This document outlines 14 tasks for a project with their durations, start and finish dates, predecessors and assigned resources. The frontend task involving the login, register and forgot password pages is 39% complete and expected to finish on February 11th. The backend task involving APIs for login, register and forgot password is 85% complete and expected to finish on February 5th. Inputting data and creating visualizations are also tasks that are 80% and 100% complete respectively.
This document outlines 14 tasks for a project with their durations, start and finish dates, predecessors and assigned resources. The frontend task involving the login, register and forgot password pages is 39% complete and expected to finish on February 11th. The backend task involving APIs for login, register and forgot password is 85% complete and expected to finish on February 5th. Inputting data and creating visualizations are also tasks that are 80% and 100% complete respectively.
This document outlines 14 tasks for a project with their durations, start and finish dates, predecessors and assigned resources. The frontend task involving the login, register and forgot password pages is 39% complete and expected to finish on February 11th. The backend task involving APIs for login, register and forgot password is 85% complete and expected to finish on February 5th. Inputting data and creating visualizations are also tasks that are 80% and 100% complete respectively.
ID Task Task Name Duration Start Finish Predecessors Resource Names % Complete
24 Jan '21 31 Jan '21 7 Feb '21
Mode S S M T W T F S S M T W T F S 1 Frontend 8.35 days Mon 1/2/21 Thu 11/2/21 Luqman 39% 2 Login page 1 day Mon 1/2/21 Mon 1/2/21 6 100% 3 Register page 1 day Tue 2/2/21 Tue 2/2/21 7 100% 4 Forgot password 4.6 days Wed 3/2/21 Thu 11/2/21 8 13% 5 Backend 5 days Mon 1/2/21 Fri 5/2/21 Fauzi 85% 6 API login 2 days Mon 1/2/21 Tue 2/2/21 100% 7 API resgister 1 day Wed 3/2/21 Wed 3/2/21 100% 8 API forgot password2 days Wed 3/2/21 Fri 5/2/21 63% 9 Input data 4 days Mon 8/2/21 Thu 11/2/21 Miza 80% 10 Ears Sabah 1 day Mon 8/2/21 Mon 8/2/21 60% 11 Isu tempatan 1 day Tue 9/2/21 Tue 9/2/21 100% 12 Visualization 2 days Mon 1/2/21 Tue 2/2/21 Pezri 100% 13 Isu tempatan 1 day Mon 1/2/21 Mon 1/2/21 100% 14 Ears Sabah 1 day Mon 1/2/21 Mon 1/2/21 100%