ID Task Task Name Duration Start Finish Oct 18, '22 Nov 15, '22 Dec 13, '22

Mode M F T S W S T M F
1 1 Analisa dan Desain Sistem 24 days Fri 10/1/21 Sun 10/24/21
2 1.1 Menganalisis Sistem Kasir Minimarket Dengan 2 days Fri 10/1/21 Sat 10/2/21 Reyka Shelia Mardyana
Melakukan Observasi
3 1.2 Membuat Statement Of Purpose, Event, List dan Unified 2 days Sun 10/3/21 Mon 10/4/21 Reyka Shelia Mardyana
Modelling Language (UML)
4 1.3 Membuat Use Case Diagram 5 days Tue 10/5/21 Sat 10/9/21 Reyka Shelia Mardyana
5 1.4 Membuat Activity Diagram 5 days Sun 10/10/21 Thu 10/14/21 Reyka Shelia Mardyana
6 1.5 Membuat Sequence Diagram 5 days Fri 10/15/21 Tue 10/19/21 Reyka Shelia Mardyana
7 1.6 Membuat Class Diagram 5 days Wed 10/20/21 Sun 10/24/21 Reyka Shelia Mardyana
8 1.7 Dokumentasi Analisa dan Desain Sistem 20 days Tue 10/5/21 Sun 10/24/21
9 2 Desain Aplikasi 14 days Mon 10/25/21Sun 11/7/21
10 2.1 Membuat Desain Database 7 days Mon 10/25/21 Sun 10/31/21 Tasya Marzuqah
11 2.2 Membuat Desain Interface 7 days Mon 11/1/21 Sun 11/7/21 Tasya Marzuqah
12 2.3 Dokumentasi Desain Aplikasi 14 days Mon 10/25/21 Sun 11/7/21
13 3 Programming 50 days Mon 11/8/21 Mon 12/27/21
14 3.1 Programming (Back End & Front End) 50 days Mon 11/8/21 Mon 12/27/21 Dyana Rachma
15 3.2 Dokumentasi Program (Front End & Back End) 50 days Mon 11/8/21 Mon 12/27/21
16 4 Testing Program 4 days Tue 12/28/21Fri 12/31/21
17 4.1 Melakukan test terhadap program 1 day Tue 12/28/21 Tue 12/28/21 Muhammad
18 4.2 Memberikan catatan list perbaikan 3 days Wed 12/29/21 Fri 12/31/21 Ilham Ak
19 4.3 Dokumentasi Testing Program 4 days Tue 12/28/21 Fri 12/31/21
20 5 Dokumentasi 92 days Fri 10/1/21 Fri 12/31/21
21 5.1 Pembuatan Laporan Akhir 92 days Fri 10/1/21 Fri 12/31/21

Task Project Summary Manual Task Start-only Deadline

Project: KELOMPOK 4 ITAPP-W Split Inactive Task Duration-only Finish-only Progress

Date: Thu 9/30/21 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1
Jan 10, '22 Feb 7, '22 Mar 7, '22 Apr 4, '22 May 2, '22 May 30, '22 Jun 27, '22
F T S W S T M F T S W S T M F T S W

Dyana Rachmawati

Muhammad Fadli
Ilham Akbarudin

Task Project Summary Manual Task Start-only Deadline

Project: KELOMPOK 4 ITAPP-W Split Inactive Task Duration-only Finish-only Progress

Date: Thu 9/30/21 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 2

You might also like