ID Task Task Name Duration Start Finish Predecessors Resource Names % Complete

24 Jan '21 31 Jan '21 7 Feb '21


Mode S S M T W T F S S M T W T F S
1 Frontend 8.35 days Mon 1/2/21 Thu 11/2/21 Luqman 39%
2 Login page 1 day Mon 1/2/21 Mon 1/2/21 6 100%
3 Register page 1 day Tue 2/2/21 Tue 2/2/21 7 100%
4 Forgot password 4.6 days Wed 3/2/21 Thu 11/2/21 8 13%
5 Backend 5 days Mon 1/2/21 Fri 5/2/21 Fauzi 85%
6 API login 2 days Mon 1/2/21 Tue 2/2/21 100%
7 API resgister 1 day Wed 3/2/21 Wed 3/2/21 100%
8 API forgot password2 days Wed 3/2/21 Fri 5/2/21 63%
9 Input data 4 days Mon 8/2/21 Thu 11/2/21 Miza 80%
10 Ears Sabah 1 day Mon 8/2/21 Mon 8/2/21 60%
11 Isu tempatan 1 day Tue 9/2/21 Tue 9/2/21 100%
12 Visualization 2 days Mon 1/2/21 Tue 2/2/21 Pezri 100%
13 Isu tempatan 1 day Mon 1/2/21 Mon 1/2/21 100%
14 Ears Sabah 1 day Mon 1/2/21 Mon 1/2/21 100%

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: ProjectTest
Summary Manual Summary Rollup Progress
Date: Tue 9/3/21
Project Summary Manual Summary Manual Progress