ID Task Task Name Duration Start Finish Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023

Mode Jan Feb Mar Apr May Jun Jul Aug Sep
1 Rubble Wall Construction 186 days Thu 09/02/23Sun 13/08/23
2 Procurement 31 days Thu 09/02/23Sat 11/03/23
3 Setting Out 31 days Mon 13/03/23Wed 12/04/23
4 Excavation/ Rock hacking 90 days Mon 27/03/23Sat 24/06/23
5 Laying and compacting 90 days Mon Sat 01/07/23
crusher run 03/04/23
6 Lean concrete 90 days Mon 10/04/23Sat 08/07/23
7 Rebar Installation 90 days Thu 20/04/23Tue 18/07/23
8 Concrete Base Grade 90 days Thu 27/04/23Tue 25/07/23
9 Stone Block 90 days Thu 04/05/23Tue 01/08/23
10 Backfilling 95 days Thu 11/05/23Sun 13/08/23

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Rubber Wall Constructi
Summary Manual Summary Rollup Progress
Date: Thu 09/02/23
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only