ID Task Task Name Duration

Start Finish
Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022
#. Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
1 1 Team No.1 262 Thu Sat 262 days
days 4/22/21 1/8/22 4/22 1/8
2 2 Initial dossier, site surveying and 71 Thu Thu 71 days
mobilization days 4/22/21 7/1/21 4/22 7/1
3 3 L641 115 Sat Mon 115 days
days 6/5/21 9/27/21 6/5 9/27
4 3.1 Excavation 11 Sat Tue 11 days
days 6/5/21 6/15/21 6/5 6/15
5 3.2 Existing concrete removal 5 Wed Sun 5 days
days 6/16/21 6/20/21 6/16 6/20
6 3.3 ROCKSHIELD Protect mesh 2 Mon Tue 2 days Team No.1
days 6/21/21 6/22/21 6/21 6/22
7 3.4 GEOTEXTILE TERRAM 2000 UV 5 Wed Sun 5 days
days 6/23/21 6/27/21 6/23 6/27
8 3.5 Gabion Boxes 19 Mon Fri 19 days
days 6/28/21 7/16/21 6/28 7/16
9 3.6 Reinforced Concrete material including 4 Sat Tue 4 days
Form works with strength of (C25/30) and days 7/17/21 7/20/21 7/17 7/20
streel grade to be R420.
10 3.7 Filling materials, Graded compacted soil, 9 Wed Thu 9 days
Granular Backfill, MAX particle size < days 7/21/21 7/29/21 7/21 7/29
50mm
11 3.8 Capping stabilized with 300mm compacted 19 Fri Tue 19 days
gatch materials approved by company days 7/30/21 8/17/21 7/30 8/17

12 3.9 RIP-RAP, D = 750mm. 23 Wed Thu 23 days


days 8/18/21 9/9/21 8/18 9/9

Task Inactive Summary External Tasks


Split Manual Task External Milestone
Milestone Duration-only Deadline
Project: Rect. of 38 RoW Geo. Defects
Date: Wed 6/9/21 Summary Manual Summary Rollup Progress
Project Summary Manual Summary Manual Progress
Inactive Task Start-only
Inactive Milestone Finish-only

Page 1
ID Task Task Name Duration
Start Finish
Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022
#. Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
13 3.10 RIP-RAP, D = 900mm. 18 Fri Mon 18 days
days 9/10/21 9/27/21 9/10 9/27
14 4 L407 7 Tue Mon 7 days
days 9/28/21 10/4/21 9/28 10/4
15 4.1 Re-slope and scaling including Fillings if 6 Tue Sun 6 days
necessary days 9/28/21 10/3/21 9/28 10/3
16 4.2 DOC has to be checked along the whole 1 day Mon Mon 1 day
defect site with rockfall above the pipeline 10/4/21 10/4/21 10/4 10/4
using GPR
17 5 L408 7 Tue Mon 7 days
days 10/5/21 10/11/21 10/5 10/11
18 5.1 Re-slope and scaling including Fillings if 6 Tue Sun 6 days
necessary days 10/5/21 10/10/21 10/5 10/10
19 5.2 DOC has to be checked along the whole 1 day Mon Mon 1 day
defect site with rockfall above the pipeline 10/11/21 10/11/21 10/11 10/11
using GPR
20 6 L409 & L410 8 Tue Tue 8 days
days 10/12/21 10/19/21 10/12 10/19
21 6.1 Re-slope and scaling including Fillings if 7 Tue Mon 7 days
necessary days 10/12/21 10/18/21 10/12 10/18
22 6.2 DOC has to be checked along the whole 1 day Tue Tue 1 day
defect site with rockfall above the pipeline 10/19/21 10/19/21 10/19 10/19
using GPR
23 7 U3 20 Wed Mon 20 days
days 10/20/21 11/8/21 10/20 11/8
24 7.1 GEOTEXTILE TERRAM 2000 UV 3 Wed Fri 3 days
days 10/20/21 10/22/21 10/20 10/22

Task Inactive Summary External Tasks


Split Manual Task External Milestone
Milestone Duration-only Deadline
Project: Rect. of 38 RoW Geo. Defects
Date: Wed 6/9/21 Summary Manual Summary Rollup Progress
Project Summary Manual Summary Manual Progress
Inactive Task Start-only
Inactive Milestone Finish-only

Page 2
ID Task Task Name Duration
Start Finish
Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022
#. Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
25 7.2 RIP-RAP, D = 750mm. 17 Sat Mon 17 days
days 10/23/21 11/8/21 10/23 11/8
26 8 L644 19 Tue Sat 19 days
days 11/9/21 11/27/21 11/9 11/27
27 8.1 Excavation 3 Tue Thu 3 days
days 11/9/21 11/11/21 11/9 11/11
28 8.2 Existing concrete removal 1 day Fri Fri 1 day
11/12/21 11/12/21 11/12 11/12
29 8.3 ROCKSHIELD Protect mesh 1 day Sat Sat 1 day
11/13/21 11/13/21 11/13 11/13
30 8.4 GEOTEXTILE TERRAM 2000 UV 1 day Sun Sun 1 day
11/14/21 11/14/21 11/14 11/14
31 8.5 Gabion Boxes 9 Mon Tue 9 days
days 11/15/21 11/23/21 11/15 11/23
32 8.6 Reinforced Concrete material including 1 day Wed Wed 1 day
Form works with strength of (C25/30) and 11/24/21 11/24/21 11/24 11/24
streel grade to be R420.
33 8.7 1 Filling materials, Graded compacted soil, 1 day Thu Thu 1 day
Granular Backfill, MAX particle size < 11/25/21 11/25/21 11/25 11/25
50mm
34 8.8 RIP-RAP, D = 600mm. 2 Fri Sat 2 days
days 11/26/21 11/27/21 11/26 11/27
35 9 L645 19 Sun Thu 19 days
days 11/28/21 12/16/21 11/28 12/16
36 9.1 Excavation 3 Sun Tue 3 days
days 11/28/21 11/30/21 11/28 11/30

Task Inactive Summary External Tasks


Split Manual Task External Milestone
Milestone Duration-only Deadline
Project: Rect. of 38 RoW Geo. Defects
Date: Wed 6/9/21 Summary Manual Summary Rollup Progress
Project Summary Manual Summary Manual Progress
Inactive Task Start-only
Inactive Milestone Finish-only

Page 3
ID Task Task Name Duration
Start Finish
Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022
#. Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
37 9.2 Existing concrete removal 1 day Wed Wed 1 day
12/1/21 12/1/21 12/1 12/1
38 9.3 ROCKSHIELD Protect mesh 1 day Thu Thu 1 day
12/2/21 12/2/21 12/2 12/2
39 9.4 GEOTEXTILE TERRAM 2000 UV 1 day Fri Fri 1 day
12/3/21 12/3/21 12/3 12/3
40 9.5 Gabion Boxes 9 Sat Sun 9 days
days 12/4/21 12/12/21 12/4 12/12
41 9.6 Reinforced Concrete material including 1 day Mon Mon 1 day
Form works with strength of (C25/30) and 12/13/21 12/13/21 12/13 12/13
streel grade to be R420.
42 9.7 Filling materials, Graded compacted soil, 1 day Tue Tue 1 day
Granular Backfill, MAX particle size < 12/14/21 12/14/21 12/14 12/14
50mm
43 9.8 RIP-RAP, D = 600mm. 1 day Wed Wed 1 day
12/15/21 12/15/21 12/15 12/15
44 9.9 RIP-RAP, D = 750mm. 1 day Thu Thu 1 day
12/16/21 12/16/21 12/16 12/16
45 10 Final Dossier 30 Fri Sat 30 days
days 12/10/21 1/8/22 12/10 1/8

Task Inactive Summary External Tasks


Split Manual Task External Milestone
Milestone Duration-only Deadline
Project: Rect. of 38 RoW Geo. Defects
Date: Wed 6/9/21 Summary Manual Summary Rollup Progress
Project Summary Manual Summary Manual Progress
Inactive Task Start-only
Inactive Milestone Finish-only