HORIZON 7LTD PROJECT PLANNING DEEPRIVERS

ID Task Task Name Duration Start Finish % Complete Jan 24, '21 Jan 31, '21 Feb 7, '21 Feb 14, '21 Feb 21, '21
Mode S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
1 FABRICATION OF 22M LONG REACH BOOM/ARM FOR CAT345BL 21 days Mon 1/25/21 Mon 2/22/21 65%
2 Preliminary 1 day Mon 1/25/21 Mon 1/25/21 98%
3 - Engineering studies and Production of shop drawings 1 day Mon 1/25/21 Mon 1/25/21 100%
4 - Material Purchases 1 day Mon 1/25/21 Mon 1/25/21 95%
5 Prefabrication in the Workshop 16 days Tue 1/26/21 Tue 2/16/21 77%
6 - Cutting of assorted pieces from design 8 days Tue 1/26/21 Thu 2/4/21 100%
7 - Welding and assembling of structure 5 days Fri 2/5/21 Thu 2/11/21 80%
8 - Sandblasting and Priming of Prefabricated profiles 2 days Fri 2/12/21 Mon 2/15/21 15%
9 - Mobilization to site for installation 1 day Tue 2/16/21 Tue 2/16/21 0%
10 Installation on site 3 days Wed 2/17/21 Fri 2/19/21 0%
11 - Mounting of Boom/Arm on the Catapiller 345 engine. 3 days Wed 2/17/21 Fri 2/19/21 0%
12 Demobilization from site 1 day Mon 2/22/21 Mon 2/22/21 0%
13 - Housekeeping and Transportation of equipment from site 1 day Mon 2/22/21 Mon 2/22/21 0%

We presently on mechanical fittings on articulation points. We mount progressively as the internal surface is blasted and painted.

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: Project Planning Split External Tasks Inactive Summary Manual Summary Progress
Date: Wed 2/10/21 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

By ASONGWE HANS Page 1