2022-08_PoW_Bonyokwa-rev00_KSM

ID WBS Task Name Start Finish Duration Predecessors


2023
4th Quarter 1st Quarter 2nd Quarter 3rd Quarter
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
1 1 Proposed Construction of Classroom Block for Mon Mon 318.33
Bonyokwa Secondary School at Dar es Salaam City 10/17/22 11/13/23 days
Council [Tender No.
LGA/018/DCC/2021/2022/BONYOKWA-SEC/W/01]

2 2 CONTRACT Mon 10/17/22


Wed 8/30/23318 days 0%
3 2.1 Commencement Date Mon 10/17/22Mon 10/17/221 day 0%
4 2.2 MOBILIZATION & ESTABLISHMENT Wed 10/19/22
Wed 8/30/23256 days 0%
5 2.2.1 Mobilisation Tools & Equipment Wed 10/19/22Fri 11/4/22 14 days 3FS+1 day 0%
6 2.2.2 Site hoarding Wed 10/19/22Fri 10/28/22 8 days 5SS 0%
7 2.2.3 Site Establishment Mon 10/24/22Fri 11/4/22 10 days 6SS+4 days 0%
8 2.2.4 Material Confirmation and Approval by Engineer Thu Wed 5 days 0%
- Rebars & Blocks 10/20/22 10/26/22
9 2.2.5 Demobilization Mon 8/28/23Wed 8/30/233 days 0%
10 2.3 SUBSTRUCTURE Tue 11/1/22 Mon 1/23/2367 days 0%
11 2.3.1 Earthworks Tue 11/1/22 Fri 12/23/22 43 days 0%
12 2.3.1.1 Setting out Tue 11/1/22 Fri 11/4/22 3 days 6FS+3 days 0%
13 2.3.1.2 Excavation of column pits Fri 11/4/22 Thu 11/17/2210 days 12 0%
14 2.3.1.3 Excavation of Rift Pit Thu 11/17/22Fri 11/18/22 1 day 13 0%
15 2.3.1.4 Excavation of Trenches Wed 11/30/22Mon 12/12/2210 days 39SS+5 days 0%
16 2.3.1.5 Backfilling & Compaction Tue 12/13/22Mon 12/19/225 days 45 0%
17 2.3.1.6 Disposal of excavated unsuitable materials Thu 12/22/22Fri 12/23/22 2 days 18FF 0%
18 2.3.2 Hardcore Filling Mon 12/19/22Fri 12/23/22 5 days 16FS-1 day 0%
19 2.3.3 Sand blinding to Hardcore bed Sat 12/24/22 Mon 12/26/221 day 18 0%
20 2.3.4 Ant-termite Treatment Mon 12/26/22Tue 12/27/221 day 19 0%
21 2.3.5 DPM Laying Mon 12/26/22Tue 12/27/221 day 20FF 0%
22 2.3.6 Concrete works Mon 11/7/22Thu 1/5/23 49 days 0%
23 2.3.6.1 Reinforcement work Mon 11/7/22Thu 12/29/2243 days 0%
24 2.3.6.1.1 Column base & starter columns Mon 11/7/22Mon 11/21/2212 days 13SS+1 day 0%
25 2.3.6.1.2 Beams and base slab Mon 12/26/22Thu 12/29/223 days 18FS+1 day 0%
26 2.3.6.1.3 Base & Starter Lift Walls Mon 11/21/22Wed 11/23/222 days 24FF+2 days 0%
27 2.3.6.2 Formwork Fri 11/11/22 Mon 1/2/23 42 days 0%
28 2.3.6.2.1 Footing Fri 11/11/22 Mon 11/28/2214 days 24SS+4 days 0%
29 2.3.6.2.2 Starter Columns Fri 11/18/22 Fri 12/9/22 17 days 37SS+2 days 0%
30 2.3.6.2.3 Ground Beams & Base Slab Fri 12/30/22 Mon 1/2/23 2 days 25FS+1 day 0%
31 2.3.6.2.4 Lift Starter walls Wed 12/7/22Fri 12/9/22 2 days 29FF 0%
32 2.3.6.3 C10 Concrete Fri 11/11/22 Tue 12/13/2226 days 0%
33 2.3.6.3.1 Blinding Column pits Fri 11/11/22 Fri 11/18/22 6 days 13SS+5 days 0%
34 2.3.6.3.2 Lift pit Sat 11/19/22 Mon 11/21/221 day 14FS+1 day 0%
35 2.3.6.3.3 Foundation Trenches Sat 12/3/22 Tue 12/13/228 days 15SS+3 days 0%
36 2.3.6.4 C25 Concrete Wed 11/16/22
Thu 1/5/23 41 days 0%
37 2.3.6.4.1 Column bases Wed 11/16/22Thu 12/8/22 18 days 28SS+4 days 0%
38 2.3.6.4.2 Lift wall base Thu 12/8/22 Fri 12/9/22 1 day 37FF+1 day 0%
39 2.3.6.4.3 Starter Columns Wed 11/23/22Sat 12/10/22 14 days 29SS+4 days 0%
40 2.3.6.4.4 Lift Starter walls Fri 12/9/22 Sat 12/10/22 1 day 39FF 0%
41 2.3.6.4.5 Ground Beams Wed 1/4/23 Thu 1/5/23 1 day 30FS+2 days 0%
42 2.3.6.4.6 Base Slab & Column kickers Wed 1/4/23 Thu 1/5/23 1 day 41FF 0%
43 2.3.7 Foundation Walling Mon 12/5/22Mon 1/23/2340 days 0%
44 2.3.7.1 DPC Laying Tue 1/17/23 Mon 1/23/235 days 65SS 0%
45 2.3.7.2 230mm Wall Mon 12/5/22Tue 12/13/227 days 39FF+2 days 0%
46 2.4 GROUND FLOOR Fri 1/6/23 Tue 3/21/23 59 days 0%
47 2.4.1 Reinforcement work Fri 1/6/23 Thu 2/9/23 27 days 0%
48 2.4.1.1 Columns Fri 1/6/23 Mon 1/16/237 days 42FS+1 day 0%
49 2.4.1.2 Lift walls Fri 1/13/23 Mon 1/16/232 days 48FF 0%
50 2.4.1.3 Beams Tue 1/31/23 Fri 2/3/23 4 days 56FF-8 days 0%
51 2.4.1.4 Suspended Slab Sat 2/4/23 Thu 2/9/23 4 days 50 0%
52 2.4.2 Formwork Wed 1/11/23Thu 3/16/23 53 days 0%
53 2.4.2.1 Vertical Sides of Columns Wed 1/11/23Thu 1/19/23 7 days 48SS+3 days 0%
54 2.4.2.2 Vertical Sides of Lift walls Tue 1/17/23 Thu 1/19/23 2 days 53FF 0%
55 2.4.2.3 Sides & Soffits of Beams Sat 1/21/23 Wed 1/25/233 days 59 0%
56 2.4.2.4 Sides & Soffits of Suspended Slab Thu 1/26/23 Tue 2/14/23 15 days 55FS+1 day 0%
57 2.4.2.5 Deshuttering of slab Wed 3/15/23Thu 3/16/23 2 days 62FS+21 days 0%
58 2.4.3 C25 Concrete Fri 1/13/23 Thu 2/16/23 28 days 0%
59 2.4.3.1 Columns Fri 1/13/23 Sat 1/21/23 7 days 53SS+2 days 0%
60 2.4.3.2 Lift walls Fri 1/20/23 Sat 1/21/23 1 day 59FF 0%
61 2.4.3.3 Beams Wed 2/15/23Thu 2/16/23 1 day 56FS+1 day 0%
62 2.4.3.4 Suspended Slab Wed 2/15/23Thu 2/16/23 1 day 61FF 0%
63 2.4.4 Walling Tue 1/17/23 Tue 3/21/23 51 days 0%
64 2.4.4.1 150mm walls Fri 3/17/23 Mon 3/20/232 days 57 0%
65 2.4.4.2 230mm Wall Tue 1/17/23 Tue 1/24/23 6 days 59SS+3 days 0%
66 2.4.4.3 Louver blocks Fri 3/17/23 Tue 3/21/23 3 days 64FF+1 day 0%
67 2.4.5 StairCase Tue 1/24/23 Thu 2/16/23 19 days 0%
68 2.4.5.1 First Flight Tue 1/24/23 Sat 1/28/23 4 days 0%
69 2.4.5.1.1 Formwork Tue 1/24/23 Fri 1/27/23 3 days 65 0%

Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone
Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary
Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline

Page 1
2022-08_PoW_Bonyokwa-rev00_KSM
ID WBS Task Name Start Finish Duration Predecessors
2023
4th Quarter 1st Quarter 2nd Quarter 3rd Quarter
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
70 2.4.5.1.2 Reinforcement work Wed 1/25/23Thu 1/26/23 1 day 69SS+1 day 0%
71 2.4.5.1.3 Concrete works Fri 1/27/23 Sat 1/28/23 1 day 69 0%
72 2.4.5.2 Second Flight Fri 2/10/23 Thu 2/16/23 5 days 0%
73 2.4.5.2.1 Formwork Fri 2/10/23 Tue 2/14/23 3 days 56FS-3 days 0%
74 2.4.5.2.2 Reinforcement work Sat 2/11/23 Mon 2/13/231 day 73SS+1 day 0%
75 2.4.5.2.3 Concrete works Wed 2/15/23Thu 2/16/23 1 day 62SS 0%
76 2.5 FIRST FLOOR Fri 2/17/23 Tue 5/2/23 59 days 0%
77 2.5.1 Reinforcement work Fri 2/17/23 Thu 3/23/23 27 days 0%
78 2.5.1.1 Columns Fri 2/17/23 Mon 2/27/237 days 62FS+1 day 0%
79 2.5.1.2 Lift walls Fri 2/24/23 Mon 2/27/232 days 78FF 0%
80 2.5.1.3 Beams Tue 3/14/23 Fri 3/17/23 4 days 86FF-8 days 0%
81 2.5.1.4 Suspended Slab Sat 3/18/23 Thu 3/23/23 4 days 80 0%
82 2.5.2 Formwork Wed 2/22/23Thu 4/27/23 53 days 0%
83 2.5.2.1 Vertical Sides of Columns Wed 2/22/23Wed 3/1/23 6 days 78SS+3 days 0%
84 2.5.2.2 Vertical Sides of Lift walls Mon 2/27/23Wed 3/1/23 2 days 83FF 0%
85 2.5.2.3 Sides & Soffits of Beams Sat 3/4/23 Wed 3/8/23 3 days 89 0%
86 2.5.2.4 Sides & Soffits of Suspended Slab Thu 3/9/23 Tue 3/28/23 15 days 85FS+1 day 0%
87 2.5.2.5 Deshuttering of slab Wed 4/26/23Thu 4/27/23 2 days 92FS+21 days 0%
88 2.5.3 C25 Concrete Fri 2/24/23 Thu 3/30/23 28 days 0%
89 2.5.3.1 Columns Fri 2/24/23 Sat 3/4/23 7 days 83SS+2 days 0%
90 2.5.3.2 Lift walls Fri 3/3/23 Sat 3/4/23 1 day 89FF 0%
91 2.5.3.3 Beams Wed 3/29/23Thu 3/30/23 1 day 86FS+1 day 0%
92 2.5.3.4 Suspended Slab Wed 3/29/23Thu 3/30/23 1 day 91FF 0%
93 2.5.4 Walling Tue 2/28/23 Tue 5/2/23 51 days 0%
94 2.5.4.1 150mm walls Fri 4/28/23 Mon 5/1/23 2 days 87 0%
95 2.5.4.2 230mm Wall Tue 2/28/23 Tue 3/7/23 6 days 89SS+3 days 0%
96 2.5.4.3 Louver blocks Fri 4/28/23 Tue 5/2/23 3 days 94FF+1 day 0%
97 2.5.5 StairCase Tue 3/7/23 Thu 3/30/23 19 days 0%
98 2.5.5.1 First Flight Tue 3/7/23 Sat 3/11/23 4 days 0%
99 2.5.5.1.1 Formwork Tue 3/7/23 Fri 3/10/23 3 days 95 0%
100 2.5.5.1.2 Reinforcement work Wed 3/8/23 Thu 3/9/23 1 day 99SS+1 day 0%
101 2.5.5.1.3 Concrete works Fri 3/10/23 Sat 3/11/23 1 day 99 0%
102 2.5.5.2 Second Flight Fri 3/24/23 Thu 3/30/23 5 days 0%
103 2.5.5.2.1 Formwork Fri 3/24/23 Tue 3/28/23 3 days 86FS-3 days 0%
104 2.5.5.2.2 Reinforcement work Sat 3/25/23 Mon 3/27/231 day 103SS+1 day 0%
105 2.5.5.2.3 Concrete works Wed 3/29/23Thu 3/30/23 1 day 92SS 0%
106 2.6 SECOND FLOOR Fri 3/31/23 Tue 6/13/23 59 days 0%
107 2.6.1 Reinforcement work Fri 3/31/23 Thu 5/4/23 27 days 0%
108 2.6.1.1 Columns Fri 3/31/23 Mon 4/10/237 days 92FS+1 day 0%
109 2.6.1.2 Lift walls Fri 4/7/23 Mon 4/10/232 days 108FF 0%
110 2.6.1.3 Beams Tue 4/25/23 Fri 4/28/23 4 days 116FF-8 days 0%
111 2.6.1.4 Suspended Slab Sat 4/29/23 Thu 5/4/23 4 days 110 0%
112 2.6.2 Formwork Wed 4/5/23 Thu 6/8/23 53 days 0%
113 2.6.2.1 Vertical Sides of Columns Wed 4/5/23 Wed 4/12/236 days 108SS+3 days 0%
114 2.6.2.2 Vertical Sides of Lift walls Mon 4/10/23Wed 4/12/232 days 113FF 0%
115 2.6.2.3 Sides & Soffits of Beams Sat 4/15/23 Wed 4/19/233 days 119 0%
116 2.6.2.4 Sides & Soffits of Suspended Slab Thu 4/20/23 Tue 5/9/23 15 days 115FS+1 day 0%
117 2.6.2.5 Deshuttering of slab Wed 6/7/23 Thu 6/8/23 2 days 122FS+21 days 0%
118 2.6.3 C25 Concrete Fri 4/7/23 Thu 5/11/23 28 days 0%
119 2.6.3.1 Columns Fri 4/7/23 Sat 4/15/23 7 days 113SS+2 days 0%
120 2.6.3.2 Lift walls Fri 4/14/23 Sat 4/15/23 1 day 119FF 0%
121 2.6.3.3 Beams Wed 5/10/23Thu 5/11/23 1 day 116FS+1 day 0%
122 2.6.3.4 Suspended Slab Wed 5/10/23Thu 5/11/23 1 day 121FF 0%
123 2.6.4 Walling Tue 4/11/23 Tue 6/13/23 51 days 0%
124 2.6.4.1 150mm walls Fri 6/9/23 Mon 6/12/232 days 117 0%
125 2.6.4.2 230mm Wall Tue 4/11/23 Mon 4/17/235 days 119SS+3 days 0%
126 2.6.4.3 Louver blocks Fri 6/9/23 Tue 6/13/23 3 days 124FF+1 day 0%
127 2.6.5 StairCase Mon 4/17/23Thu 5/11/23 20 days 0%
128 2.6.5.1 First Flight Mon 4/17/23Fri 4/21/23 4 days 0%
129 2.6.5.1.1 Formwork Mon 4/17/23Thu 4/20/23 3 days 125 0%
130 2.6.5.1.2 Reinforcement work Tue 4/18/23 Wed 4/19/231 day 129SS+1 day 0%
131 2.6.5.1.3 Concrete works Thu 4/20/23 Fri 4/21/23 1 day 129 0%
132 2.6.5.2 Second Flight Fri 5/5/23 Thu 5/11/23 5 days 0%
133 2.6.5.2.1 Formwork Fri 5/5/23 Tue 5/9/23 3 days 116FS-3 days 0%
134 2.6.5.2.2 Reinforcement work Sat 5/6/23 Mon 5/8/23 1 day 133SS+1 day 0%
135 2.6.5.2.3 Concrete works Wed 5/10/23Thu 5/11/23 1 day 122SS 0%
136 2.7 THIRD FLOOR Fri 5/12/23 Thu 8/3/23 67 days 0%
137 2.7.1 Reinforcement work Fri 5/12/23 Thu 6/15/23 27 days 0%
138 2.7.1.1 Columns Fri 5/12/23 Mon 5/22/237 days 122FS+1 day 0%
139 2.7.1.2 Lift walls Fri 5/19/23 Mon 5/22/232 days 138FF 0%
140 2.7.1.3 Beams Tue 6/6/23 Fri 6/9/23 4 days 146FF-8 days 0%
141 2.7.1.4 Suspended Slab Sat 6/10/23 Thu 6/15/23 4 days 140 0%

Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone
Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary
Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline

Page 2
2022-08_PoW_Bonyokwa-rev00_KSM
ID WBS Task Name Start Finish Duration Predecessors
2023
4th Quarter 1st Quarter 2nd Quarter 3rd Quarter
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
142 2.7.2 Formwork Wed 5/17/23Thu 7/20/23 53 days 0%
143 2.7.2.1 Vertical Sides of Columns Wed 5/17/23Wed 5/24/236 days 138SS+3 days 0%
144 2.7.2.2 Vertical Sides of Lift walls Mon 5/22/23Wed 5/24/232 days 143FF 0%
145 2.7.2.3 Sides & Soffits of Beams Sat 5/27/23 Wed 5/31/233 days 149 0%
146 2.7.2.4 Sides & Soffits of Suspended Slab Thu 6/1/23 Tue 6/20/23 15 days 145FS+1 day 0%
147 2.7.2.5 Deshuttering of slab Wed 7/19/23Thu 7/20/23 2 days 152FS+21 days 0%
148 2.7.3 C25 Concrete Fri 5/19/23 Thu 6/22/23 28 days 0%
149 2.7.3.1 Columns Fri 5/19/23 Sat 5/27/23 7 days 143SS+2 days 0%
150 2.7.3.2 Lift walls Fri 5/26/23 Sat 5/27/23 1 day 149FF 0%
151 2.7.3.3 Beams Wed 6/21/23Thu 6/22/23 1 day 146FS+1 day 0%
152 2.7.3.4 Suspended Slab Wed 6/21/23Thu 6/22/23 1 day 151FF 0%
153 2.7.4 Walling Tue 5/23/23 Tue 7/25/23 51 days 0%
154 2.7.4.1 150mm walls Fri 7/21/23 Mon 7/24/232 days 147 0%
155 2.7.4.2 230mm Wall Tue 5/23/23 Mon 5/29/235 days 149SS+3 days 0%
156 2.7.4.3 Louver blocks Fri 7/21/23 Tue 7/25/23 3 days 154FF+1 day 0%
157 2.7.5 StairCase Tue 7/11/23 Thu 8/3/23 19 days 0%
158 2.7.5.1 First Flight Tue 7/11/23 Sat 7/15/23 4 days 0%
159 2.7.5.1.1 Formwork Tue 7/11/23 Fri 7/14/23 3 days 155,185 0%
160 2.7.5.1.2 Reinforcement work Wed 7/12/23Thu 7/13/23 1 day 159SS+1 day 0%
161 2.7.5.1.3 Concrete works Fri 7/14/23 Sat 7/15/23 1 day 159 0%
162 2.7.5.2 Second Flight Fri 7/28/23 Thu 8/3/23 5 days 0%
163 2.7.5.2.1 Formwork Fri 7/28/23 Tue 8/1/23 3 days 146FS-3 days,176FS-3 days 0%
164 2.7.5.2.2 Reinforcement work Sat 7/29/23 Mon 7/31/231 day 163SS+1 day 0%
165 2.7.5.2.3 Concrete works Wed 8/2/23 Thu 8/3/23 1 day 152SS,182SS 0%
166 2.8 FORTH FLOOR Fri 6/23/23 Tue 8/22/23 48 days 0%
167 2.8.1 Reinforcement work Fri 6/23/23 Wed 7/26/2326 days 0%
168 2.8.1.1 Columns Fri 6/23/23 Mon 7/3/23 7 days 152FS+1 day 0%
169 2.8.1.2 Lift walls Fri 6/30/23 Mon 7/3/23 2 days 168FF 0%
170 2.8.1.3 Beams Tue 7/18/23 Fri 7/21/23 4 days 176FF-8 days 0%
171 2.8.1.4 Suspended Slab Sat 7/22/23 Wed 7/26/233 days 170 0%
172 2.8.2 Formwork Wed 6/28/23Tue 8/22/23 45 days 0%
173 2.8.2.1 Vertical Sides of Columns Wed 6/28/23Wed 7/5/23 6 days 168SS+3 days 0%
174 2.8.2.2 Vertical Sides of Lift walls Mon 7/3/23 Wed 7/5/23 2 days 173FF 0%
175 2.8.2.3 Sides & Soffits of Beams Sat 7/8/23 Wed 7/12/233 days 179 0%
176 2.8.2.4 Sides & Soffits of Suspended Slab Thu 7/13/23 Tue 8/1/23 15 days 175FS+1 day 0%
177 2.8.2.5 Deshuttering of slab Mon 8/21/23Tue 8/22/23 1 day 182FS+14 days 0%
178 2.8.3 C25 Concrete Fri 6/30/23 Thu 8/3/23 28 days 0%
179 2.8.3.1 Columns Fri 6/30/23 Sat 7/8/23 7 days 173SS+2 days 0%
180 2.8.3.2 Lift walls Fri 7/7/23 Sat 7/8/23 1 day 179FF 0%
181 2.8.3.3 Beams Wed 8/2/23 Thu 8/3/23 1 day 176FS+1 day 0%
182 2.8.3.4 Suspended Slabs Wed 8/2/23 Thu 8/3/23 1 day 181FF 0%
183 2.8.4 Walling Tue 7/4/23 Tue 8/1/23 23 days 0%
184 2.8.4.1 150mm walls Tue 7/11/23 Thu 7/13/23 2 days 179FS+2 days 0%
185 2.8.4.2 230mm Wall Tue 7/4/23 Tue 7/11/23 6 days 179SS+3 days 0%
186 2.8.4.3 Louver blocks Tue 7/11/23 Fri 7/14/23 3 days 184SS 0%
187 2.8.4.4 Roofing Thu 7/13/23 Tue 8/1/23 15 days 0%
188 2.8.4.4.1 Carpentry works Thu 7/13/23 Mon 7/24/238 days 185FS+2 days 0%
189 2.8.4.4.2 Roof covering Mon 7/24/23Fri 7/28/23 4 days 188 0%
190 2.8.4.4.3 Drainage Fri 7/28/23 Tue 8/1/23 3 days 189 0%
191 2.9 FINISHING WORKS Thu 2/9/23 Wed 8/30/23164 days 0%
192 2.9.1 Windows & Doors Tue 8/1/23 Mon 8/14/2310 days 0%
193 2.9.1.1 Carpentry works Tue 8/1/23 Mon 8/14/2310 days 190 0%
194 2.9.1.2 Metal Works Tue 8/1/23 Mon 8/14/2310 days 193SS 0%
195 2.9.2 Plumbing Thu 2/9/23 Wed 8/30/23164 days 0%
196 2.9.2.1 First Fix Thu 2/9/23 Sat 7/15/23 127 days 51 0%
197 2.9.2.2 Second Fix Sat 8/19/23 Wed 8/30/239 days 204FS+1 day 0%
198 2.9.3 Electrical Thu 2/9/23 Tue 8/29/23 163 days 0%
199 2.9.3.1 First Fix Thu 2/9/23 Sat 7/15/23 127 days 196SS 0%
200 2.9.3.2 Second Fix Tue 8/15/23 Tue 8/29/23 12 days 206FS+1 day 0%
201 2.9.4 Finishing Wed 6/14/23Fri 8/18/23 53 days 0%
202 2.9.4.1 Plastering & Rendering Wed 6/14/23Thu 7/27/23 35 days 124FS+2 days 0%
203 2.9.4.2 Floor Sceeding Fri 7/28/23 Tue 8/15/23 14 days 202FS+1 day 0%
204 2.9.4.3 Floor & Wall Tiles Mon 8/7/23 Fri 8/18/23 10 days 203FF+3 days 0%
205 2.9.5 Painting & Decoration Sat 7/29/23 Mon 8/28/2324 days 0%
206 2.9.5.1 Skimming Sat 7/29/23 Mon 8/14/2312 days 202FS+2 days 0%
207 2.9.5.2 Painting Tue 8/15/23 Mon 8/28/2311 days 206FS+1 day 0%
208 2.9.5.3 Balustrades Wed 8/16/23Mon 8/28/2310 days 203FS+1 day 0%

Critical Task Manual Task Duration-only Baseline Milestone Summary External Tasks Inactive Milestone
Critical Split Split Start-only Baseline Milestone Manual Summary External Milestone Inactive Summary
Critical Progress Task Progress Finish-only Baseline Split Summary Progress Project Summary Inactive Task Deadline