ID Task Task Name Duration Start July 2023 Finish Predecessors

Mode 19 21 23 25 27 29 31
1 Environment and Social Managament 5 days Wed 11/1/23 Sun 11/5/23
2 Moblisation 2 days Thu 11/2/23 Fri 11/3/23
3 Emplying of labors 5 days Thu 11/2/23 Mon 11/6/23
4 Excavation of Sub Grade 25 days Sat 11/4/23 Tue 11/28/23
5 Excavation of Drain 10 days Wed 11/15/23Fri 11/24/23
6 Subgrade Prepration for bed of drain 5 days Mon 11/20/23Fri 11/24/23
7 Filling of Crushed for Bed of Drain 2 days Wed 11/22/23Thu 11/23/23
8 Filling for subgrade 15 days Thu 11/16/23 Thu 11/30/23
9 Filling for subbase 15 days Mon 11/20/23Mon 12/4/23
10 prepration to plume concrete 5 days Sat 11/25/23 Wed 11/29/23
11 Concete of Bed drain 4 days Tue 11/28/23 Fri 12/1/23
12 Plume Concrete with wall drain Concrete 28 days Wed 11/15/23Tue 12/12/23
13 Curring of Concrete
14 Site prepration 2 days Wed 12/13/23Thu 12/14/23
15 Steel Grilles 3 days Thu 12/14/23 Sat 12/16/23
16 Demoblisation 1 day Sun 12/17/23 Sun 12/17/23

Tamim Matin Road and Construction Company

Work Plan of Jadah-e-Mehri 1009631

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Work Plan for Mehri
Summary Manual Summary Rollup Progress
Date: Mon 10/23/23
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
August 2023 September 2024 October 2024
31 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 1 3 5 7 9 11

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Work Plan for Mehri
Summary Manual Summary Rollup Progress
Date: Mon 10/23/23
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2
November 2024 December 2024
11 13 15 17 19 21 23 25 27 29 31 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 2 4 6 8 10 12 14 16 18 20 22

Tamim Matin Road and Construction Company

Work Plan of Jadah-e-Mehri 1009631

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Work Plan for Mehri
Summary Manual Summary Rollup Progress
Date: Mon 10/23/23
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only