration Start Finish Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022
Mode Dec Jan Feb Mar Apr May Jun Jul
351 1.4.4.2.3 Ground stabilization&Blinding works 3 days Thu 5/5/22 Sun 5/8/22
352 1.4.4.2.3 Foundation concrete works 9 days Wed 5/11/22 Fri 5/20/22
353 1.4.4.2.3 Neck Columns&walls works 6 days Sat 5/21/22 Fri 5/27/22
354 1.4.4.2.3 Damp proof works 1 day Sun 5/29/22 Mon 5/30/22
355 1.4.4.2.3 Backfill&compaction works 1 day Wed 6/1/22 Thu 6/2/22
356 1.4.4.2.3 Superstructure 28 days Wed 6/1/22 Fri 7/1/22
357 1.4.4.2.3 Ground beams works 5 days Wed 6/1/22 Mon 6/6/22
358 1.4.4.2.3 First fix works(MEP) 3 days Sat 6/4/22 Tue 6/7/22
359 1.4.4.2.3 Oversite Concrete Slab works 7 days Thu 6/9/22 Thu 6/16/22
360 1.4.4.2.3 Columns works 9 days Sat 6/18/22 Tue 6/28/22
361 1.4.4.2.3 Roofing works 4 days Mon 6/27/22 Fri 7/1/22
362 1.4.4.2.3 Masonry works 7 days Thu 6/23/22 Thu 6/30/22
363 1.4.4.3 WASTEWATER TREATMENT AREA WORKS 49 days Sat 5/7/22 Tue 6/28/22
364 1.4.4.3.1 Substructure works 19 days Sat 5/7/22 Fri 5/27/22
365 1.4.4.3.1 Ground stabilization & Blinding works 3 days Sat 5/7/22 Tue 5/10/22
366 1.4.4.3.1 Foundation concrete works 6 days Wed 5/11/22 Tue 5/17/22
367 1.4.4.3.1 Neck Columns & walls works 5 days Mon 5/16/22 Fri 5/20/22
368 1.4.4.3.1 Damp proof works 1 day Tue 5/24/22 Wed 5/25/22
369 1.4.4.3.1 Backfill & compaction works 1 day Thu 5/26/22 Fri 5/27/22
370 1.4.4.3.2 Superstructure 28 days Mon 5/30/22 Tue 6/28/22
371 1.4.4.3.2 Ground beams works 7 days Mon 5/30/22 Mon 6/6/22
372 1.4.4.3.2 First fix works(MEP) 3 days Tue 6/7/22 Fri 6/10/22
373 1.4.4.3.2 Oversite Concrete Slab works 6 days Mon 6/13/22 Sun 6/19/22
374 1.4.4.3.2 Columns  works 7 days Tue 6/21/22 Tue 6/28/22
375 1.4.4.3.2 Roofing works 5 days Sun 6/19/22 Fri 6/24/22
376 1.4.4.3.2 Masonry works 5 days Wed 6/22/22 Mon 6/27/22
377 1.5 DECOMMISIONING 1.25 days Sat 7/2/22 Sun 7/3/22
378 1.5.1 Site Cleaning & Decommissioning 1 day Sat 7/2/22 Sun 7/3/22
379 1.5.2 Site Inspection & Handover 1 day Sat 7/2/22 Sun 7/3/22

Page 10