ID Task 

Name Duration Start Finish Feb '21 Mar '21 Apr '21 May '21 Jun '21 Jul '2
01 08 15 22 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 05 12
1 Unit Control Panel of Bleed Water  110 days Mon 08/02/21 Fri 09/07/21
Treatment Plant
2 Start 0 days Mon 08/02/21 Mon 08/02/21 08/02
3 Engineering 18 days Wed 17/03/21 Fri 09/04/21
4 I/O List & I/O Arrangement Final 2 days Wed 17/03/21 Thu 18/03/21
5 Drawing Revision (GA Drawing,  5 days Fri 19/03/21 Thu 25/03/21
Wiring Diagram)
langkah-langkah fabrikasi
6 Approval Drawing 11 days Fri 26/03/21 Fri 09/04/21 1. mall material
7 Procurement 45 days Mon 05/04/21 Fri 04/06/21 2. pasang part2nya
3. pasang kabel2nya
8 Enclosure panel (ready stock) 15 days Mon 05/04/21 Fri 23/04/21 ini sampe di weeks 2 juni
9 Accessories panel 45 days Mon 05/04/21 Fri 04/06/21
14 juni 2021 mulai internal FAT
10 Fabrication 55 days Mon 12/04/21 Fri 25/06/21 internal FAT untuk hardware 1 minggu
11 Wiring Panel 55 days Mon 12/04/21 Fri 25/06/21
target dari EMI untuk melakukan percepatan agar
12 Internal Test 10 days Mon 28/06/21 Fri 09/07/21 14 juni sudah mulai FAT internal hardware transavia
13 Internal FAT (Panel only) 10 days Mon 28/06/21 Fri 09/07/21 Transavia akan menginformasikan mitigasi untuk
mempercepat schedule 09/07
14 Finish 0 days Fri 09/07/21 Fri 09/07/21

Transavia akan update indent item bisa sampai


di workshop kapan

target instalasi seluruh item yg sudah ada sebelum lebaran.


saat ini sudah terpasang 50%

email atau statement letter terkait perbedaan delivery time yg di


unpriced PO dan actualnya, ini lama nya karna apa

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: Project Schedule rev Split External Tasks Inactive Summary Manual Summary Baseline


Date: Tue 30/03/21 Milestone External Milestone Manual Task Start‐only Progress
Summary Inactive Task Duration‐only Finish‐only

Page 1
Jul '21 Aug '21 Sep '21 Oct '21 Nov '21 Dec '21 Jan '22 Feb '22 Mar '22
12 19 26 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 07 14 2

09/07

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: Project Schedule rev Split External Tasks Inactive Summary Manual Summary Baseline


Date: Tue 30/03/21 Milestone External Milestone Manual Task Start‐only Progress
Summary Inactive Task Duration‐only Finish‐only

Page 2